Meridian Engineering Company v. United States
Opinion
Meridian Engineering Company ("Meridian") appeals two final decisions of the U.S. Court of Federal Claims determining, inter alia, that (1) Meridian did not meet standards of proof to show that the United States ("Government") breached certain contractual obligations and its duty of good
*1354
faith and fair dealing in a dispute under the Contract Disputes Act,
BACKGROUND 1
In 2007, Meridian entered into a contract with the Government to construct flood control structures, referred to as the Chula Vista Project.
Meridian I
,
Following the parties' disagreements over payment owed to Meridian, Meridian filed suit in the Court of Federal Claims for breach of contract, breach of the duty of good faith and fair dealing, and a violation of the CDA.
See
J.A. 127, 3000-53. The Government conceded liability for costs relating to three counts of Meridian's Second Amended Complaint (Counts VII-IX), which were the subject of a separate damages trial.
See
J.A. 3032-36 (Count VII (Suspension of Work), Count VIII (Channel Fill), Count IX (Interim Protection) ).
See generally
Meridian II
,
DISCUSSION
I. Standard of Review
We review the Court of Federal Claims' legal conclusions de novo and its
*1355
factual findings for clear error.
See
John R. Sand & Gravel Co. v. United States
,
II. CDA Claims
Meridian asserts that the Court of Federal Claims erred when it "reasoned that only Meridian's breach of contract and breach of good faith and fair dealing claims presented a viable cause of action," because "Meridian's CDA claims should have been analyzed under the framework contemplated by the CDA, and not under the rubric of a 'breach' claim." Appellant's Br. 23, 24 (capitalization modified). However, Meridian does not explain the alternate CDA framework to which it refers, nor does it state how analysis under a different hypothetical framework would result in a finding in its favor. See id. at 22-25 (stating only that the use of the breach of contract standard "skewed" the Court of Federal Claims' analysis).
"The[ ] requirements of the CDA are jurisdictional prerequisites to any appeal."
M. Maropakis Carpentry, Inc. v. United States
,
III. The Court of Federal Claims Did Not Err in Its Differing Site Conditions Analysis (Counts II and V)
The Court of Federal Claims found that Meridian did not offer sufficient evidence to satisfy its Type I differing site condition ("DSC") claim alleging that in the channel
*1356
and sewer line areas of the project the unexpected conditions of "soupy" soil caused delays and imposed unanticipated costs.
4
Meridian I
,
A. Legal Standard
"A Type I [DSC claim] arises when the conditions encountered differ from what was indicated in the contract documents."
Renda Marine, Inc. v. United States
,
B. Meridian Has Not Shown a Type I Differing Site Condition
The Court of Federal Claims found in relevant part that Meridian's interpretation of the Contract was not reasonable, and that the existence of subsurface saturated soil conditions was "reasonably foreseeable."
Meridian I
,
id="p1357" href="#p1357" data-label="1357" data-citation-index="1" class="page-label">*1357
We see no error in the Court of Federals Claims' findings with respect to the first two elements of a Type I DSC claim.
7
As noted by the Court of Federal Claims, several instances in the Specification and accompanying drawings indicate the potential presence of water and saturated soil.
See, e.g.
, J.A. 1664, 1725-26;
see also
J.A. 1729, 3274-76, 3286, 3367-68. Boring logs that accompanied the Contract also recorded sub-surface conditions near the boring holes that were "silty clay, with sand, black, wet, medium to high plasticity, [and] soft." J.A. 1652;
see
J.A. 1653-63 (recording similar descriptions in additional boring hole logs). Further, the boring hole logs stated that "variations may exist in the subsurface between boring locations," J.A. 1736, and that the logs, which recorded boring log data from nearly two decades prior, "should not be construed as ... defining construction conditions," J.A. 1651;
see, e.g.
, J.A. 1664 (dating boring excavations to 1989). Therefore, even though the Contract indicated "hard unyielding material" found at parts of the site, J.A. 1737, a "reasonable and prudent contractor would not have understood the [C]ontract documents as providing an affirmative indication of the subsurface conditions" to be non-saturated at the site,
H.B. Mac, Inc. v. United States
,
A reasonable and prudent contractor would have foreseen the saturated soil condition, based on the Contract documents and the fact that the actual conditions at
*1358
the site indicated such conditions.
