Parker v. John Moriarty & Assocs. of Va., LLC
Parker v. John Moriarty & Assocs. of Va., LLC
Opinion of the Court
On September 16, 2015, Plaintiffs Johnnie Parker and Starrelette Gail Jones-Parker brought this action against Defendant John Moriarty & Associates of Virginia, LLC ("JMAV"). Plaintiffs alleged that JMAV, as general contractor of a construction project, was negligent resulting in serious injury to Mr. Parker, a construction worker on the project site. Defendant JMAV subsequently filed a Third-Party Complaint against Third-Party Defendant Strittmatter Metro, LLC ("Strittmatter"), and Strittmatter, in turn, filed a Fourth-Party Complaint against Fourth-Party Defendant Environmental Consultants and Contractors, Inc. ("ECC"). Subsequent procedural developments included Plaintiffs' amendment of their Complaint to add ECC as a Defendant. ECC also asserted counterclaims against Strittmatter and *227cross-claims against JMAV. JMAV in turn asserted cross-claims against ECC.
Presently before the Court are Strittmatter's [121] Motion for Summary Judgment, ECC's [122] Motion for Summary Judgment, and JMAV's [123] Motion for Summary Judgment on Count I and II of Its Amended Third Party Complaint. Upon consideration of the parties' submissions,
I. BACKGROUND
A. Factual Background and Procedural Posture
This case arises out of the construction work completed on the Apollo H Street Project ("the project"), located between 600 and 624 H Street, NE, Washington, D.C. Am. Compl., ECF No. 87, ¶ 13. The owner of the project, H Street NE Owner, LLC ("Owner"), hired JMAV to serve as general contractor and ECC to provide certain "professional environmental services." Id. ¶¶ 3, 6. JMAV subcontracted the excavation and related services to Strittmatter. Id. ¶ 5.
Johnnie Parker worked on the project as an employee of Strittmatter and alleges that on December 18, 2014, he was instructed to excavate between 600 and 624 H Street, NE. Id. ¶¶ 12, 22. While performing this work, Mr. Parker allegedly was injured upon exposure to toxic chemicals from leaking underground storage tanks. See id. ¶¶ 22-31. While Plaintiffs did not allege the specific location onsite where Mr. Parker was injured, the other parties generally agree that it was in the southwestern portion. See, e.g. , Strittmatter's *228Resp. to Statements of Undisputed Material Facts Submitted by JMAV and ECC, ECF No. 124-2, ¶ 37 (Resp. to Moriarity's [sic] Statement of Undisputed Material Facts).
On September 16, 2015, Mr. Parker and his wife, Starrelette Gail Jones-Parker, filed the underlying two-count Complaint against JMAV, claiming that 1) JMAV was liable for negligence, and 2) JMAV's alleged willful, or reckless and wanton, conduct entitled the Parkers to punitive damages. See Compl., ECF No. 1, ¶¶ 16-28. On November 6, 2015, JMAV filed a two-count Third-Party Complaint against Strittmatter, alleging that 1) Strittmatter was contractually obligated to indemnify JMAV, and 2) Strittmatter had breached its subcontract with JMAV. See Third-Party Compl., ECF No. 10, ¶¶ 21-33. JMAV sought summary judgment on its contractual indemnity claim against Strittmatter, which the Court denied on May 23, 2016. See Mem. Op., Parker v. John Moriarty & Assocs. (Parker I ),
On May 12, 2016, Strittmatter filed a four-count Fourth-Party Complaint against ECC, asserting claims of 1) negligence, 2) indemnity and/or contribution as a joint tortfeasor, 3) breach of contract to a third-party beneficiary, and 4) negligent misrepresentation. See Fourth-Party Compl., ECF No. 38, ¶¶ 40-65. ECC moved to dismiss the Fourth-Party Complaint on the grounds that Strittmatter failed to state claims in contract and in tort upon which relief could be granted, which the Court denied on December 14, 2016. See Mem. Op., Parker v. John Moriarty & Assocs. (Parker II ),
On January 17, 2017, Plaintiffs requested leave to amend their Complaint to assert a negligence claim against ECC, which the Court granted on February 16, 2017. See Mem. Op. & Order, Parker v. John Moriarty & Assocs. (Parker III ),
On February 15, 2017, ECC sought the Court's permission to amend ECC's [71] Answer to assert counterclaims against Strittmatter and cross-claims against JMAV based on allegations of 1) negligence, 2) negligent misrepresentation, and 3) indemnity and contribution. On the same day, JMAV requested leave to amend its [10] Third-Party Complaint against Strittmatter to add further details and a common law indemnity claim. The Court granted ECC's and JMAV's requests on April 6, 2017. See Mem. Op. and Order, Parker v. John Moriarty & Assocs. (Parker IV ),
The Court instructed JMAV and Strittmatter to respond to the new pleadings that the Court permitted to be filed against them. Parker IV ,
Pursuant to the Court's [120] Scheduling and Procedures Order, three of the four parties have moved for summary judgment as to at least some claims. ECC seeks summary judgment as to each claim against it, specifically Plaintiffs' claim of negligence, JMAV's claims of negligence, indemnity and/or contribution, breach of *229contract to a third-party beneficiary, and promissory estoppel, and Strittmatter's claims of negligence, indemnity and/or contribution, breach of contract to a third-party beneficiary, and negligent misrepresentation. ECC's Mot. Strittmatter's motion likewise challenges all claims against it, namely JMAV's claims of contractual indemnity, breach of contract, and common law indemnity, and ECC's claims of negligence, negligent misrepresentation, and indemnity and contribution. Strittmatter's Mot. Of the three movants, JMAV seeks the narrowest ruling, asking only for summary judgment on its contractual indemnity and breach of contract claims against Strittmatter. JMAV's Mot. Upon conclusion of briefing, all three motions are ripe for resolution.
