Maine Public Utilities Commission v. Federal Energy Regulatory Commission
Opinion of the Court
The consolidated petitions for review challenge FERC’s approval of a comprehensive settlement that redesigned New England’s capacity market. The Maine Public Utilities Commission and the Attorneys General of Connecticut and Massachusetts assert that FERC’s approval of the settlement was arbitrary and capricious, contrary to law, and beyond the Commission’s jurisdiction. We reject most of these arguments, but we agree with the petitioners that the Commission has unlawfully deprived non-settling parties of their rights under the Federal Power Act.
I.
In a “capacity” market — as opposed to a wholesale electricity market — “the [transmission provider] compensates the generator for the option of buying a specified quantity of power irrespective of whether it ultimately buys the electricity.”
For many years, New England’s capacity market has been rife with problems. As the Commission explained in 2003, “existing generators needed for reliability are not earning sufficient revenues (and are in fact losing money), and [ ] additional infrastructure is needed soon to avoid violations of reliability criteria.” Devon Power LLC, 115 FERC ¶ 61,340 at 62,315 (2006). In other words, the supply of capacity was barely sufficient to meet the region’s demand.
FERC, the generators, the transmission providers, and the power customers have made several attempts to address these issues. In 2003, a group of generators sought to enter into “Reliability Must-Run” agreements with the New England Independent System Operator (“ISO”),
[Must-Run] contracts suppress market-clearing prices, increase uplift payments, and make it difficult for new generators to profitably enter the market.... [Expensive generators under [Must-Run] contracts receive greater revenues than new entrants, who would receive lower revenues from the suppressed spot market price. In short, extensive use of [those] contracts undermines efficient market performance.
Devon Power LLC, 103 FERC ¶ 61,082 at 61,270 (2003). For these reasons, FERC accepted the MusNRun agreements filed by the New England generators, but only allowed these generators to recover certain maintenance costs, not their full cost-of-service. Id. at 61,270-71.
In its orders addressing the Must-Run agreements, the Commission simultaneously directed the ISO to develop a new market mechanism that would include a location requirement. Id. at 61,271. In a locational market, prices are set separately for various geographical sub-regions. Thus, prices would be highest in the regions with the most severe capacity shortages, which would encourage new entry.
In response to FERC’s directive, the ISO proposed a locational capacity market structure in March 2004. This proposed market mechanism included four sub-regions, each of which would have a monthly auction for capacity. The auctions would be based on an “administratively-determined demand curve” that would establish the price and quantity of capacity that must be procured within each sub-region.
In June 2005, the ALJ issued a 177-page order that largely accepted the ISO’s proposed demand curve. Devon Power LLC, 111 FERC ¶ 63,063 (2005). Several parties filed exceptions to this decision, arguing that the ALJ wrongfully excluded evidence and failed to respond to comments about flaws in the ISO’s demand curve. On September 20, 2005, the full Commission held an all-day oral argument on the locational market structure and the proposed demand curve. FERC subsequently established settlement procedures to allow the parties to develop a new market mechanism.
After four months of negotiations involving 115 parties, a settlement was reached. As FERC has repeatedly reminded us, only eight of these parties opposed the final settlement. 115 FERC at 62,306. The key feature of the settlement agreement is the Forward Capacity Market, which would replace the ISO’s earlier proposal and eliminate the need for the controversial demand curve. Under the Forward Market, there will be annual auctions for capacity, which will be held three years in advance of when the capacity is needed. Id. The settling parties determined that a three-year lead time will “provide for a planning period for new entry and allow potential new capacity to compete in the auctions.” Id. Each transmission provider will be required to purchase enough capacity to satisfy its “installed capacity requirement,” which is the minimum level of capacity that is necessary to maintain reliability on the grid. Id. at 62,307. As FERC requested, the Forward Market also includes a locational component — the annual auctions will be held in different “capacity zones” based on transmission constraints between the various sub-regions within New England. Id.