See
H.B. Mac
,
C. Meridian's Counterarguments on Its Type I DSC Claim Are Unpersuasive
Meridian makes four primary arguments why we should find the Court of Federal Claims erred in finding that "the actual conditions at the site were reasonably foreseeable,"
8
Meridian I
,
First, Meridian contends that the Court of Federal Claims' review "was based on an improper interpretation of the Contract documents, which failed to give proper weight to [certain] geotechnical information." Appellant's Br. 29; see id. at 29-39. Specifically, Meridian alleges that the geotechnical information provided in the solicitation "indicated that there would be hard, unyielding materials in the excavation areas" rather than the discovered groundwater and clay materials. Id. at 31; see, e.g. , J.A. 1737 (providing Section 3.2 of the Specification stating certain areas of the Project contained "hard unyielding material").
Despite Section 3.2's language, the Court of Federal Claims noted several other portions of the Contract that indicated areas of the site contained saturated soil.
See
Meridian I
,
Second, Meridian contends that the Court of Federal Claims erred in not giving sufficient weight to Meridian's expert and witness testimony, which explained that Meridian relied on certain statements in the Specification in making its assessment.
See
Appellant's Br. 32-34 (describing reliance on Meridian's president, Mr. Sutton), 34-36 (asserting the findings of Meridian's expert, Dr. James W. Mahar, which it deems consistent with Mr. Sutton's conclusions that it was reasonable not to expect groundwater flows or clay materials at the site). We do not find clear error in the Court of Federal Claims' consideration of the expert and witness testimony. We have stated that "weighing of conflicting evidence is a task within the special province of the trial judge who, having heard the evidence, is in a better position than we to evaluate it."
Pac. Gas & Elec. Co. v. United States
,
Third, Meridian contends that the Court of Federal Claims erred because its conclusion was based on an improper finding
*1360
that "a reasonable contractor would have conducted an independent soils investigation." Appellant's Br. 29. Meridian incorrectly summarizes the Court of Federal Claims' findings. The Court of Federal Claims did not state that a reasonable contractor would make an independent soils investigation. It stated that "a reasonable contractor would want to investigate whether there were unstable, saturated conditions upstream" because the work site was in a floodplain and the plan drawings showed saturated soil with no bearing capacity as needed for the project, and "[a] site visit also would have made these conditions known, because large portions of saturated, alluvial soil were located '100 feet or so' away from" the proposed worksite.
Meridian I
,
Fourth, Meridian argues that the Government's "various modifications to address the soils issues" by the CO acts as an admission that a Type I DSC claim exists. Appellant's Br. 38;
see
id.
at 38-39. However, we have stated that "in court litigation, a contractor is not entitled to the benefit of any presumption arising from the [CO]'s decision. De novo review precludes reliance upon the presumed correctness of the decision."
Wilner v. United States
,
D. Meridian's Defective Pipe and Dewatering Specification Claims
The Court of Federal Claims found that Meridian's defective pipe and dewatering specification claims were so intertwined with its DSC claim that they constituted a single claim.
1. The Defective Pipe Specification Claim
Meridian alleges that "[e]ven if Meridian had not encountered a [DSC], it is entirely possible that Meridian would be entitled to recover damages incurred as a result of the defective pipe specification alone." Id. at 46. We disagree with Meridian.
We have previously stated:
*1361 Although [DSC] and defective specifications claims are distinct in theory, they collapse into a single claim ... where the alleged defect in the specification is the failure to disclose the alleged [DSC]. Where the [DSC] claim and the defective specifications claim are so intertwined as to constitute a single claim, that claim will be governed by the specific [DSC] clause and the cases under that clause.
Comtrol, Inc. v. United States
,
The Specification called for Class IV unlined pipe to be used in the sewer relocation project. J.A. 1449;
see
J.A. 1446-47. Upon installation, the Class IV pipe bowed and Meridian had to "remove and reinstall" the pipe with stronger Class V pipe. J.A. 357. Meridian admits that the bowing of the pipe "was undoubtedly exacerbated" by the purported DSC, "i.e., the unanticipated subsurface soil conditions." Appellant's Br. 45 n.7. However, it incorrectly states that the "problems ... were certainly in part attributable to the defective specifications,"
Meridian's counterarguments are unpersuasive. To the extent Meridian argues that the Specification was defective because it should have required a contractor to provide Class V pipe, see Appellant's Br. 43 (stating that the Arizona Department of Environmental Quality ("ADEQ") "required Class V pipe"), we do not find sufficient evidence in the record to support this claim. The Government's witness stated that Class IV was "right on the line of being adequate," J.A. 567, and that Class IV was not "the wrong pipe" because alterations could have been made to compensate for the later-discovered issues and satisfy ADEQ requirements, J.A. 496. Meridian has not presented evidence that, given the information in the Specification, Class V was required. Rather, it claims that the purported DSC caused Class IV pipes to be inadequate.
