Oglala Sioux Tribe v. U.S. Nuclear Regulatory Comm'n
Opinion
GARLAND, Chief Judge : Powertech (USA), Inc. applied to the Nuclear Regulatory Commission for a license to construct a uranium mining project in the Black Hills of South Dakota. The Oglala Sioux Tribe, which has historical ties to the proposed project area, intervened in opposition because it feared the destruction of its cultural, historical, and religious sites. The staff of the Commission granted the license.
On administrative appeal, the Commission decided to leave the license in effect-notwithstanding its own determination that *523 there was a significant deficiency in its compliance with the National Environmental Policy Act-pending further agency proceedings to remedy the deficiency. The Commission grounded this decision on the Tribe's inability to show that noncompliance with the Act would cause irreparable harm. In so doing, the Commission was following what appears to be the agency's settled practice to require such a showing.
The National Environmental Policy Act, however, obligates every federal agency to prepare an adequate environmental impact statement before taking any major action, which includes issuing a uranium mining license. The statute does not permit an agency to act first and comply later. Nor does it permit an agency to condition performance of its obligation on a showing of irreparable harm. There is no such exception in the statute.
In fact, such a policy puts the Tribe in a classic Catch-22. In order to require the agency to complete an adequate survey of the project site before granting a license, the Tribe must show that construction at the site would cause irreparable harm to cultural or historical resources. But without an adequate survey of the cultural and historical resources at the site, such a showing may well be impossible. Of course, if the project does go forward and such resources are damaged, the Tribe will then be able to show irreparable harm. By then, however, it will be too late.
The Commission's decision to let the mining project proceed violates the National Environmental Policy Act. Indeed, it vitiates the requirements of the Act. We therefore find the decision contrary to law and grant the petition for review in part. The Tribe also challenges other aspects of the Commission's order but, as we explain, we lack jurisdiction to consider those rulings.
I
The Atomic Energy Act,
The licensing process involves three relevant components of the NRC.
The first is the Commission Staff, which is responsible for reviewing a license application, analyzing the environmental effects and other features of the proposed project, and issuing an initial decision approving or denying the application.
The second is an Atomic Safety and Licensing Board (ASLB), a panel that can be designated to preside over a licensing hearing, at which the Board hears contentions from intervenors and then issues an initial decision on those contentions.
Third is the Commission itself. Once the Board issues an initial decision on the contentions before it, parties can seek review from the Commission.
In 2009, Powertech applied for an NRC license authorizing it to "construct and operate" a uranium mining project, called the "Dewey-Burdock project," in the southwest corner of South Dakota. NRC, Record of Decision for the Dewey-Burdock Uranium In-Situ Recovery Project at 1 (2014) ("Record of Decision") (J.A. 738). The NRC described the project as follows:
The proposed facility will encompass approximately ... 10,580 acres[,] which consists of two contiguous mining units .... Powertech intends to recover uranium and produce yellowcake at the Dewey-Burdock site. Powertech's proposed activities include construction, operation, aquifer restoration, and decommissioning of its ISR facility. In addition, Powertech has proposed that liquid wastewater generated during uranium recovery be disposed of through one of the following methods: (i) deep well disposal via Class V injection wells, (ii) land application, or (iii) a combination of deep well disposal and land application.
The petitioner here, the Oglala Sioux Tribe, intervened to challenge Powertech's application. The Tribe's Pine Ridge Reservation is located roughly fifty miles from the project site, Powertech USA, Inc.,
While the Board set the stage for the Powertech hearing, the Commission Staff drew up environmental documents for the Dewey-Burdock project, including an EIS, which it published in 2014. See EIS, NUREG-1910 (J.A. 567-737). 2 After publishing the EIS, the Staff granted Powertech's *525 application and issued the requested license. Record of Decision at 1 (J.A. 738).
The Tribe promptly moved to stay the license. Without assessing the merits of the Tribe's contentions, the Board denied the stay. It did so on the ground, inter alia, that the Tribe's allegations "lack[ed] the specificity needed to demonstrate a serious, immediate, and irreparable harm to cultural and historic resources." Order, Powertech USA, Inc., No. 40-9075-MLA at 6 (May 20, 2014) ("ASLB Stay Denial Order") (J.A. 516).
After denying the stay, the Board held a hearing on the merits of the contentions pending before it. The Board ruled against the Tribe, and in favor of the Staff and Powertech, on the bulk of those contentions.