The most contentious issue regarding the Forward Market is the set of “transition payments” that will be required from December 1, 2006 until June 1, 2010. As explained above, the Forward Market provides for a three-year lead time in the capacity auctions, in order to allow new entrants to bid in the auctions. However, this leaves a three-year gap between the first auction and the time when the capacity procured in this auction will be provided. The parties addressed this issue by negotiating a series of fixed payments that will be paid to generators during the transition period. 115 FERC at 62,308. The agreement also provides that challenges to the transition payments and the final Forward Market auction clearing prices — regardless of whether the challenge is brought by a settling party, a non-settling party, or the Commission — will be adjudicated under the highly-deferential “public interest” standard rather than the usual “just and reasonable” standard. Id. at 62,332-33.
On June 16, 2006, FERC approved the settlement agreement, finding that “as a package, it presents a just and reasonable outcome for this proceeding consistent with the public interest.” Id. at 62,304. Most importantly, the Commission determined that the settlement would address the problems that had plagued New England’s capacity market:
The settlement package, including both the [Forward Market] and the interim transition mechanism, resolves the issues raised in this proceeding concerning the under-compensation of capacity resources in New England, and provides the appropriate market structure to ensure that generating resources are appropriately compensated based on their location and contribution to system reliability and provides incentives to attract new infrastructure where needed.
After FERC denied rehearing, the Maine Public Utilities Commission and the Attorneys General of Connecticut and Massachusetts petitioned for review, arguing that the Commission’s approval of the settlement was arbitrary and capricious, contrary to law, and beyond the scope of FERC’s jurisdiction.
II.
The petitioners argue that FERC’s approval of the settlement’s transition payments was arbitrary and capricious, in violation of the Administrative Procedure Act, 5 U.S.C. § 706(2)(A). To withstand review under that standard, FERC must have “examine[d] the relevant data and articulate[d] a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made.’ ” Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983) (quoting Burlington Truck Lines, Inc. v. United States, 371 U.S. 156, 168, 83 S.Ct. 239, 9 L.Ed.2d 207 (1962)). The Commission’s findings of fact, “if supported by substantial evidence,” are conclusive. 16 U.S.C. § 8251(b). When the record would support more than one outcome, we must uphold FERC’s order because “[t]he question we must answer ... is not whether record evidence supports [the petitioner’s desired outcome], but whether it supports FERC’s.” Fla. Mun. Power Agency v. FERC, 315 F.3d 362, 368 (D.C.Cir. 2003). See generally NorAm Gas Transmission Co. v. FERC, 148 F.3d 1158, 1162 (D.C.Cir. 1998) (“[I]n reviewing the Commission’s approval of a contested settlement, we must determine whether the Commission has supplied a ‘reasoned decision’ that is supported by ‘substantial evidence.’ ” (quoting 18 C.F.R. § 385.602(h)(1)(i))).
In this case, after considering the merits of the settlement as a whole, FERC
In challenging FERC’s decision to approve the transition payments, the petitioners argue that there was no record evidence of existing generators’ costs and that without such evidence FERC could not find that the payments fell within a reasonable range of capacity prices. In its early orders in Devon Power, however, FERC determined that reliance on individualized cost recovery proceedings was not a policy in the public interest and that, instead, capacity payments should be made to all suppliers with a single market-clearing price. See, e.g., Devon Power LLC, 110 FERC ¶ 61,315 at 62,227 (2005). FERC is correct that it need not rely on generators’ costs to determine rates. The Supreme Court has disavowed the notion that rates must depend on historical costs and has held that rates may be determined by a variety of formulae. See, e.g., FPC v. Hope Natural Gas Co., 320 U.S. 591, 602, 64 S.Ct. 281, 88 L.Ed. 333 (1944) (“[T]he Commission [i]s not bound to the use of any single formula or combination of for-mulae in determining rates.”); see also Mobil Oil Corp. v. FPC, 417 U.S. 283, 316, 94 S.Ct. 2328, 41 L.Ed.2d 72 (1974) (“Mobil’s argument assumes that there is only one just and reasonable rate possible for each vintage of gas, and that this rate must be based entirely on some concept of cost plus a reasonable rate of return. We rejected this argument in Permian Basin and we reject it again here.”); Am. Pub. Power Ass’n v. FPC, 522 F.2d 142, 146 (D.C.Cir. 1975) (“Congress carefully eschewed tying ‘just and reasonable’ rates to any particular method of deriving the rates. Certainly there is nothing in the Federal Power Act specifically endorsing historic test year ratemaking or any other technique of ratemaking. Congress clearly intended to allow the Commission broad discretion in regard to the methodology of testing the reasonableness of rates.”).
