Old Dominion Elec. Coop. v. Fed. Energy Regulatory Comm'n
Old Dominion Elec. Coop. v. Fed. Energy Regulatory Comm'n
Opinion
In the past, electric utilities in the mid-Atlantic region have shared the costs of high-voltage transmission lines, which benefit the entire region. In 2015, some of these utilities proposed to eliminate cost sharing for projects undertaken only to satisfy an individual utility's planning criteria, including projects that involve high-voltage lines. The Federal Energy Regulatory Commission approved this change and applied it to deny cost sharing for projects to rebuild two high-voltage lines. The petitioners, whose local zone now must bear the entire cost of these two projects, contend that FERC's decisions were unlawful or inadequately explained.
I
A
The Federal Power Act gives FERC jurisdiction over facilities that transmit electricity in interstate commerce.
See
To promote more efficient coordination among electric utilities, FERC has promulgated a regulation known as "Order No. 1000." Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities,
This case involves disputes within a planning region encompassing much of the Mid-Atlantic and part of the Midwest. In this region, the transmission of electricity is overseen by PJM Interconnection, LLC, which controls but does not own the facilities of its member utilities. ("PJM" refers to P ennsylvania, New J ersey, and M aryland-the first three states in which PJM operated.) The region is subdivided into zones that correspond to areas served by each individual utility. The utilities are governed by the PJM Operating Agreement, which sets forth the respective rights and duties of PJM and its members, and the PJM Open Access Transmission Tariff, which details the terms on which the utilities provide service.
To comply with the regional-planning requirement of Order No. 1000, PJM-member utilities maintain a Regional Transmission Expansion Plan. Schedule 6 of the Operating Agreement specifies what kind of projects must be included in this Regional Plan. As relevant here, Schedule 6 designates three categories of projects for inclusion in the Plan: (1) projects to satisfy PJM's own planning and reliability criteria; (2) projects to satisfy reliability criteria developed by standard-setting organizations such as the North American Electric Reliability Corporation ("NERC"); and (3) projects to satisfy planning criteria established by individual utilities. The utilities submit their individual planning criteria both to FERC, on a document called Form 715, and to PJM.
Schedule 12 of the Tariff addresses the cost-sharing requirements of Order No. 1000. Before 2015, Schedule 12 required regional cost sharing for all "Regional Facilities," which it defined as projects that were (a) included in the Regional Plan to satisfy any of the planning criteria described above and (b) particular kinds of high-voltage projects. Schedule 12 also establishes the cost-allocation formula for such Regional Facilities. Half of these costs are allocated on a pro rata basis, based on the level of customer demand within each zone, regardless of where the specific project at issue is located. This method of cost allocation is called the "postage stamp" approach. The remaining costs are allocated based on an estimate of which zones most directly benefit from the project at issue, as made under what is called a "distribution factor ('DFAX') analysis." In contrast, the costs of lower-voltage facilities, which generally do not qualify *1257 as "Regional Facilities," are allocated solely under a DFAX analysis.
As required by Order No. 1000, PJM submitted this cost-allocation methodology to FERC, which approved it in March 2013.
PJM Interconnection, LLC
,
B
Petitioners are three Virginia-based members of PJM-Old Dominion Electric Cooperative, Dominion Energy Services, Inc., and Virginia Electric & Power Co. d/b/a Dominion Energy Virginia (collectively "Dominion"). In July 2013, Dominion proposed to rebuild an aging high-voltage transmission line between Elmont and Cunningham, Virginia. The project initially did not qualify for cost sharing because it was unnecessary to satisfy the extant planning and reliability criteria of PJM, NERC, or Dominion.
In September 2014, Dominion adopted its own "end of life" planning criteria, submitted the criteria on Form 715 to FERC, and presented them to a PJM planning committee. Dominion concluded that replacing the Elmont-Cunningham line was necessary to satisfy these new criteria. PJM reviewed the project and agreed.
In March 2015, PJM initiated the first of three proceedings at issue here-the "Elmont-Cunningham Proceeding"-by filing with FERC proposed cost allocations for the Elmont-Cunningham project. Under Schedule 12's hybrid methodology for high-voltage facilities, nearly half of the costs would be allocated to Dominion; the remaining costs would be spread among 23 other utilities, with shares ranging from roughly 8% to 0.1%. Dayton Power and Light Co., an Ohio-based utility, intervened in the proceeding and objected. Dayton, which would be responsible for roughly 1% of the costs, complained that Dominion had unilaterally imposed costs on other utilities by adopting new end-of-life criteria.