B. Relevant Reports, Agreements, and Safety Plans
The Court shall summarize the reports, agreements, and safety plans that are pertinent to the resolution of the pending motions. This is not the first time that the Court has needed to consider the intersections of documents at issue in this case. See, e.g. , Parker II ,
Taken chronologically, the first key document is ECC's Phase I Environmental Site Assessment, dated March 20, 2014. ECC's Mot., Ex. F, ECF No. 122-6 ("2014 Report").
*230See, e.g. ,
Several agreements follow in close cluster and suggest by their chronological ordering that they were negotiated concurrently. Both these general contractor and excavation subcontractor agreements incorporate ECC's 2014 Report.
The Owner entered into an agreement with JMAV, as general contractor, on September 2, 2014. JMAV's Opp'n to ECC's Mot., Ex. 5, ECF No. 129-6 ("Owner/JMAV Agreement"). JMAV's obligations under the agreement include "design/build responsibility" for "support of excavation."
JMAV's subcontract signed shortly beforehand also incorporates the 2014 Report. JMAV subcontracted with Strittmatter on August 12, 2014, to cover JMAV's (then-forthcoming) obligations to the Owner for excavation services. See JMAV's Mot., Ex. 8, ECF No. 123-10 ("JMAV/Strittmatter Agreement"), at 2-3, 6. Like the Owner/JMAV Agreement, the "Scope of Work" exhibit to the JMAV/Strittmatter Agreement carves out "[s]oil and [m]aterial [t]esting (by Owner)" and "[c]ontaminated soils" from the scope of Strittmatter's responsibility.
In between the conclusion of the JMAV/Strittmatter Agreement on August 12, 2014, and the Owner/JMAV Agreement on September 2, 2014, ECC produced its Voluntary Remediation Action Plan ("VRAP") on August 22, 2014. ECC's Mot., Ex. N, ECF No. 122-14 ("VRAP"). The cover page indicates that the VRAP was "[p]repared for" the Owner and "[s]ubmitted to" several District of Columbia officials.
As contemplated by the VRAP, ECC's Environmental Health and Safety and Impacted Material Management Plan ("EHASP") also appears in the record, as a revised version dated September 8, 2014. ECC's Mot., Ex. M, ECF No. 122-13 ("EHASP"). The EHASP likewise indicates that it was prepared for the Owner and submitted to District of Columbia officials, and that it draws on the 2014 Report.
The EHASP sets forth in some detail the safety responsibilities of parties at the project site, including ECC, the general contractor (i.e., JMAV), and subcontractors (e.g., Strittmatter).
Under the EHASP, JMAV's obligations as general contractor entail "overall responsibility for monitoring and enforcing all aspects of site safety, including construction safety and all other safety, health, and OSHA related requirements."
JMAV and Strittmatter have obligations as "contractors [and] subcontractors" to "read this EHASP in its entirety and 'sign-off' to acknowledge their understanding of site conditions and hazards, and safety protocol prior to entry to the exclusion zone."
To name a few more cross-cutting obligations under the EHASP, "[t]he Site Safety Officer and the Environmental Technician will monitor soil excavation activities."Id. at 20. "Care should be taken by all site personnel during excavation operations to avoid possible chemical and physical hazards."
Last in time among the key documents is the agreement between the Owner and ECC entered into on November 1, 2014.
*233ECC's Mot., Ex. B, ECF No. 122-2 ("Owner/ECC Agreement"). ECC commits in the "Scope of Services" exhibit to "implement the [V]RAP for the Project" and "provide Environmental Oversight services as detailed in [ECC's EHASP] for the Project, dated August 22, 2014," "includ[ing] implementation of EHASP."
II. LEGAL STANDARD
Summary judgment is appropriate where "the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). The mere existence of some factual dispute is insufficient on its own to bar summary judgment; the dispute must pertain to a "material" fact.
In order to establish that a fact is or cannot be genuinely disputed, a party must (a) cite to specific parts of the record-including deposition testimony, documentary evidence, affidavits or declarations, or other competent evidence-in support of its position, or (b) demonstrate that the materials relied upon by the opposing party do not actually establish the absence or presence of a genuine dispute. Fed. R. Civ. P. 56(c)(1). Conclusory assertions offered without any factual basis in the record cannot create a genuine dispute sufficient to survive summary judgment. See Ass'n of Flight Attendants-CWA, AFL-CIO v. U.S. Dep't of Transp. ,
When faced with a motion for summary judgment, the district court may not assess credibility or weigh evidence; instead, the evidence must be analyzed in the light most favorable to the non-movant, with "all justifiable inferences ... drawn in his favor." Anderson ,
III. DISCUSSION
Whether grounded in common law or contract, the causes of action at issue in these motions generally turn on an assessment of the parties' respective duties regarding worker safety on the project site. Those duties arise, if at all, from the intricate web of reports, agreements, and safety standards that involved the parties. Viewing the record evidence in the light most favorable to the non-movants, the Court finds genuine disputes of material fact as to the precise application of duties that these documents appear to create. The parties' divergent interpretations of these documents, coupled with differing accounts of the parties' practices at the project site, preclude the entry of summary judgment with respect to each claim except for ECC's counterclaim against Strittmatter for contribution. The Court shall grant summary judgment to Strittmatter on that counterclaim.
The Court shall discuss further as to each motion in turn, beginning with ECC's motion and continuing with Strittmatter's and then JMAV's. Because the Court is not the finder of fact as to at least some of the claims, the Court shall not touch on all of the parties' various relevant duties, nor shall it belabor its several explanations of genuine disputes of material fact.
A. ECC's Motion for Summary Judgment
ECC seeks summary judgment on all claims against it, namely negligence (alleged by Plaintiffs, JMAV, and Strittmatter), negligent misrepresentation (Strittmatter), breach of contract (JMAV and Strittmatter), promissory estoppel (JMAV), and common law indemnity and contribution (JMAV and Strittmatter). The Court shall explain why summary judgment is not available to ECC as to any of these claims.