In establishing the reasonable range of capacity prices, FERC first reviewed evidence introduced at the hearing on the locational installed capacity mechanism (which was later replaced by the Forward Market). FERC decided to look at projected prices for Maine and Northeastern Massachusetts under both the demand curve proposed by Maine and Vermont load representatives and the demand curve proposed by the ISO. The Commission acknowledged that these were not the only two demand curves proposed at the hearing, but, as it explained more fully in the order on rehearing, it chose to rely on these two curves because they came from two different sectors. Load representatives offered demand curves that projected low prices, while supplier representatives offered demand curves that projected high prices; thus, FERC noted that “[i]f the Commission relied only upon demand curves proposed by parties representing load, the transition payments may have appeared excessive; relying only on demand curves proposed by suppliers would imply that the transition payments were inadequate.” 117 FERC at 61,719. FERC accordingly “conclude[d] that relying on proposed demand curves from a single sector would have been unreasonable” and focused on two curves — from two different sectors — that provided a narrow range of price projections. Id.; see also 115 FERC at 62,319-20. Comparing the transition payments to these demand curve projections, FERC found that the transition payments fell within the range of capacity prices projected by both demand curves. 115 FERC at 62,321.
The petitioners object that FERC improperly relied on the demand curves as a basis of comparison because FERC did not expressly find them to be just and reasonable. Since it never made that finding, the petitioners insist, FERC could not rely on the demand curves to find that the transition payments were reasonable. It is true that FERC may not use unexamined rates as a basis of comparison. Cf. Laclede Gas Co. v. FERC, 997 F.2d 936, 946-47 (D.C.Cir. 1993). But here, FERC examined the record evidence and concluded that these two curves “establishe[d] a rea
The petitioners also object to FERC’s reliance on evidence of the estimated cost of new entry to determine a reasonable range of rates. The petitioners raise two concerns. First, they argue that cost of new entry represents the estimated costs of a new peaker, not those of an existing generator, and that the two may have different capital costs. The Commission determined, however, that new peakers have “capital costs [that] are lower than most, if not all, other plants.” 115 FERC at 62,321. Hence, if cost of new entry is used as a reference point, the transition payments “are likely to be significantly lower than a cost-of-service payment for most, if not all, new generators.” Id.; see id. at 62,319 (concluding that “in the first years,” the transition “payments are less than the cost of new entry, accurately reflecting market conditions”).
Second, the petitioners argue that cost of new entry is an arbitrary reference point for the transition period because, although cost of new entry provides a starting point for the Forward Market auction, the Forward Market does not exist during the transition period. But the fact that cost of new entry is used to kick off the auction does not mean that it is relevant only for that purpose. If anything, the reliance on cost of new entry as a starting point of the Forward Market auction underscores its relevance to appropriate rates: it is used to commence the auction because it approximates reasonable compensation for existing as well as new generators. See id. at 62,326. FERC sets rates to ensure both that existing generators are adequately compensated and that prices support new entry when additional capacity is needed. See, e.g., Recording of Oral Arg. at 1:02:34-1:03:01, 1:09:30-1:10:35. As FERC therefore noted, cost of new entry is “a key factor in determining appropriate rates for capacity” and was central to the demand curves under the locational installed capacity market as well as the Forward Market design. 117 FERC at 61,718; cf. Elec. Consumers Res. Council v. FERC, 407 F.3d 1232, 1235, 1237-38 (D.C.Cir. 2005) (upholding FERC’s approval of a demand curve that sets prices based on the annualized cost of a new peaker plant); New York Indep. Sys. Operator, Inc., 117 FERC ¶ 61,086 at 61,443 n.7 (2006) (“In a competitive market, prices should reach equilibrium at or near to the levelized net cost of new en
Finally, the petitioners claim that FERC did not respond meaningfully to their objections to the transition payments. See PPL Wallingford Energy LLC v. FERC, 419 F.3d 1194, 1198 (D.C.Cir. 2005) (“An agency’s ‘failure to respond meaningfully’ to objections raised by a party renders its decision arbitrary and capricious.” (quoting Canadian Ass’n of Petroleum Producers v. FERC, 254 F.3d 289, 299 (D.C.Cir. 2001))). Specifically, the petitioners argue that FERC did not address the argument of the Attorneys General that the transition payments do not reflect market conditions, reliability contributions, or cost-of-service; and they cite witness that the transition payments are significantly in excess of what is needed to retain existing resources because many generators rely in part on sources of energy other than oil and gas (e.g., nuclear and hydro power). The Commission did, however, respond to these objections, discussing the long-term commitment and enhanced reliability contributions of generators that the transition payment mechanism requires. See 115 FERC at 62,322; 117 FERC at 61,720, 61,724. FERC also rejected the petitioners’ premise that their expert’s testimony was the only relevant evidence about whether the transition payments were reasonable and explained that cost of new entry and the demand curves were relevant evidence. E.g., 117 FERC at 61,718-20. In short, FERC’s conclusion that the transition payments fell within a reasonable range of capacity prices was a reasoned decision supported by substantial evidence.