Meridian also contends that the Specification was defective because the design drawings called for Class V pipe, J.A. 1725, such that the discrepancy itself constitutes error,
see
Appellant's Br. 43. This argument is without merit. The Contract states that "[i]n case of difference between drawings and specifications, the specifications shall govern." J.A. 1156. Meridian does not challenge this unambiguous contract language.
See generally
Appellant's Br. Moreover, if the documents were on their face ambiguous, as Meridian alleges, Meridian "ha[d] a duty to seek clarification of a patent ambiguity" on this basis.
Comtrol
,
2. The Defective Dewatering Specification Claim
In a footnote, the Court of Federal Claims found that the dewatering requirements in the Specification were
performance
requirements, rather than
design
requirements.
Meridian I
,
Meridian argues that the dewatering specification is a design specification, not a performance specification, and therefore the Court of Federal Claims was required to consider it separately from a DSC analysis. Appellant's Br. 46-49;
see
J.A. 1628-31. However, Meridian does not contest that the underlying allegations related to the purported defective dewatering specification are so intertwined with the DSC claim as to constitute a single claim.
See generally
Appellant's Br. Nor does Meridian argue that
Comtrol
's instruction to treat DSC and defective specification claims as a single claim would not apply to its dewatering specification claim, regardless of whether the dewatering specification is categorized as a performance or design specification.
See generally
IV. The Court of Federal Claims Provided Insufficient Analysis for Meridian's Flood Event Claim (Count IV)
Meridian sought additional damages below that it purportedly accrued "due to the [Government's] modifications and specification defects" that caused delay and forced Meridian to work in "inclement weather" conditions.
Meridian I
,
*1363
Meridian I
,
Discharge of a claim by accord and satisfaction occurs when some performance different from that which was claimed as due is rendered and such substituted performance is accepted by the claimant as full satisfaction of his claim. However, courts may refuse to bar a claim based upon the defense of accord and satisfaction where the parties continue to consider the claim after the execution of a release.
Meridian asserts that the defense of accord and satisfaction for Count IV 11 should be barred because the parties continued to consider the claim after the bilateral modifications, and the Court of Federal Claims' finding to the contrary is clearly erroneous. See Appellant's Br. 52-53. Meridian contends that the continued drafting of Government estimates for flood damage, "even absent any 'negotiations' with Meridian[,]" indicates that the Government "did not believe there had been a release or abandonment [of] Meridian's claims." Id . at 53. Meridian further argues the Court of Federal Claims erred because it did not use the four-part standard for accord and satisfaction as articulated in Holland . See id. at 48-51; see also 621 F.3d at 1382. We find the Court of Federal Claims provided insufficient analysis of this defense.
Accord and satisfaction has been "aptly described" as a four-part test of "proper subject matter, competent parties, meeting of the minds of the parties, and consideration."
Brock & Blevins Co. v. United States
,
The Court of Federal Claims solely considered whether Meridian
knew of
the August 10, 2009 Government draft modification in determining whether the parties continued to consider the flood events claim.
See
Meridian I
,
In our precedent on accord and satisfaction, we have never held that the affirmative defense of accord and satisfaction may only be barred with evidence of formal draft modifications negotiated between parties after a release's execution. Indeed, in several cases, we have found accord and satisfaction barred when a contractor submitted a proposed claim before the execution of a release, and only one party, the Government, responded in some fashion after execution.
See, e.g.
,
England v. Sherman R. Smoot Corp.
,
Thus, the Court of Federal Claims' assumption that Meridian had to have known of the proposed draft modification for the meeting of the minds requirement improperly applied the law on accord and satisfaction. Our precedent on the meeting of the minds inquiry accepts a wide range of evidence in its fact-specific consideration. Accordingly, we remand for the Court of Federal Claims to consider whether the parties reached a meeting of the minds on the flood event claims in light of all of the evidence.
See
Yankee Atomic Elec. Co. v. United States
,
V. The Court of Federal Claims Erred When It Denied Meridian's Unpaid Contract Quantities Claim (Count VI)
Meridian sought damages for "unpaid contract quantities" of certain items purchased in excess of original contract estimates in the amount of $358,913.63.
Meridian I
,
First, the Court of Federal Claims found the Government was entitled to withhold up to 10% of payment based on FAR 52.232-5.
Meridian I
,
*1366
Indeed, the Government abandoned its arguments related to the progress payment provisions with respect to the unpaid contract quantities after the partial summary judgment phase of the trial.