1. Negligence and Negligent Misrepresentation Claims
ECC argues that it did not owe any duties under tort law that could sustain a negligence claim by the Plaintiffs, JMAV, or Strittmatter, or a negligent misrepresentation claim by Strittmatter. ECC's Mot. at 17, 22 n.2. Previously, the Court denied ECC's motion to dismiss because, as to Strittmatter's negligence and negligent misrepresentation claims, the Court could not "conclusively find that no such duty exists," in light of the Owner/ECC Agreement, the VRAP, and the EHASP, as well as applicable law. See Parker II ,
In the District of Columbia,
One who undertakes, gratuitously or for consideration, to render services to another which he should recognize as necessary for the protection of a third person or his things, is subject to liability to the third person for physical harm resulting from his failure to exercise reasonable care to protect his undertaking, if
(a) his failure to exercise reasonable care increases the risk of such harm, or
(b) he has undertaken to perform a duty owed by the other to the third person, or
(c) the harm is suffered because of reliance of the other or the third person upon the undertaking.
Id. at 889 (quoting Restatement (Second) of Torts § 324A (Am. Law Inst. 1965) ). While the District of Columbia Court of Appeals has not "formally adopted" the Second Restatement, that court has found that the "particular concept" embodied by Section 324A is among those that are "well known and [have] been readily applied, where appropriate." Haynesworth ,
In Presley , the District of Columbia Court of Appeals found that a consultant need not have foreseen that its services were necessary for the protection of a worker injured on a construction site. See
Viewing the record evidence in the light most favorable to the non-movants, the Court cannot conclude that ECC lacked a duty of care to the other parties at the project site. The finder of fact could determine, based on the Owner/ECC Agreement, that ECC was hired for an implementation role. See Owner/ECC Agreement at 11. ECC was required to implement two documents-namely the VRAP and the EHASP-that ECC itself had developed for the site based on its *236findings in the 2014 Report. See
The finder of fact could conclude that ECC should have foreseen the necessity of its services for the protection of others, at the least because ECC's failure to exercise reasonable care in its monitoring could increase the risk of harm to construction workers like Mr. Parker, and JMAV and Strittmatter might have relied on ECC for adequate air monitoring while Mr. Parker excavated. ECC has not discharged its burden to establish that there is no dispute of material fact, and that it is entitled to judgment as a matter of law, based on its assertion that it had no duty of care to the other parties at the job site.
ECC's effort to dispose of Strittmatter's negligent misrepresentation claim fails for the same reason.
Under District of Columbia law, a plaintiff alleging negligent misrepresentations or omissions must show (1) the defendant made a false statement or omission of a fact, (2) the statement or omission was in violation of a duty to exercise reasonable care, (3) the false statement or omission involved a material issue, and (4) the plaintiffs reasonably and to their detriment relied on the false information.
Regan v. Spicer HB, LLC ,
2. Breach of Contract Claims
As it did in opposing Strittmatter's motion to dismiss, ECC again argues that Strittmatter, and now JMAV as well, are only incidental third-party beneficiaries of the Owner/ECC Agreement, rather than intended third-party beneficiaries who could pursue damages for breach thereof. See ECC's Mot. at 22. The Court denied ECC's motion to dismiss because the evidence at that stage was "in equipoise"
*237as to Strittmatter's status. Parker II ,
"Generally, a stranger to a contract may not bring a claim on the contract." Fort Lincoln Civic Ass'n, Inc. v. Fort Lincoln New Town Corp. ,
(1) Unless otherwise agreed between promisor and promisee, a beneficiary of a promise is an intended beneficiary if recognition of a right to performance in the beneficiary is appropriate to effectuate the intention of the parties and either
(a) the performance of the promise will satisfy an obligation to pay money to the beneficiary; or
(b) the circumstances indicate that the promisee intends to give the beneficiary the benefit of the promised performance.
Instead of focusing on this District of Columbia authority,
As articulated above, on-point authority is available in this jurisdiction. ECC does cite to one controlling authority that, at least superficially, runs in its favor. See ECC's Reply at 9-10 n.6 (citing Presley ,
As the Court previously has recognized, the Owner/ECC Agreement does not refer to Strittmatter by name, but the Court has found other factors that could indicate the contracting parties' intent to benefit Strittmatter. Parker II ,
*239safety monitoring). Furthermore, the Agreement obligates ECC to coordinate with the Owner's "Contractor." Owner/ECC Agreement at 2 (Art. 1(f) ) ("[N]othing herein is intended to relieve Consultant of its obligation to coordinate its Services with the services performed by the Owner's Contractor, consultants and design professionals."). Without the benefit of further definition in the Owner/ECC Agreement, the finder of fact could construe "Contractor" as JMAV and possibly also as Strittmatter, for Strittmatter assumed JMAV's obligations to the Owner with respect to excavation. The Agreement also contemplates that other parties on the project site may want to rely on ECC's "reports ... and any other information generated by [ECC] for the Project," which reliance the Agreement prohibits "without the prior written consent of Owner."