III.
Petitioner Maine Public Utilities Commission (Maine PUC) argues that FERC’s acceptance of non-locational pricing during the transition period was arbitrary and capricious, attacking FERC’s decision on both general and specific grounds.
At a general level, Maine PUC contends that FERC acted arbitrarily in approving non-locational transition payments when FERC had previously insisted that a locational structure was necessary for New England. Maine PUC’s claim is that, by approving non-locational transition payments, FERC abandoned the core of the market reform it set out to implement, a mechanism that would “appropriately value capacity resources according to their location.” Pet’r Br. 48 (quoting Devon Power LLC, 109 FERC ¶ 61,154 at 61,631 (2004)). But the Forward Market, which is the ultimate product of the settlement, includes locational pricing.
Maine PUC’s specific contention is that separate prices are warranted for Maine during the transition period because Maine has a capacity surplus and is export constrained (so that it would experience lower capacity prices in an actual market). It maintains that FERC refused to consider the evidence that it presented to support this contention. But FERC did consider Maine’s argument that it should pay lower transition payments because of its capacity surplus. The Commission offered two interrelated reasons for its conclusion that the transition payments should not have a locational component. First, FERC cited record evidence that projected “little to no variability in capacity prices across New England regions for the period covered by the transition mechanism.” 115 FERC at 62,322. Second, to the extent that import constraints do exist in other areas of New England, thereby creating a need for additional capacity, FERC noted that Reliability Must-Run agreements had already been approved and would continue during the transition period, with the costs for these contracts paid locally. Id.
To be sure, Maine PUC offered some contradictory evidence about capacity price variability, see, e.g., J.A. 1941-47 (Supplemental Affidavit of Thomas D. Austin), but FERC’s orders do “not lack substantial evidence simply because petitioners offered some contradictory evidence,” Ariz. Corp. Comm’n v. FERC, 397 F.3d 952, 954 (D.C.Cir. 2005) (internal quotation marks omitted). FERC was entitled to reject Maine PUC’s evidence and to base its conclusion on different evidence in the record. See, e.g., Elec. Consumers Res. Council, 407 F.3d at 1236 (“[T]he court defers to the Commission’s resolution of factual disputes between expert witnesses.”); see also Fla. Mun. Power Agency, 315 F.3d at 368.
Maine PUC insists that FERC cannot rely on the rationale that price separation between Maine and the rest of New England was unsupported by the record. Although FERC did rely on this rationale in its initial order, Maine PUC claims that the Commission abandoned it in its order on rehearing. According to Maine PUC, on rehearing FERC refused to consider data presented by the petitioners and instead found that it was irrelevant whether Maine was export constrained. But despite somewhat infelicitous language in its rehearing order, FERC did not abandon the findings and conclusions of its initial order. To the contrary, the rehearing order first discussed both the evidence presented by Maine PUC, including Dr. Austin’s affidavits, and the data and arguments in the record that contradicted this evidence. See 117 FERC at 61,722-23; see also id. at 61,724 (“The Commission did consider arguments presented in Dr. Austin’s affidavits in approving the Settlement Agreement.”). FERC’s subsequent statement that the “issue of Maine being export-constrained is not the subject of this proceeding,” id. at 61,724, did not undo all of that previous discussion. Rather, it merely clarified that the question of whether Maine was export constrained was relevant only insofar as it affected FERC’s determination of reasonable rates; it was not an
Finally, Maine PUC challenges FERC’s denial of a motion that it filed on September 8, 2006, following the Commission’s initial June 16 order. By that motion, Maine PUC sought to lodge the Department of Energy’s National Electric Transmission Congestion Study, which Maine PUC argued supported its claim that the transition payments should be locational. We accord the Commission “broad discretion in fashioning hearing procedures,” Mich. Consol. Gas Co. v. FERC, 883 F.2d 117, 125 (D.C.Cir. 1989) (quoting Lyons v. Barrett, 851 F.2d 406, 410 (D.C.Cir. 1988)), and find no abuse of discretion here. The motion at issue was filed nearly three months after FERC’s decision approving the settlement, and FERC acted reasonably in holding that it “would be inappropriate to accept evidence at this extremely late date in this proceeding (after a dispositive order has been issued), since it would effectively deny parties the opportunity to respond to the evidence.” 117 FERC at 61,724. FERC similarly denied untimely motions to intervene by Bridgeport Energy, LLC and Casco Bay Energy Company, LLC, which had been filed several weeks before Maine PUC’s motion. See id. at 61,715.