3
However, on two of the Tribe's contentions, Contentions 1A and 1B, the Board ruled in favor of the Tribe. ASLB Initial Decision,
In Contention 1A, which is most significant for our purposes, the Tribe charged that the EIS did not satisfy NEPA because it failed to adequately address the environmental effects of the Dewey-Burdock project on Native American cultural, religious, and historical resources. The Board agreed with this charge, finding that:
[T]he [EIS] in this proceeding does not contain an analysis of the impacts of the project on the cultural, historical, and religious sites of the Oglala Sioux Tribe and the majority of the other consulting Native American tribes. ... Because the cultural, historical, and religious sites of the Oglala Sioux Tribe have not been adequately catalogued, the [EIS] does not include mitigation measures sufficient to protect this Native American tribe's cultural, historical, and religious sites that may be affected by the Powertech project.
Accordingly, as to Contention 1A, the Board finds and concludes that the [EIS] has not adequately addressed the environmental effects of the Dewey-Burdock project on Native American cultural, religious, and historic resources. ... NEPA's hard look requirement has not been satisfied.
In Contention 1B, the Tribe charged that the NRC Staff had failed to fulfill its responsibilities regarding consultation with Native American tribes under the National Historic Preservation Act (NHPA),
Despite what the Board concluded was a "significant deficiency in the NRC Staff's NEPA review," it did not suspend Powertech's previously issued license.
The action then moved to the Commission. The Tribe, the Staff, and Powertech all petitioned the Commission for review of the Board's decision. The Staff and Powertech challenged the Board's partial resolution of Contentions 1A and 1B in favor of the Tribe. With respect to those same contentions, the Tribe argued that NEPA and the National Historic Preservation Act "prohibit[ed] the Board from leaving [Powertech's] license in place," given the project's inadequate environmental review. Powertech (USA), Inc.,
The Commission generally upheld the Board's rulings.
Commissioner Baran dissented on the point that is now at issue before us: the Commission's decision to leave Powertech's license in effect while the Staff attempted to resolve the deficiencies in its NEPA review. His dissent stated as follows:
[A] core requirement of NEPA is that an agency decisionmaker must consider an adequate environmental review before making a decision on a licensing action. If the Commission allows a Board to supplement and cure an inadequate NEPA document after the agency has already made a licensing decision, then this fundamental purpose of NEPA is frustrated.
In this case, the Board found that the Staff's [EIS] did not meet the requirements of NEPA because the [EIS] was deficient with respect to the effects of the licensing action on Native American cultural, religious, and historic resources. Thus, the agency did not have an adequate environmental analysis at the time it decided whether to issue the license. In fact, the deficiencies in the NEPA analysis remain unaddressed today, and therefore the Staff still cannot make an adequately informed decision on whether to issue the license. The Staff's licensing decision was based on (and continues to rest on) an inadequate environmental review. As a result, the Staff has not complied with NEPA.
The Commission should suspend the license until the Staff has ... demonstrat[ed] that the [EIS] complies with NEPA ....
Thereafter, the Tribe filed a petition in this court for review of the Commission's order. Its principal challenge is to the NRC's decision to leave the license in effect pending the Staff's effort to cure the NEPA deficiencies. The Tribe also challenges the disposition of its other contentions, which are set out in footnote 3, supra .
II
We begin with our jurisdiction.
*527 A
Under the Hobbs Act, this court has jurisdiction to review "final orders" of the Commission.
Applying this standard, we conclude that the Commission's order, as a whole, is not final. It did not consummate the agency's decisionmaking process as to all issues, but instead left the proceeding "open" while the Staff attempted to resolve the deficiencies in NEPA compliance (Contention 1A) and in the National Historic Preservation Act consultation process (Contention 1B). NRC Order,
In keeping with this instruction, the Atomic Safety and Licensing Board has continued to oversee the Staff's efforts to cure the statutory deficiencies. In October 2017, the Board granted the Staff's motion for summary disposition regarding Contention 1B, concluding that the Staff's consultation efforts over the intervening two years had satisfied the National Historic Preservation Act. Powertech USA, Inc
.
,
Because the Commission's order did not end the agency proceeding as to all issues, we do not have jurisdiction to review the bulk of the rulings challenged by the Tribe.