Viewed in the light most favorable to JMAV and Strittmatter, the Owner/ECC Agreement recognizes that any party receiving the Owner's prior written consent is entitled to rely on information originally generated by ECC, and accordingly the Owner, as promisee, "intends to give [that] beneficiary the benefit of [ECC's] promised performance." Fort Lincoln Civic Ass'n, Inc. ,
There is sufficient evidence in the record to create, at the least, a genuine dispute of material fact as to whether JMAV and Strittmatter were intended beneficiaries of the Owner/ECC Agreement. The finder of *240fact could determine both that "recognition of a right to performance in the beneficiary [i.e., JMAV and Strittmatter] is appropriate to effectuate the intention of the parties [i.e., Owner and ECC]," and that "circumstances indicate that the promisee [i.e., Owner] intend[ed] to give the beneficiary the benefit of the promised performance." Fort Lincoln Civic Ass'n, Inc. ,
3. Promissory Estoppel Claim
ECC also challenges JMAV's promissory estoppel claim. "In order to find a party liable on a theory of promissory estoppel, there must be evidence of a promise, the promise must reasonably induce reliance upon it, and the promise must be relied upon to the detriment of the promisee." Plesha , 725 F.Supp.2d at 111-12 (quoting Simard v. Resolution Trust Corp. ,
At the threshold, the Court rejects ECC's attempt to argue that promissory estoppel is unavailable based on language in the Owner/JMAV Agreement and EHASP. See ECC's Reply at 14 (citing D.C. Oil, Inc. v. ExxonMobil Oil Corp. ,
ECC argues that JMAV's promissory estoppel claim fails because ECC did not make any promises to JMAV. ECC's Mot. at 28. ECC amplifies the argument in its Reply by asserting that only a "direct" promise from ECC to JMAV counts. ECC Reply at 12. But ECC has evidently manufactured that notion, as it cites no case law in support (or in opposition). In the Court's view, both parties miss key language, among the thicket of documents, that could be construed as a promise to JMAV, whether or not that promise is "direct." The "Review and Approval" page of the EHASP provides that "[t]he undersigned," which includes at least ECC, "agree to abide by the safety and health requirements and procedures outlined in this document." EHASP at 3. Those requirements and procedures would seem to include ECC's commitment to monitor air using a PID "as [excavation] work progresses."
*241EHASP at 19. The finder of fact could reasonably understand this as a promise on the part of ECC, notwithstanding any obligations JMAV also had to monitor site safety. And while those to whom ECC's purported promise is directed may include the Owner and D.C. officials, for whom the EHASP was "prepared" and to whom it was "submitted," respectively, the finder of fact could also determine that promisees include other signatories to the EHASP that likewise are agreeing to abide by the document. See EHASP at 1 (cover page referring to Owner and D.C. officials). The record lacks any firm indication that JMAV signed a copy of the EHASP, but the document suggests that it has been reviewed by Strittmatter and therefore likely by JMAV as well. See id. (indicating that "[t]his document has been reviewed by the undersigned representatives of companies performing earthwork, excavation, ... and related development activities" on site).
The Court need not reach the questions of whether any promise by ECC reasonably induced reliance, and whether JMAV so relied, to its detriment. Genuine disputes of material fact remain as to the evidence of a promise that preclude a ruling at this stage in ECC's favor.
4. Common Law Contribution and Indemnity
ECC also moves for summary judgment as to JMAV's and Strittmatter's claims for "common-law contribution and indemnification,"
B. Strittmatter's Motion for Summary Judgment
Strittmatter seeks a favorable ruling on other parties' claims of negligence and negligent misrepresentation (alleged by ECC), breach of contract (JMAV), common law indemnity (ECC and JMAV), contribution (ECC), and contractual indemnity (JMAV). With the exception of ECC's counterclaim for contribution, Strittmatter has not carried its burden as to any of these claims.
1. District of Columbia Worker Compensation Act
At the threshold, the Court shall address Strittmatter's argument that certain claims against it are prohibited under the District of Columbia Worker Compensation Act,
Previously, the Court rejected Strittmatter's argument that it necessarily would be futile, under the WCA, for ECC to bring its negligence, negligent misrepresentation, and common law indemnity and contribution claims against Strittmatter. See Parker IV ,
The liability of an employer ... [under the workers' compensation provision] shall be exclusive and in place of all liability of such employer to the employee, his legal representative, spouse or domestic partner, parents, dependents, next of kin, and anyone otherwise entitled to recover damages from such employer at law on account of ... [the employee's] injury or death.
The Court likewise dealt with the WCA hurdle when it granted JMAV's motion to file an amended third-party complaint, which added, inter alia , JMAV's common law indemnity claim against Strittmatter. See id. at 513-14. JMAV too had alleged that Strittmatter had duties independent of Mr. Parker's incident that could support a finding of "special and ongoing relationship," here between the general contractor and subcontractor. Id. at 514-15 (citing Howard Univ. ,
The Court shall deal further below with whether Strittmatter has carried its burden, at the summary judgment stage, as to ECC's and JMAV's common law indemnity claims. It suffices here to recognize that the WCA's exclusivity provision is not a per se bar to those claims. Rather, the Court shall need to evaluate whether Strittmatter has a special relationship with ECC and JMAV that could bring their *243claims within the exception recognized in this jurisdiction for instances in which an employer has independent duties grounded in a special relationship with third parties. See Howard Univ. ,
In its prior discussion of the WCA, this Court did not directly and expressly address the effect of the WCA on ECC's claims for contribution and for negligence and negligent misrepresentation, or on JMAV's claims for breach of contract and contractual indemnity. It is important at this stage, however, to distinguish between third parties' efforts to recover from an employer under a common law indemnity theory and those efforts to do so under other theories. The case law in this jurisdiction that permits recovery against an employer-otherwise protected under the WCA-when the parties have a "special relationship," appears to have been developed primarily for situations in which a party seeks indemnity from the employer at common law. See generally, e.g. , Howard Univ. ,
The Court finds that ECC's effort to obtain contribution at common law fails as a matter of law. "Contribution is based on the principle that a party who discharges a liability shared with another should not bear the sole obligation for payment." Hinton ,
On the other hand, JMAV's claim for contractual indemnity against Strittmatter is not barred by the exclusivity provision. Strittmatter does not allege that the exclusivity provision so operates, but the Court addresses it here in the interest of completeness. In Myco , the D.C. Court of Appeals recognized that a contractual indemnity claim falls outside the scope of claims prohibited under the WCA because, in the event of a contractual indemnity provision:
the duty involved is one voluntarily accepted by the employer and existing separate and apart from either of the parties' relationships with the injured employee. Consequently, the duty is not one which arises "on account of" the employee's injury and thus is not covered by the statute.
