U.S. Court of Appeals for the Federal Circuit, 2001

Franklin Pavkov Construction Co. v. Delaney

Franklin Pavkov Construction Co. v. Delaney
U.S. Court of Appeals for the Federal Circuit · Decided February 20, 2001 · Newman
5 F. App'x 882

Franklin Pavkov Construction Co. v. Delaney

Opinion of the Court

ON MOTION

ORDER

NEWMAN, Circuit Judge.

Upon consideration of the unopposed motion of FranMin Pavkov Construction Co. for reconsideration of the court’s January 5, 2001 order dismissing its appeal for failure to file an opening brief,

IT IS ORDERED THAT:

(1) Franklin’s motion for reconsideration is granted; the dismissal order is vacated, the mandate is recalled, and the appeal is reinstated.

(2) Franklin’s brief is due within 14 days of the date of filing of this order.

(3) The revised official caption is reflected above.

Case-law data current through December 31, 2025. Source: CourtListener bulk data.