B
We do have jurisdiction, however, to review one of the rulings contained in the NRC order: the decision to leave the license in effect-notwithstanding the NRC's determination that the agency is not in compliance with NEPA-pending further proceedings before the Atomic Safety and Licensing Board. 4 That ruling falls within the collateral order doctrine. 5
Pursuant to
*528
... encompass[ing] not only judgments that terminate an action, but also a small class of collateral rulings that, although they do not end the litigation, are appropriately deemed 'final.' "
Mohawk Indus., Inc. v. Carpenter
,
To effectuate that admonition, the Court has limited appealable collateral rulings to a "small category [that] includes only decisions [1] that are conclusive, [2] that resolve important questions separate from the merits, and [3] that are effectively unreviewable on appeal from the final judgment in the underlying action."
First, that ruling is "a fully consummated decision ... that conclusively and finally determine[s]" the effectiveness of Powertech's license for the foreseeable future.
See
CalPortland Co.
,
Second, the order resolves an "important question[ ] separate from the merits,"
Mohawk Indus.
,
Third, the ruling that permits projects to go forward despite "significant" NEPA violations will be effectively unreviewable
*529
if the Tribe is forced to wait for the conclusion of the agency's adjudication before appealing. If we do not hear that issue now, the ASLB proceedings will continue. At the end of that process, the agency either will conclude that the Staff has been unable to satisfy NEPA and will therefore (presumably) vacate the license,
see
NRC Br. 8, 30, or it will determine that the Staff has finally satisfied NEPA and reaffirm the license. If it reaches the former conclusion, there will be nothing left for the Tribe to petition to review. If it reaches the latter, our precedent will require denial of the petition on the ground that-at that point-a remand would be futile.
See
Friends of the River v. FERC
,
In evaluating this third condition, the Supreme Court has said that "the decisive consideration is whether delaying review until the entry of final judgment would imperil a substantial public interest or some particular value of a high order."
Mohawk Indus.
,
Finally, in making the collateral order determination, the Court has instructed that we "not engage in an individualized jurisdictional inquiry," but rather focus on "the entire category to which a claim belongs."
Mohawk Indus.
,
We therefore have jurisdiction to consider whether the NRC may authorize a licensee to go ahead with construction-notwithstanding the Commission's conclusion that there has been a significant deficiency *530 in its NEPA compliance-unless an intervenor demonstrates irreparable harm. 7
III
Our review of this matter is governed by the Administrative Procedure Act (APA),
A
NEPA requires that "all agencies of the Federal Government shall ... include in every recommendation or report on proposals for ... major Federal actions significantly affecting the quality of the human environment, a detailed statement by the responsible official" on:
(i) the environmental impact of the proposed action,
(ii) any adverse environmental effects which cannot be avoided should the proposal be implemented,
(iii) alternatives to the proposed action,
(iv) the relationship between local short-term uses of man's environment and the maintenance and enhancement of long-term productivity, and
(v) any irreversible and irretrievable commitments of resources which would be involved in the proposed action should it be implemented.
This statutory provision requires agencies to take a "hard look" at environmental consequences before undertaking any such action.
Robertson
,
The Atomic Safety and Licensing Board ruled that, to "fulfill the agency's NEPA ... responsibilities to protect and preserve
*531
cultural, religious, and historical sites important to the Native American tribal cultures in the Powertech project area, the NRC Staff must conduct a study or survey of tribal cultural resources before granting a license." ASLB Initial Decision,
The Board did not find just a technical violation of NEPA. Rather, it found that "the inadequate discussion of potential impacts to Sioux cultural, historical, or religious sites in the [EIS] or Record of Decision is a
significant deficiency
in the NRC Staff's NEPA review."
For purposes of our review, we accept the Board's finding-undisturbed by the Commission-that the agency did not fulfill its NEPA responsibilities. We do not review the merits of that conclusion.
Notwithstanding the Board's finding, and in particular its acknowledgment that the Staff "must conduct a study or survey of tribal cultural resources
before
granting a license" in order to fulfill the agency's NEPA responsibilities, ASLB Initial Decision,
The agency thus conditioned enforcement of NEPA on a showing of irreparable harm by the Tribe.
8
It did so even though, as Commissioner Baran explained in dissent, the agency lacked an adequate environmental analysis when it first issued the license and the significant NEPA deficiencies identified by the Board "remain[ed] unaddressed" at the time of the Commission's decision.
*532
Moreover, this was not a one-off decision by the NRC. Rather, it appears to reflect the agency's settled practice.
See
Strata Energy, Inc.,
The agency's decision in this case and its apparent practice are contrary to NEPA. The statute's requirement that a detailed environmental impact statement be made for a "proposed" action makes clear that agencies must take the required hard look
before
taking that action.
See, e.g.