Accordingly, we reject all of Maine PUC’s attacks on FERC’s decision to accept non-locational pricing during the transition period.
IV.
Section 4.C of the settlement agreement provides that the transition payments and the final prices from the Forward Market auctions will be reviewed under the “public interest” standard rather than the “just and reasonable” standard. 115 FERC at 62,333. This is more than a matter of semantics: the public interest standard is “much more restrictive” than the just and reasonable standard, which means that the settlement agreement makes it harder to successfully challenge the transition payments and Forward Market auction prices. Wisc. Pub. Power, Inc. v. FERC, 493 F.3d 239, 271 (D.C.Cir. 2007) (citation omitted). The agreement states that the public interest standard will apply to all future challenges to the transition payments and final auction prices “whether the change is proposed by a Settling Party, a non-Settling Party, or the FERC acting sua sponte.” 115 FERC at 62,333. Petitioners&emdash;who were not parties to the settlement agreement&emdash;assert that this provision will deprive them of their statutory right to challenge rates under the “just and reasonable” standard. We agree, and we grant the petition for review on this issue.
* * :!=
Under the Mobile-Sierra doctrine, “FERC may abrogate or modify freely negotiated private contracts that set firm rates or establish a specific methodology for setting the rates for service ... only if required by the public interest.” Atl. City Elec. Co. v. FERC, 295 F.3d 1, 14 (D.C.Cir. 2002). This doctrine recognizes the superior efficiency of private bargaining, and its purpose is “to subordinate the statutory filing mechanism to the broad and familiar dictates of contract law.” Borough of Lansdale v. FPC, 494 F.2d 1104, 1113 (D.C.Cir. 1974). Thus, when the parties to a rate dispute reach a contractual settlement, FERC must enforce the terms of the bargain unless the public interest requires otherwise&emdash;that is, unless the negotiated rates “might impair the financial ability of the public utility to continue its service, cast upon other customers an excessive burden, or be unduly discriminatory.” FPC v. Sierra Pac. Pow
Section 206 of the Federal Power Act provides: “Whenever the Commission, after a hearing had upon its own motion or upon complaint, shall find that any rate, charge, or classification ... is unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate ... and shall fix the same by order.” 16 U.S.C. § 824e(a). In other words, when a party files a complaint against a rate or charge, FERC must adjudicate the challenge under the “just and reasonable” standard. The Mobile-Sierra doctrine carves out an exception to this rule based on the “familiar dictates of contract law.” Lansdale, 494 F.2d at 1113. When two or more parties reach a negotiated settlement over a disputed rate, FERC applies a strong presumption that the settled rate is just and reasonable, and the Commission may only set aside the contract for the most compelling reasons.
Courts have rarely mentioned the Mobile-Sierra doctrine without reiterating that it is premised on the existence of a voluntary contract between the parties. In Mobile, the Supreme Court stated that “the relations between the parties ” may be established by contract, subject only to “public interest” review. United Gas Pipe Line Co. v. Mobile Gas Serv. Corp., 350 U.S. 332, 339, 76 S.Ct. 373, 100 L.Ed. 373 (1956) (emphasis added). Similarly, this Court has emphasized that the deferential public interest standard only applies to “freely negotiated private contracts that set firm rates or establish a specific methodology for setting the rates for service.” Atl. City, 295 F.3d at 14 (emphasis added); see also Maine PUC v. FERC, 454 F.3d 278, 283-84 (D.C.Cir. 2006); Richmond Power & Light v. FPC, 481 F.2d 490, 493 (D.C.Cir. 1973) (“The contract between the parties governs the legality of the filing.”).