Six days after PJM initiated the Elmont-Cunningham Proceeding, a group of member utilities opposed to the proposed cost sharing initiated the second proceeding at issue-the "Cost-Allocation Proceeding." The utilities proposed to amend Schedule 12 of the Tariff to prohibit cost sharing for any project included in the Regional Plan only to satisfy individual utilities' planning criteria. Under the proposed amendment, all costs for such projects would be "allocate[d] ... to the local zone of the transmission owner that filed the planning criteria," regardless of whether the project produced regional benefits. J.A. 55. Dominion opposed the amendment as inconsistent with the cost-causation principle.
FERC initially rejected the utilities' proposed amendment on two grounds. In part, FERC concluded that the amendment violated
*1258
Order No. 1000 by creating a category of projects selected for cost allocation but not subject to the approved cost-allocation formula.
See
PJM Interconnection, LLC
,
Meanwhile, in the Elmont-Cunningham Proceeding, FERC ordered a technical conference to address how PJM satisfies its regional-planning obligations under Order No. 1000.
PJM Interconnection, LLC
,
After the technical conference, FERC reversed course and accepted the tariff amendment.
PJM Interconnection, LLC
,
On the same day, FERC rejected PJM's proposed cost allocation for the Elmont-Cunningham project.
PJM Interconnection, LLC
,
Commissioner LaFleur dissented in part from both orders. In the Cost-Allocation Proceeding, she would have narrowed the amendment to "preserv[e] the current regional cost allocation for certain high voltage projects, even if those projects are selected solely to address local planning criteria." Cost-Allocation Order,
Before FERC issued these decisions, PJM had initiated the third and final proceeding at issue-the "Cunningham-Dooms Proceeding." It involved Dominion's proposal to rebuild a high-voltage line from Cunningham to Dooms, Virginia, as required by Dominion's end-of-life criteria. In July 2016, FERC applied its Cost-Allocation Order to reject PJM's proposed cost allocation, once again over Commissioner LaFleur's dissent.
See
PJM Interconnection, LLC
,
After unsuccessfully seeking rehearing of the three orders, Dominion timely sought judicial review in this Court.
II
Before addressing Dominion's challenge to FERC's decision to accept the tariff amendment, we must first determine what the amendment says and how it operates. On that question, Intervenors LSP Transmission Holdings, LLC and Northeast Transmission Development, LLC contend that the amendment, properly construed, violates Order No. 1000 by refusing to apply the approved cost-allocation formula to projects selected for cost allocation. FERC initially adopted this argument,
FERC contends that we should not address an argument raised only by intervenors. As a general matter, an intervenor "may join only on a matter that has been brought before the court by a petitioner."
E. Ky. Power Co-op., Inc. v. FERC
,
The amendment requires the costs of projects included in the Regional Plan to satisfy only Form 715 planning criteria to be allocated entirely to the zone of the utility that filed the criteria, "[n]otwithstanding" other provisions of Schedule 12. Tariff, Schedule 12(xv) (J.A. 72). The intervenors contend that the "notwithstanding" proviso should be read to apply only after a project has been deemed a Regional Facility, and therefore selected in the Regional Plan for cost sharing. Under that interpretation, the amendment would violate Order No. 1000, which requires utilities to have in place "a regional cost allocation method for any transmission facility selected in a regional transmission plan for purposes of cost allocation."
FERC ultimately concluded that the amendment creates a category of projects included in the Regional Plan but not selected for cost sharing.
See
Cost-Allocation Order,
Although we reject the intervenors' proposed construction of the amendment, their argument does highlight something unusual about Order No. 1000-it requires a pre-approved formula for projects "selected" by member utilities for regional cost sharing, and it requires the formula to be consistent with the cost-causation principle, but it appears largely silent on which projects may or must be selected for cost sharing. We elaborate on that point below.
III
Dominion contends that FERC arbitrarily violated the cost-causation principle by accepting the tariff amendment and applying it to prevent any cost sharing for the two high-voltage projects at issue here. As noted above, the cost-causation principle requires "comparing the costs assessed against a party to the burdens imposed or benefits drawn by that party."
Midwest ISO Transmission Owners
,
Under the arbitrary-and-capricious standard of review, we uphold FERC decisions if the agency has "examined the relevant considerations and articulated a satisfactory explanation for its action, including a rational connection between the facts found and the choice made."
FERC v. Elec. Power Supply Ass'n
, --- U.S. ----,
A
Application of the cost-causation principle is simple here, because this critical point is undisputed: high-voltage power lines produce significant regional benefits within the PJM network, yet the amendment categorically prohibits any cost sharing for high-voltage projects like those at issue here.
In the various proceedings below, no party challenged, and FERC did not disavow, any of its findings in the PJM Compliance Order. There, in approving the original Tariff, the Commission found that "high-voltage transmission facilities have significant regional benefits that accrue to all members of the PJM transmission system."
Historically, FERC has pressed this view even farther. For years prior to Order No. 1000, FERC took the position that the cost of high-voltage transmission lines within PJM should be shared based
entirely
on the postage-stamp method, on the theory that "everyone benefits from high-capacity transmission facilities because they increase the reliability of the entire network."