,
Pub. Emps. for Envtl. Responsibility v. Hopper
,
The nontextual exception upon which the NRC insists would vitiate the statute's " 'action-forcing' purpose."
Robertson
,
The statutory requirement that a federal agency contemplating a major action prepare such an environmental impact statement serves NEPA's "action-forcing" purpose in two important respects. ... It ensures that the agency, in reaching its decision, will have available, and will carefully consider, detailed information concerning significant environmental impacts; it also guarantees that the relevant information will be made available to the larger audience that may also play a role in both the decisionmaking process and the implementation of that decision.
*533
Ill. Commerce Comm'n v. ICC
,
Indeed, the nature of the agency action in this case puts the problem in high relief. As we have noted, the Tribe "has shown it has the most direct historical, cultural, and religious ties to the [Dewey-Burdock project] area." ASLB Initial Decision,
In short, the NRC has placed the Tribe in a classic Catch-22. It must show irreparable harm to insist that an adequate survey be completed. But it likely cannot show even the risk of such harm unless that survey is completed. Of course, if the project goes forward and the burial or other sites are damaged, the Tribe will then be able to show irreparable harm-but by then, it will be too late to stop it.
The NRC's conduct in this case may be compared-unfavorably-to that of the Interstate Commerce Commission in
Illinois Commerce Commission v. ICC
,
B
In this subpart, we address the NRC's defense of its ruling.
1. The justification upon which the Commission relied in its order was an analogy to this court's treatment of "harmless error" when reviewing an agency decision. NRC Order,
The "harmless error" doctrine that this court applies is compelled by a statute, the Administrative Procedure Act, which provides that "due account shall be taken of the rule of prejudicial error,"
But whether or not that ends the argument-a question we do not need to decide-what the agency has done here looks nothing like the harmless error review undertaken by this court.
First, it is true that "[w]e have applied the prejudicial error rule in the NEPA context where the proposing agency engaged in significant environmental analysis before reaching a decision but failed to comply
precisely
with NEPA procedures."
Nevada v. Dep't of Energy
,
The Commission's order disparaged this error as merely "procedural." NRC Order,
Given the significant deficiency at issue in this case, the harmless error doctrine cannot justify the agency's ruling. As we have noted, the Board found that the EIS "does not contain an analysis of the impacts of the project on the cultural, historical, and religious sites of the Oglala Sioux Tribe and the majority of the other consulting Native American tribes." ASLB Initial Decision,
In this context, the agency may not properly conclude that its failure to comply with NEPA is harmless simply because the Tribe cannot point to specific historical sites that are at risk. Indeed, placing the burden on the Tribe to show harm was
*535
especially inappropriate because the inadequate EIS may well make doing so impossible.
See
Winter
,
Second, the point at issue here is not simply forgiveness of a single error. As we have explained, it appears to be the NRC's settled practice to keep licenses in effect, notwithstanding significant NEPA deficiencies, unless an intervenor shows irreparable harm. See supra Part III.A. That does not represent the application of a harmless error exception to a statutory violation. It represents a wholesale rewrite of NEPA.
Third, the standard of review the Commission approved is not just a "harmless" error standard-it is an "irreparable harm" standard.
See supra
note 8. The harmless error standard of the APA merely requires a showing of prejudice. That standard does not "impose a ... particularly onerous requirement."
Shinseki v. Sanders
,
The irreparable harm standard applied by the Board, in contrast, derives from the standard courts must apply in granting injunctive relief.
See
Monsanto Co. v. Geertson Seed Farms
,
2. NRC counsel-but not the Commission itself-also analogize the Commission's treatment of the erroneous Staff decision to the analysis this court applies when considering whether to vacate or merely remand erroneous agency actions. NRC Br. 34-39. As counsel correctly note, "[t]his Court has long held when considering remedies under § 706 that the 'decision whether to vacate depends on the seriousness of the order's deficiencies (and thus the extent of doubt whether the agency chose correctly) and the disruptive consequences of an interim change that may itself be changed.' "
Id.
at 34 (quoting, inter alia,
Allied-Signal, Inc. v. NRC
,
Because the NRC order appealed here does not rely upon this reasoning,
see
NRC Order,
As is true of this court's "harmless error" analysis, our remand practice is informed by the APA.
Compare
Without resolving whether the absence of statutory authority is sufficient to reject the analogy to judicial remand-without-vacatur, what the agency has done here does not mirror the court's decisionmaking process in that regard.
As the above quotation from
Allied-Signal
indicates, in deciding whether vacatur is required, we first consider the "seriousness of the order's deficiencies."