This case is clearly outside the scope of the Mobile-Sierra doctrine. As
In defense of the Mobile-Sierra provision, FERC argues that the “public interest” standard will only apply to future challenges to a narrow category of rates: the transition payments and the final auction clearing prices from the Forward Market. 115 FERC at 62,335. This is not persuasive. It is equivalent to arguing that FERC will use an illegal standard sparingly. Despite the “limited” applicability of the public interest standard, FERC’s approval of this agreement still deprives non-settling parties of their statutory right to have rate challenges adjudicated under the “just and reasonable” standard. And in any event, we are skeptical of FERC’s characterization of the Mobile-Sierra provision as “narrow” or “limited.” As petitioners’ counsel noted at oral argument, if circumstances change after a rate has initially been approved by the Commission, then (under the settlement agreement) subsequent challenges to that rate would be reviewed under the public interest standard. Recording of Oral Arg. at 29:25-31:20. The Mobile-Sierra provision thus departs from the usual “just and reasonable” standard and makes it harder for petitioners to successfully challenge rates in cases of changed circumstances.
FERC also argues that in other recent cases, the Commission has approved contracts that apply the “public interest” standard to non-contracting third parties. 117 FERC at 61,727 n.103. This may show that the Commission’s policy has been consistent — although even FERC concedes that is so only since 2002 — but it does not necessarily support the policy’s legality, since none of the cited orders have been subject to judicial review on the Mobile-Sierra issue. FERC states that “there is no Commission or court precedent that supports a finding that a non-signatory may unilaterally seek changes to a Mobile-Sierra ‘public interest’ contract under the ‘just and reasonable’ standard of review.” 115 FERC at 62,335 (citation omitted). It could just as easily be said that there is no “court precedent” that supports altering third parties’ statutory rights based on a contract that they refused to sign. Moreover, while FERC can find no “precedent” in support of petitioners’ arguments, the relevant statutory language is quite clear: section 206 of the FPA states that “upon
y.
Petitioners also contend that FERC’s approval of the Forward Market exceeds the Commission’s jurisdiction because it forces utilities to purchase a specific amount of capacity. Petitioners assert that FERC lacks jurisdiction under the Federal Power Act, which provides that the Commission “shall not have jurisdiction ... over facilities used for the generation of electric energy.” 16 U.S.C. § 824(b)(1). In response, FERC argues that the settlement agreement only addresses prices, which are unquestionably within FERC’s jurisdiction. The Commission’s interpretation of the scope of its jurisdiction is entitled to Chevron deference. Okla. Natural Gas Co. v. FERC, 28 F.3d 1281, 1283-84 (D.C.Cir. 1994).
We agree with the Commission that the Forward Market itself does not exceed FERC’s jurisdiction. The Federal Power Act grants the Commission broad authority over “the sale of electric energy at wholesale in interstate commerce.” 16 U.S.C. § 824(b)(1). The protracted litigation over Must-Run agreements, the locational installed capacity market, and the Forward Market is fundamentally a dispute over the rates that will be paid to suppliers of capacity. The two key components of the settlement agreement — the transition payments and the Forward Market auctions — “establish a mechanism and market structure for the purchase and sale of installed capacity at wholesale ... [and] determine the prices for those sales.” 115 FERC at 62,339 (emphasis added). Of course, it is a basic principle of economics that prices affect supply — the auction clearing prices in each sub-region of New England will certainly influence the amount of capacity that generators are willing to supply. Indeed, one of the primary purposes of the new market mechanism is to “provide[ ] incentives to attract new infrastructure where needed.” Id. at 62,316. But an incentive is not a mandate. The mere fact that the Forward Market will encourage new supply does not mean that it regulates “facilities used for the generation of electric energy.” 16 U.S.C. § 824(b)(1). Rather, the Forward Market is designed to address pricing issues, which fall comfortably within FERC’s statutory authority over “the sale of electric energy at wholesale in interstate commerce.” Id. We have previously held that the Commission has jurisdiction over a “deficiency charge” that was imposed upon transmission providers who failed to procure a specified amount of capacity:
The deficiency charge ... must be deemed to be .within the Commission’s jurisdiction because it [] represents a charge for the power and service the overloaded participant receives- — or it is at least a rule or practice affecting the charge for these services.