Ill. Commerce Comm'n
,
Given the significant regional benefits of high-voltage transmission lines, FERC's decision to approve the amendment was arbitrary. As explained above, the amendment denies cost sharing for
all
projects included in the Regional Plan only to satisfy the planning criteria of individual utilities-
including
for high-voltage lines. The amendment thus produces a severe misallocation of the costs of such projects. Here, for example, under the methodology previously endorsed by FERC as fairly matching costs to benefits, Dominion was estimated to enjoy only about 47% of the benefits from the Elmont-Cunningham project, and 43% of the benefits from the Cunningham-Dooms project. Yet, under FERC's orders approving and applying the amendment, Dominion would have to pay all of the costs of both projects. This does not amount to a quibble about "exacting precision,"
Midwest ISO Transmission Owners
, 373 F.3d at 1369, or a tempering of the cost-causation principle in pursuit of "competing goals,"
S.C. Pub. Serv. Auth. v. FERC
,
B
In the administrative proceedings, FERC did not attempt to justify its orders as a lawful departure from the cost-causation principle. Instead, FERC asserted three possible grounds for reconciling its orders with that principle. None of them is persuasive.
First, FERC noted that, of the 303 projects previously included in the Regional Plan based only on individual utilities' planning criteria, 98% of them produced only local benefits. Therefore, FERC reasoned, allocating all of the costs of these projects to the local utility at least roughly matched costs to benefits.
See
Cost-Allocation Order,
FERC's statistics misleadingly aggregate two very different categories of projects. As Commissioner LaFleur explained, the 98% of projects that produced no regional benefits involved
low
-voltage facilities.
See
Cost-Allocation Order,
Of course, a regulator need not always carve out exceptions for arguably distinct subcategories of projects. But here, it is undisputed that high-voltage and low-voltage projects are significantly different with regard to which utilities benefit from them. Moreover, FERC itself has long recognized these differences in making appropriate cost allocations-including for PJM.
See
,
e.g.
, PJM Compliance Order,
In a variation on this theme, FERC invokes the cost-allocation regime for another planning region in the Midwest.
See Midwest Indep. Transmission Sys. Operator, Inc.
,
Again, however, FERC combines dissimilar categories of projects. As explained above, the 98% of projects highlighted by FERC are low-voltage ones with no regional benefits, whereas the 2% of projects targeted by the amendment are high-voltage ones conceded by FERC to have significant regional benefits. Moreover, the MISO order was supported by a finding that the benefits of the projects at issue there were "realized primarily in the pricing zone in which the project is located."
Second, FERC reasoned that projects included in the Regional Plan to satisfy only individual utilities' planning criteria "are not needed to meet PJM regional criteria or NERC reliability standards." Cost-Allocation Order,
Finally, FERC appears to claim affirmative support from its conclusion that the amendment is consistent with Order No. 1000.
See
Cost-Allocation Order,
IV
We are sensitive to the concern, pressed by Dayton and the other amici supporting FERC, that individual utilities should not have free rein to impose unjustified costs on an entire region by unilaterally adopting overly ambitious planning criteria. However, nothing we say here prevents PJM or its member utilities from amending the Tariff, the Operating Agreement, or PJM's own planning criteria to address any problem of prodigal spending, to establish appropriate end-of-life planning criteria, or otherwise to limit regional cost sharing-as long as any amendment respects the cost-causation principle. Indeed, the cost-causation principle, by allocating project costs consistent with project benefits, creates the best incentives for PJM member utilities themselves to agree on when to invest their scarce resources in transmission improvements. Likewise, nothing we say prevents FERC from trimming excessive spending in the course of exercising its overarching mandate to ensure just and reasonable rates. See 16 U.S.C. § 824d(a). Nor do we limit the ability of PJM or FERC to assess whether individual projects are in fact appropriate under the governing planning or reliability criteria. Finally, nothing we say constrains PJM's or FERC's ability to require competitive-bidding processes for regionally beneficial projects.
Instead, we hold only that FERC did not adequately justify its approval of the amendment at issue here, which prohibited cost sharing for a category of high-voltage projects conceded to have significant regional benefits, and which did so only because those projects reflected the planning *1264 criteria of individual utilities. The legal or economic merit of Dominion's particular end-of-life planning criteria, and the appropriateness of the Elmont-Cunningham and Cunningham-Dooms projects under those criteria, remain open issues on remand.
* * * *
The Commission acted arbitrarily and capriciously in approving the tariff amendment and applying it to the Elmont-Cunningham and Cunningham-Dooms projects. We therefore grant the petitions for review, set aside the orders under review to the extent that they approved the amendment and applied it to the two projects, and remand for further proceedings consistent with this opinion.
So ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.