The seriousness of the NEPA deficiency is particularly clear here because the point of NEPA is to require an adequate EIS before a project goes forward, so that construction does not begin without knowledge of the affected cultural and historical sites. "Part of the harm NEPA attempts to prevent in requiring an EIS is that, without one, there may be little if any information about
prospective
environmental harms and potential mitigating measures."
Winter
,
*537
As
Allied-Signal
further indicates, we also evaluate the "disruptive consequences of an interim change."
Allied-Signal
,
Finally, once again the issue here is not just what to do about a single agency error, but what to do about the validity of an NRC practice that permits NEPA-deficient licenses to remain in place unless an intervenor can show irreparable harm. We have never turned merely to a remand remedy when an agency refused to adhere to a statutory command in such an across-the-board fashion.
3. NRC counsel make two further arguments that are also not reflected in the Commission's order. Even if they were meritorious, Chenery would render them insufficient to uphold the order.
First, NRC counsel maintain that the ASLB's decision to leave the license in place was justified because it was "based in part on the Tribe's own actions making the NHPA consultation process unnecessarily difficult." NRC Br. 35. But the Commission's order did not rely on this justification and instead noted that "the Board acknowledged that it could not definitively determine whether the Staff or the Tribe bore responsibility for what the Board considered a breakdown in consultation." NRC Order,
Second, counsel argue that the agency's "adjudicatory hearing process, which led to the identification of deficiencies in NRC's compliance with NEPA ... , did not arise from th[at] statute[ ], but, rather, from the Atomic Energy Act." NRC Br. 38. Whether the Commission could have delegated to its Staff the final authority to resolve NEPA issues without appeal to the Commission is a question that we need not answer today. The fact is that the Commission did not do so, and thus must explain why it permitted the project to go forward despite its own determination that the Staff had failed to comply with NEPA. As we have explained, the Commission has failed to offer a justification that is consistent with its statutory responsibility.
*538 C
To be clear, today we hold only that, once the NRC determines there is a significant deficiency in its NEPA compliance, it may not permit a project to continue in a manner that puts at risk the values NEPA protects simply because no intervenor can show irreparable harm. We do not decide that the Commission may never leave in place a license that its Staff previously issued but that the Commission later finds NEPA-deficient. That is, we do not decide that there is no version of a harmless error rule that the Commission may apply. Nor do we decide that there are no protective conditions the Commission might impose that would justify leaving a license in place during an administrative remand intended to cure a NEPA deficiency.
Cf.
Pub. Utils. Comm'n v. FERC
,
Regardless of whether one of those options might pass muster, the Commission did not follow such a course here.
IV
Because the standard that the Commission applied in permitting Powertech's license to remain in effect is inconsistent with NEPA, we remand this matter to the agency for further consideration consistent with this opinion. We do not, however, vacate the agency's ruling. As we recounted above, an appellate court's decision regarding whether to vacate or merely remand "depends on the seriousness of the order's deficiencies (and thus the extent of doubt whether the agency chose correctly) and the disruptive consequences of an interim change that may itself be changed."
Allied-Signal
,
We have no doubt about the seriousness of the order's deficiencies. But we have not been given any reason to expect that the agency will be unable to correct those deficiencies, and we are concerned about the disruptive consequences of vacating the license while the agency proceeds to satisfy NEPA. Powertech reasonably relied on the NRC's ruling and settled practice that permitted the continued effectiveness of the license the Staff issued. And it has represented to the court that its stock price "would plummet" if the license were "suspended, vacated, or revoked." Oral Arg. Tr. 30.
More important, it appears that the Tribe will not suffer harm-irreparable or otherwise-from a disposition that leaves the license in effect
for now
. Powertech has further represented that a South Dakota permitting requirement independently bars it from moving forward with construction on the site until the NRC completes its compliance with NEPA. Oral Arg. Tr. 32-35. We note that the Tribe doubts this representation.
Id.
at 37. But for now, we rely on it. If the representation turns out not to be correct, the Tribe will have grounds to seek further redress from this court.
Cf.
Pub. Empls. for Env. Responsibility
,
V
The Nuclear Regulatory Commission's December 2016 order is not entirely final, and as a consequence we do not have jurisdiction over the bulk of the rulings challenged by the Oglala Sioux Tribe. Under the collateral order doctrine, however, we do have jurisdiction to review the Commission's decision to leave Powertech's license in place-notwithstanding the *539 NRC's acknowledgment that it has not yet complied with the National Environmental Policy Act-on the ground that the Tribe failed to show irreparable harm. Because that decision is contrary to law, we grant the petition for review in part and remand the case to the Commission for further proceedings consistent with this opinion.