Municipalities of Groton v. FERC, 587 F.2d 1296, 1302 (D.C.Cir. 1978).
In support of their jurisdictional argument, petitioners focus heavily upon the
VI.
For the aforementioned reasons, the consolidated petitions for review are granted with respect to the Mobile-Sierra issue, denied with respect to all other issues, and remanded to the Commission for further proceedings.
So ordered.
. It would have been helpful if the parties had actually defined “capacity” before delving into the intricacies of New England's capacity market. Also, the briefs would have been much easier to read if the parties had used fewer acronyms.
. An ISO is an independent company that has operational control, but not ownership, of the transmission facilities owned by member utilities. ISOs "provide open access to the regional transmission system to all electricity generators at rates established in a single, unbundled, grid-wide tariff....” Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1364 (D.C.Cir. 2004) (citation omitted). In 2004, the New England ISO was organized as a Regional Transmission Organization ("RTO”). RTOs are given greater regulatory flexibility by FERC, provided that they (inter alia): are regional in scope, have exclusive operational control over all transmission facilities within their control, and have sole authority to approve or deny requests for transmission service. Id. at 1365.
. Although the parties refer to this as a "demand curve,” that term is misleading. Normally, a "demand curve” is a model of the relationship between prices and consumer preferences in a free market. In contrast, the "demand curve” proposed by the ISO is an entirely artificial construct that specifies the prices that must be paid for various quantities of capacity. 107 FERC at 62,022; see also Elec. Consumers Res. Council v. FERC, 407 F.3d 1232, 1234-35 (D.C.Cir. 2005) (explaining the construction of a similar "demand curve” by the New York ISO). This proposal was intended to make revenues and price movements more stable and predictable. 107 FERC at 62,022. That may or may not have been sound policy, but it more accurately should be termed a "non-demand demand curve” reminiscent of the once regulatory invention, a "non-bank bank.”
. The orders under review are Devon Power LLC, 115 FERC ¶ 61,340 (2006); Devon Power LLC, 117 FERC ¶ 61,133 (2006); ISO New England, Inc., 117 FERC ¶ 61,132 (2006); and ISO New England, Inc., 119 FERC ¶ 61,044 (2007).
. The petitioners cite NSTAR Electric & Gas Corp. v. FERC, 481 F.3d 794 (D.C.Cir. 2007), for the proposition that FERC cannot approve a rate without reviewing cost data, but this
. The petitioners also argue that FERC acted arbitrarily and capriciously in ordering an overbroad remedy to the market problem it had identified. According to the petitioners, the ongoing use of Reliability Must-Run contracts during the transition period contravenes FERC’s initial desire to implement a market structure to replace Must-Run contracts. This objection was not raised before the agency and is therefore waived. See 16 U.S.C. § 8251(b) (“No objection to the order of the Commission shall be considered by the court unless such objection shall have been urged before the Commission in the application for rehearing unless there is reasonable ground for failure so to do.’’).
. For the Forward Market, capacity is purchased three years in advance, so the full market design, including the locational element, cannot be implemented until 2010.
. As one commentator has noted, the Mobile-Sierra doctrine “recognize[s] that the existence of a contract infuses the rate with the attribute of reasonableness....” Carmen L. Gentile, The: Its Illustrious Past and Uncertain Future, 21 Energy LJ. 353, 357 (2000).
. FERC asserts that third parties’ interests are adequately safeguarded because under Mobile-Sierra, the Commission "retains significant authority to protect non-parties to the settlement from harm.” 115 FERC at 62,335. But whatever comfort third parties might derive from FERC’s continued ability to defend their interests, the existence of such powers does not justify derogation of the statutory right to "just and reasonable” review of rates.
Reference
- Full Case Name
- MAINE PUBLIC UTILITIES COMMISSION v. FEDERAL ENERGY REGULATORY COMMISSION, Connecticut Department of Public Utility Control, Intervenors
- Status
- Published