The Court is left to determine the effects of the WCA's exclusivity provision on ECC's negligence and negligent *244misrepresentation claims and JMAV's breach of contract claim. Strittmatter does not cite any authority-aside from the plain text of the WCA's exclusivity provision-in support of its argument that ECC's negligence and negligent misrepresentation claims are barred by that provision. See Strittmatter's Mot. at 22; Strittmatter's Reply at 10-11. Strittmatter does not argue that JMAV's breach of contract claim is barred by the exclusivity provision. Accordingly, the Court shall proceed to consider the merits of the negligence, negligent misrepresentation, and breach of contract claims. In any event, the Court is of the view that the WCA exclusivity provision does not bar these claims against Strittmatter, for the same reasons that actions for contractual indemnity are not so barred. JMAV's breach of contract claim, like its contractual indemnity claim, should survive the WCA exclusivity bar because Strittmatter shouldered certain duties voluntarily upon entering into contract with JMAV, and those duties exist "apart from either of the parties' relationships with the injured employee." Myco, Inc. ,
The Court now turns to the merits of claims against Strittmatter that are not barred by the WCA.
2. Negligence and Negligent Misrepresentation Claims
Strittmatter argues that ECC's negligence and negligent misrepresentation claims alike fail for one reason: Strittmatter lacked "any duty" to ECC. Strittmatter's Mot. at 19. But Strittmatter is unable to carry its burden as to either claim.
As with ECC's motion, the Court shall again apply the Second Restatement's standard for third-party liability on a negligence claim. The Court considers whether Strittmatter "under[took], gratuitously or for consideration, to render services to another which [it] should [have] recognize[d] as necessary for the protection of a third person or his things." Presley ,
As ECC observes, the JMAV/Strittmatter Agreement deems Strittmatter's "coordination and cooperation" with third parties on site to be an "essential term" under that agreement:
Subcontractor shall coordinate and cooperate in all respects , during every phase of Subcontractor's performance of the Work, with Owner, Contractor, Architect, other Subcontractors, and any public authority or third party who may be employed or engaged in activity on or near the site in relation to the Project . Subcontractor recognizes and acknowledges that its coordination and cooperation obligations are essential terms of the Subcontract . Subcontractor acknowledges that the project is in a congested site and agrees to work in close coordination with other trades in order to maintain all schedules and phases of work.
*245JMAV/Strittmatter Agreement at 19 (Ex. B) (emphasis added); see ECC's Opp'n to Strittmatter's Mot. at 4. Strittmatter concedes that it "was responsible ... for coordinating [its] work [e.g., of "digging holes"] with others onsite." Strittmatter's Reply at 10. But Strittmatter seems to dispute the full implications of the JMAV/Strittmatter Agreement language when Strittmatter asserts that "[t]he Subcontract does not require Strittmatter to perform any work related to environmental controls at the site nor does it require any specific communications with or obligations to ECC ." Strittmatter's Statement of Undisputed Material Facts, ECF No. 121-2, ¶ 16 (emphasis added). Whatever specific communications the JMAV/Strittmatter Agreement may have required, or not required, Strittmatter does not dispute that it had "daily on-site conversations" with JMAV and ECC representatives as to "where the work would occur each day, so ECC could coordinate its work at the Apollo jobsite." Strittmatter's Resp. to Statements of Undisputed Material Facts Submitted by JMAV and ECC, ECF No. 124-2, ¶ 53 (Resp. to ECC's Statement of Undisputed Material Facts); see also id. ¶¶ 54-55 (indicating that these conversations would "direct[ ]" ECC as to excavation location).
Strittmatter's efforts to defend against ECC's negligent misrepresentation claim also fail. In arguing that it has no duty to ECC, Strittmatter evidently attempts to prove that the second prong of the negligent misrepresentation test cannot be satisfied. See Regan ,
3. Breach of Contract
Strittmatter challenges JMAV's breach of contract claim as nothing more than a re-styled indemnity claim, and accordingly defends only on that basis. See Strittmatter's Mot. at 7. But Strittmatter cites no authority for this position. JMAV, in turn, responds to Strittmatter's motion by discussing only indemnity issues. See generally JMAV's Opp'n to Strittmatter's Mot. Yet, the Court is unpersuaded that JMAV's breach of contract claim should *246simply be lumped together with its indemnity claim.
In order to prove that it did not breach its contract with JMAV, Strittmatter's defense should include a showing that it lacked relevant contractual obligations to JMAV, or, if it concedes such obligations, that Strittmatter did not breach them. Cf. Winston & Strawn LLP v. Law Firm of John Arthur Eaves ,
4. Common Law Indemnity
The Court returns to the issue of whether Strittmatter can prevail as to JMAV's and ECC's common law indemnity claims, notwithstanding the Court's finding above that they are not barred per se by the WCA.