So ordered.
The NRC further explained the ISR process as follows:
[A]n oxidant-charged solution, called a lixiviant, will be injected into the production zone aquifer (uranium orebody) through injection wells. ... As the lixiviant circulates through the production zone, it will oxidize and dissolve the mineralized uranium .... The resulting uranium-rich solution will be drawn to recovery wells by pumping and then transferred to a processing facility via a network of underground pipelines. At the processing facility, the uranium will be removed from solution via ion exchange.
Record of Decision at 2 (J.A. 739).
Technically, this was the Final Supplemental Environmental Impact Statement (FSEIS) for the project. The Staff first published a draft supplemental EIS, which built on the Commission's generic EIS for in-situ leach uranium mining facilities. In 2014, it issued the FSEIS, which is the document most relevant to this case. The NRC brief occasionally refers to the document as the "EIS." See, e.g. , NRC Br. 49-52. For purposes of clarity, we will do so consistently throughout this opinion.
As relevant to the Tribe's petition in this court, the Board ruled against the Tribe on: Contention 2, regarding the sufficiency of baseline groundwater quality information; Contention 3, concerning the EIS's analysis of features that could permit groundwater migration; and Contention 6, relating to the EIS's analysis of proposed mitigation measures. ASLB Initial Decision,
Although the collateral order doctrine might also have given us jurisdiction over the NRC's parallel ruling regarding compliance with the National Historic Preservation Act, the ASLB's subsequent determination that the Staff's consultation efforts satisfied that Act, ASLB Summary Disposition Order,
Because we find that the ruling is reviewable as a collateral order, we do not decide whether review of the ruling would also fall within the scope of this circuit's "immediate effectiveness" doctrine.
See
Blue Ridge Envtl. Def. League
,
See
We are unpersuaded by NRC counsel's suggestion that the Tribe should have raised this challenge when the Staff first made Powertech's license effective in 2014. NRC Br. 33. The Tribe did apply for a stay at that time, and it did not appeal after the ASLB denied its application. But the question posed at that moment was not the same as the one raised here. When the Tribe first sought a stay, neither the Commission nor the Board had yet acknowledged the NEPA violation and neither had ruled that the license could remain in effect notwithstanding the violation. See ASLB Stay Denial Order, No. 40-9075-MLA at 8-9 (J.A. 518-19). Hence, the Tribe could not have challenged the ruling and policy that it alleges here is unlawful: letting a project go forward despite the Commission's acknowledgment that it has not satisfied NEPA's requirements.
Although the Commission's order vaguely referred to "harm or prejudice," NRC Order,
See also
Marsh v. Or. Nat. Res. Council
,
This circuit has also sometimes regarded deviations from NEPA as harmless when an agency subsequently completed a comprehensive environmental review before the matter reached our court.
See
Nat. Res. Def. Council
,
NRC counsel maintain that the Board "determined that vacating the license would not prevent potential harm to the Tribe's cultural resources." NRC Br. 35. The Board did conclude, more than two years
before
the order at issue here, that a stay would be of only "limited and incomplete effect." ASLB Stay Denial Order, No. 40-9075-MLA at 7-8 (J.A. 517-18). But that 2014 order was based on an assessment of ground-disturbing work expected only "for the next few months,"
id.
at 7 (J.A. 517), and there is no reason to believe its reasoning remained relevant to the status of construction in 2016. Indeed, that explanation was not repeated in either the Board's 2015 decision or the 2016 Commission order that upheld the 2015 decision and is now under review. We are therefore unable to evaluate its validity, which reaffirms the wisdom of adhering to
Chenery
's rule that the soundness of an agency's decision must rest on the reasoning contained therein, and not on any post hoc justifications offered by counsel.
Chenery Corp.
,
The NRC brief posits that "the Commission reasonably left the license in place-thereby ensuring NRC's continued ability to enforce the cultural-resource protections the license already imposes on Powertech-while allowing the agency to address the procedural deficiencies identified by the Board." NRC Br. 35 (citing, by analogy,
Ctr. for Biological Diversity v. EPA
,
Reference
- Full Case Name
- OGLALA SIOUX TRIBE, Petitioner v. U.S. NUCLEAR REGULATORY COMMISSION and United States of America, Respondents Powertech (Usa), Inc., Intervenor
- Cited By
- 31 cases
- Status
- Published