"Indemnity is a common law remedy which shifts a monetary loss from one compelled to pay it to another whom equity dictates should bear it instead." Myco, Inc. ,
At the threshold, Strittmatter argues that the presence of a contractual indemnity provision between JMAV and Strittmatter bars JMAV from recovering on a common law indemnity claim. Strittmatter's Mot. at 8-9. But, as JMAV points out, this construction would seem to ignore contractual language that expressly contemplates permitting common law indemnity claims to proceed. See JMAV's Opp'n to Strittmatter's Mot. at 14-15; JMAV/Strittmatter Agreement at 10 ("Such obligation [of contractual indemnity] shall not be construed to negate, or abridge, or otherwise reduce any other right or obligation of indemnity which would otherwise exist as to any party or person described in this Paragraph 11.11."). Strittmatter does not respond to this citation of pertinent contractual language. Absent a reason to do so, this Court shall not adopt a construction of contractual language, agreed upon by the parties, that would seem to "render the provision meaningless." Princemont Constr. Corp. v. Baltimore & Ohio R.R. Co. ,
As third parties to the employer-employee relationship, JMAV and ECC can recover on their common law indemnity claims against Strittmatter only if their claims fit within an exception to the WCA. The Court agrees with Strittmatter and ECC-JMAV does not comment-that the District of Columbia does not employ the active/passive theory of implied-in-law indemnity. See Hinton ,
Strittmatter argues that it lacked an independent duty to JMAV and ECC that could give rise to implied-in-fact indemnity. Strittmatter's Mot. at 9-10. But based on the JMAV/Strittmatter Agreement and the parties' daily conversations at the project site, the Court has already determined above that the finder of fact could discern that Strittmatter had a duty to inform ECC as to where excavation would be occurring each day. The finder of fact likewise could determine that the same contractual language and on-site conversations support a duty to inform JMAV. The "coordination and cooperation" clause in the JMAV/Strittmatter Agreement expressly applied to Strittmatter's interaction with JMAV, defined as the "Contractor," just as it also expressly applied to third parties on site such as ECC. See *248JMAV/Strittmatter Agreement at 19 (Ex. B). Moreover, the daily coordination meetings-suggesting at least one means by which contractual coordination was to take place-included JMAV. See Strittmatter's Resp. to Statements of Undisputed Material Facts Submitted by JMAV and ECC, ECF No. 124-2, ¶ 53 (Resp. to ECC's Statement of Undisputed Material Facts). While JMAV would not be using information from Strittmatter in order to determine where to take air measurements, the finder of fact could determine that JMAV could use this information as part of its "overall responsibility" to ensure site safety. EHASP at 7.
Because the finder of fact could discern that Strittmatter owed duties to JMAV and ECC, independent of the incident involving Mr. Parker, the Court need not reach the issue of Strittmatter's special relationship with JMAV and ECC. The Court finds that genuine disputes of material fact regarding Strittmatter's duties preclude Strittmatter from obtaining summary judgment as to JMAV's and ECC's common law indemnity claims.
5. Contractual Indemnity
Strittmatter also seeks summary judgment as to JMAV's contractual indemnity claim, which the Court determined above is not barred by the WCA's exclusivity provision. JMAV's claim is based on the following language in the JMAV/Strittmatter Agreement:
To the fullest extent permitted by the law of the District of Columbia, the Subcontractor [Strittmatter] shall indemnify and hold harmless the Owner, the Architect and the Contractor [JMAV] and all of their agents and employees from and against all claims, damages, losses and expenses, including but not limited to attorney's fees, caused by, arising out of, in connection with, or resulting from the performance of the Subcontractor's Work under this Subcontract, where any such claim, damage, loss or expense is attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible property including the loss of use resulting therefrom, and is caused by or arises in whole or in part, from any negligent or non-negligent act or omission of the Subcontractor or any of its agents, employees, sub-subcontractors or others ....
JMAV/Strittmatter Agreement at 10 (Art. 11.11.1). In the Court's decision denying JMAV's first motion for partial summary judgment, which the Court expressly incorporates herein, the Court determined whether the contract was ambiguous as a matter of law such that discovery would be necessary to fill the gap. See Parker I ,
Now in Strittmatter's motion for summary judgment on JMAV's claim, Strittmatter argues that the Court's first ruling precludes a finding that Strittmatter is contractually obligated to indemnify JMAV. See Strittmatter's Mot. at 5-8. Strittmatter's interpretation is incorrect. The issue is instead whether discovery has cleared up the ambiguity in the contractual language. Strittmatter has not cited any evidence in the record to resolve that ambiguity. Accordingly, the Court finds that Strittmatter has not carried its burden to prove that it is entitled to judgment as a matter of law on JMAV's contractual indemnity claim based on undisputed material facts.
C. JMAV's Motion for Partial Summary Judgment
As the Court has discussed, JMAV previously sought partial summary judgment as to the contractual indemnity claim in Count I of its Third-Party Complaint against Strittmatter, which the Court denied. Parker I ,
At the threshold, the Court reiterates its finding above that neither JMAV's contractual indemnity claim nor its breach of contract claim is barred by the WCA's exclusivity provision. But, for the reasons that follow, JMAV is unable to carry its burden as to either its contractual indemnity claim or its breach of contract claim.
1. Contractual Indemnity
The Court found above that Strittmatter did not discharge its burden to show that ambiguity in the JMAV/Strittmatter Agreement's indemnity provision could be resolved in its favor based on facts presently in the record. The Court now finds that JMAV similarly has failed to cite any evidence that was not before the Court in Parker I to show that JMAV and Strittmatter intended the indemnity provision to cover JMAV's own negligence, if any. JMAV attempts instead to basically re-open the entirety of the Court's Parker I decision, urging again that the law supports its reading of the contractual language, as well as arguing that Strittmatter's and Mr. Parker's alleged negligence require Strittmatter to indemnify JMAV. See generally JMAV's Mot. (focusing on Strittmatter's and Mr. Parker's actions); JMAV's Reply (focusing on contractual interpretation and Strittmatter's actions). JMAV did not seek reconsideration of the *250Court's decision in Parker I , and the Court sees no reason now to revisit its prior finding that the contractual language was ambiguous.
JMAV's various arguments do not answer the question that remains, namely whether any evidence from outside of the contract can clarify whether the parties intended that JMAV could recover regardless of its negligence.
2. Breach of Contract
JMAV also seeks to recover for the alleged breach of Strittmatter's obligations under the JMAV/Strittmatter Agreement. JMAV's Mot. at 18-19. Strittmatter's opposition is limited to arguing that JMAV's breach of contract claim is effectively a recycled contractual indemnity claim. See Strittmatter's Opp'n to JMAV's and ECC's Mots. at 13. The Court has elsewhere rejected Strittmatter's attempt to lump ECC's negligence and negligent misrepresentation claims into its common law indemnity claim, in part for lack of authority supporting that notion. Here again, Strittmatter offers no authority for its assertion-in essence-that JMAV cannot separately pursue both contractual indemnity and breach of contract claims against Strittmatter springing from the injury to Mr. Parker.
In evaluating Strittmatter's motion for summary judgment as to JMAV's breach of contract claim, the Court found that Strittmatter failed to establish that it lacked contractual obligations to JMAV, and accordingly the Court declined to reach the issue of whether Strittmatter breached any such duties. Now that JMAV has the burden, the Court agrees that the record could support a finding that Strittmatter had certain safety obligations under the JMAV/Strittmatter Agreement. See JMAV's Mot. at 18-19 (arguing that those obligations included training employees). For example, "Subcontractor Foremen" were required to "train their employees to perform their work in a safe manner and to recognize and correct potential and actual hazards and unsafe acts." JMAV/Strittmatter Agreement at 52 (Ex. D). Accordingly, the Court proceeds to consider whether Strittmatter breached those obligations.
JMAV argues that Strittmatter "failed to provide [Mr. Parker with] any information about the existence, safe handling, or excavation of contaminated soil on *251the Apollo Project." JMAV's Mot. at 18-19 (citing Statement of Material Facts Not in Genuine Dispute, ECF No. 123-2 ("JMAV's Statement"), ¶¶ 31, 43). Strittmatter denies JMAV's assertions of undisputed material fact, arguing that "Mr. Abel specifically testified that he spoke to Mr. Parker about the job he was to do on the Apollo work site and that Mr. Parker should have received further orientation and training from [JMAV]." Strittmatter's Resp. to Statements of Undisputed Material Facts Submitted by JMAV and ECC, ECF No. 124-2, ¶ 31 (Resp. to Moriarity's [sic] Statement of Undisputed Material Facts) (citing Dep. of Richard Abel at 12:16-21, 13:11-18, JMAV's Ex. 17, ECF No. 123-21); see also id. ¶ 43 (referring to response to ¶ 31). Strittmatter refers in support to portions of the Strittmatter foreman's deposition that are not in evidence. See Dep. of Richard Abel, JMAV's Ex. 17, ECF No. 123-21 (not containing 12:16-21, 13:11-18). Absent record evidence to support Strittmatter's position, the Court would be led to conclude that JMAV had carried its burden.
Upon examination of JMAV's evidence for its so-called undisputed facts, however, the Court is not persuaded that summary judgment is warranted. JMAV refers to the deposition testimony of Mr. Parker and of Strittmatter's corporate designee. JMAV's Statement ¶ 31 (citing Dep. of J. Parker at 160:14-16, JMAV's Ex. 11, ECF No. 123-15; Dep. of C.R. Strittmatter at 49:3-52:9, JMAV's Ex. 10B, ECF No. 123-13). In particular, JMAV cites the following exchange in a deposition of Mr. Parker:
Q .... When you got to the Apollo job site, what did Strittmatter tell you about the job site?
A Nothing.
Dep. of J. Parker at 160:14-16, JMAV's Ex. 11, ECF No. 123-15. The cited deposition testimony of Strittmatter's designee is longer and covers several topics, but it likewise involves questioning as to "what specifically ... Mr. Parker [was told] when he first got to this jobsite." Dep. of C.R. Strittmatter at 49:3-52:9, JMAV's Ex. 10B, ECF No. 123-13. That designee indicates that Mr. Parker was told about "the potential of underground tanks." Id. at 52:2-5. The Court is not permitted in this posture to assess the credibility of this testimony or weigh the evidence. See Anderson ,
IV. CONCLUSION
For the foregoing reasons, the Court shall GRANT-IN-PART and DENY-IN-PART Strittmatter's [121] Motion for Summary Judgment, DENY ECC's [122] Motion for Summary Judgment, and DENY JMAV's [123] Motion for Summary Judgment on Count I and II of Its Amended Third Party Complaint.
Strittmatter's [121] Motion is granted only insofar as it seeks summary judgment as to ECC's counterclaim for contribution. ECC's counterclaim against Strittmatter for contribution is accordingly DISMISSED .
*252An appropriate Order accompanies this Memorandum Opinion.
While the Court bases its decision on the record as a whole, its consideration has focused on the following motions and accompanying briefing: Strittmatter's Mot. for Summ. J., ECF No. 121 ("Strittmatter's Mot."); ECC's Opp'n to Strittmatter's Mot. for Summ. J., ECF No. 126 ("ECC's Opp'n to Strittmatter's Mot."); ECC's Resp. to Strittmatter's Statement of Undisputed Material Facts, ECF No. 125; JMAV's Opp'n to Strittmatter's Mot. for Summ. J., ECF No. 128 ("JMAV's Opp'n to Strittmatter's Mot."); Strittmatter's Reply Mem. of P & A in Further Supp. of Its Mot. for Summ. J., ECF No. 133 ("Strittmatter's Reply"); ECC's Mot. for Summ. J., ECF No. 122 ("ECC's Mot."); Strittmatter's Opp'n to Mots. for Summ. J. Filed by Moriarty and ECC, ECF No. 124 ("Strittmatter's Opp'n to JMAV's and ECC's Mots."); Strittmatter's Notice of Filing Corrected Summ. J. Opp'n, ECF No. 131; Pls.' Opp'n to ECC's Mot. for Summ. J., ECF No. 127 ("Pls.' Opp'n to ECC's Mot."); JMAV's Opp'n to ECC's Mot. for Summ. J., ECF No. 129 ("JMAV's Opp'n to ECC's Mot."); ECC's Reply Mem. of Law in Supp. of Its Mot. for Summ. J., ECF No. 132 ("ECC's Reply"); JMAV's Mot. for Summ. J. on Count I and II of Its Am. Third Party Compl., ECF No. 123 ("JMAV's Mot."); JMAV's Mem. in Reply to Strittmatter's Opp'n to JMAV's Mot. for Summ. J., ECF No. 134 ("JMAV's Reply"); and JMAV's Errata to Its Mem. in Reply to Strittmatter's Opp'n to JMAV's Mot. for Summ. J., ECF No. 135. These motions are fully briefed and ripe for adjudication. In an exercise of its discretion, the Court finds that holding oral argument would not be of assistance in rendering its decision. See LCvR 7(f).
Despite the summary judgment posture at present, the Court shall again generally draw for this brief factual background from Plaintiffs' allegations rather than the parties' various statements of undisputed material facts, in light of the number of such statements and the number of disputes as to purportedly undisputed facts. In any event, the parties generally do not dispute these background facts, and even where they may, the Court's decisions in this Memorandum Opinion do not hinge on any of the background facts cited here.
In referring to the 2014 Report and other documents introduced in this Subpart I.B, the Court shall cite to the page numbers automatically generated by ECF in the header of each document. Where multiple versions of a given document appear in the record, the Court shall generally cite the version produced by the entity that generated it or is otherwise party to the document and is party to this lawsuit. In the instance of the JMAV/Strittmatter Agreement, the Court shall cite the version produced by general contractor JMAV.
Article 16.1.7 of the Owner/JMAV Agreement discusses certain "[a]dditional documents forming part of the Contract Documents." Owner/JMAV Agreement at 17. Documents listed include an Exhibit A entitled "Drawings List and Specifications."
The sentence in the Owner/JMAV Agreement permitting JMAV's reliance on certain documents and information furnished by Owner continues by providing that "in the event that any such information is not accurate and adversely affects the time and/or cost to perform the Work, the Contractor shall be entitled to an equitable adjustment in the Contract Sum and/or Contract Time, as applicable." Owner/JMAV Agreement at 80. ECC argues that this language shows that JMAV should not be permitted to rely on documents and information generated by ECC with regard to safety , since that does not relate to the time and cost factors in this second clause. See ECC's Reply at 13. However, viewing the evidence in the light most favorable to non-movant JMAV, the first clause can be read to permit reliance independently of whether it has any effect on time or cost. The Court shall discuss in further detail below why summary judgment is precluded as to ECC's motion.
Previously the Court did not draw this distinction regarding signatories when it observed that "[t]he EHASP was prepared by ECC and reviewed and approved by companies performing work on the site, including Strittmatter as a subcontractor completing excavation work." Parker II ,
There is some dispute over ambiguity in the EHASP's definition of the terms "General Contractor" and "Contractor." See, e.g. , EHASP at 6 (defining "General Contractor, Contractor" as "[t]he Contractor or General Contractor leading any element of the remediation work set forth herein, or a designated representative (including subcontractors for trades such as excavation and dewatering" (emphasis added) ); JMAV's Resp. to ECC's Statement of Undisputed Material Facts, ECF No. 129-1, ¶ 36 (disputing that the definition of "General Contractor" refers to JMAV); Parker II ,
The EHASP requires the demarcation of an exclusion zone in the event of encounter with "soil ... conditions ... which require personal protective equipment." EHASP at 20.
None of the parties has raised an issue with the discrepancy between the August 22, 2014, version of the EHASP referenced in the Owner/ECC Agreement, and the revised version dated September 8, 2014, that appears in the record. For purposes of the pending motions, the Court shall assume that there is no material difference between these versions.
None of the parties has raised a choice-of-law issue in briefing any of the pending motions. Because litigants may waive choice-of-law issues, the Court need not challenge their evident assumption that District of Columbia law applies. See Plesha v. Ferguson ,
The Owner/ECC Agreement provides that it "shall be governed by the law of the District of Columbia." Owner/ECC Agreement at 8 (Art. 10(f) ).
The Court cannot, of course, fault ECC for not citing Silberberg , as that case was decided after briefing concluded. But Silberberg breaks little new ground in comparison with Fort Lincoln Civic Ass'n, Inc. , with which ECC spends little time. See ECC's Mot. at 22-23.
With regarding to indemnity, JMAV seeks from ECC "express and/or implied indemnification." JMAV's Answer to ECC's Crosscl. and Crosscl. Against ECC, ECF No. 107, ¶ 44. The Court need not explore that distinction here.
Strittmatter incorrectly refers to the WCA where it was formerly codified, at
The Court need not reach the issue of whether Strittmatter's own claim against ECC for contribution concedes that Strittmatter is a joint tortfeasor with ECC. See ECC's Opp'n to Strittmatter's Mot. at 11; Strittmatter's Reply at 11 n.3.
In the Court's view, it is of no consequence that Strittmatter's agreement with these material facts occurs in the context of its response to ECC's motion, rather than briefing associated with Strittmatter's motion. ECC's opposition to Strittmatter's motion relies on ECC's assertion of material facts in support of ECC's own motion. See ECC's Opp'n to Strittmatter's Mot. at 5-6. Strittmatter does not express any objection to this approach to the briefing. See generally Strittmatter's Reply at 7-10.
The JMAV/Strittmatter Agreement provides for its interpretation "in accordance with the laws of the District of Columbia, without reference to its choice of law." JMAV/Strittmatter Agreement at 13 (Art. 13.3).
Because the D.C. Court of Appeals in Schlosser has indicated that a trial court applying D.C. law should be firmly convinced of the parties' intention to permit indemnification of a negligent indemnitee, at the summary judgment stage the Court does not resort to several other tools for resolving a contractual ambiguity, such as finding against the drafter or plugging a gap in the parties' foresight with the Court's own reasonable interpretation. See Aziken ,
The Court disagrees with JMAV's argument that a certain D.C. Court of Appeals decision is evidence of "customs and norms regarding allocation of risk on construction sites in the District of Columbia." JMAV's Reply at 2 (citing Steele Founds., Inc. v. Clark Constr. Grp., Inc. ,