Compare
J.A. 166-214 (setting forth the Government's arguments on progress payments at the hearing on motion for summary judgment),
with
Def.'s Trial Br. at 82,
Meridian v. United States
, No. 1:11-cv-00492-SGB (Fed. Cl. Sept. 18, 2014), ECF No. 122 (hereinafter "Gov't's Post-Trial Br."). Moreover, withholding is only allowable if "satisfactory progress has not been made" on a contract, FAR 52.232-5, but the Government has conceded that "unit priced quantity work was generally done" and there was no allegation of unsatisfactory performance that would merit withholding,
Meridian I
,
The Court of Federal Claims also cited in part to
Johnson v. All-State Construction, Inc.
to support its holding supporting the Government's refusal to pay any of the alleged unpaid contract quantities.
Meridian I
,
Meridian does not contest that the Government has a common law right to a set off, rather, it argues that "the amount of any potential set[ ]off" was not established by the Government at trial because the issue was not addressed in the quantum phase. Reply Br. 27. The Government, which also argued before the Court of Federal Claims that the issue would be "resolved at the damages portion of trial," Gov't's Post-Trial Br. 82, presented evidence in the form of its expert Mr. Stephen Weathers's report that the Government overpaid Meridian for contract items by $326,642.32, J.A. 3239; see J.A. 3227-39. Meridian claimed in detail damages for unpaid contract quantities in the amount of $358,913.63. J.A. 3030-32 (Second Amended Complaint); see J.A. 2301-13 (detailing alleged unpaid quantities).
The Court of Federal Claims did not provide any analysis of the parties' varying cost estimates to explain why it found that Meridian had not shown by a preponderance of the evidence it was entitled to the amount claimed.
See
Meridian I
,
CONCLUSION
We have considered Meridian's remaining arguments and find them unpersuasive. 14 We vacate and remand the Court of Federal Claims' findings in Meridian I on Counts IV and VI, reverse and remand the Court of Federal Claims' interest calculation in Meridian II , and affirm the remainder of the decisions. Accordingly, the Final Decisions of the U.S. Court of Federal Claims are
AFFIRMED-IN-PART, VACATED-IN-PART, REVERSED-IN-PART, AND REMANDED
COSTS
Each party shall bear its own costs.
The undisputed facts and procedural history of this case are extensive and are described in full in
Meridian I
.
See
Both parties agree that the Court of Federal Claims erred in setting the date from which interest accrued at January 7, 2014.
See
Appellant's Br. 61-62; Appellee's Br. 60. Interest accrues from the date that the contracting officer ("CO") receives a claim.
See
Recodified at Federal Acquisition Regulation ("FAR") 2.101 (2002);
see
Federal Acquisition Regulation; Definition of 'Claim' and Terms Relating to Termination,
Meridian's DSC claim originates from the standard "differing site conditions" clause located in the Contract pursuant to FAR 52.236-2(a) (2017). See J.A. 1150-51.
For example, Meridian argues that the Court of Federal Claims only addressed Count V's DSC claim with respect to the sewer relocation work but "wholly failed to address Meridian's Count II [DSC] claim" related to the area of construction around the concrete channels. Appellant's Br. 40 (capitalization modified). Meridian is incorrect. The Court of Federal Claims noted at the start of its DSC analysis that, "because the parties' briefs jointly discuss [DSC] and sewer relocation, the court addresses Counts [II] and [V] together."
Meridian I
,
It "is distinguished from a Type II [DSC claim], which arises when the conditions encountered are of an unusual nature and differ materially from those normally encountered in the kind of work contemplated by the contract."
Renda Marine
,
Meridian's arguments related to the third and fourth elements of the Type I DSC claim-reliance in fact and material differences-are "premised on the [Court of Federal Claims'] erroneous conclusions regarding [the second element of reasonable foreseeability]." Appellant's Br. 39 (capitalization modified). We may affirm the Court of Federal Claims' holding that Meridian has not proven a DSC based on the failure of a single element of the DSC claim.
See
Renda Marine
,
Meridian also contends that the Court of Federal Claims erred by determining "what specific representations the contract made" under the first element of the Type I DSC claim, i.e., what representations were made to a reasonable contractor, when that determination should have been made under the second element of the Type I DSC claim.
See
Appellant's Br. 27. However, Meridian does not allege this error would affect the disposition of the Court of Federal Claims' holding, nor does Meridian present any evidence in support of its argument. Accordingly, we find Meridian waived this undeveloped argument.
See
SmithKline Beecham Corp. v. Apotex Corp.
,
Meridian separately alleges that Mr. Chickey "was not accepted by the [Court of Federal Claims] as an expert," such that his testimony should not be relied upon. Appellant's Br. 36. The Court of Federal Claims commented in a supplemental hearing during trial, at which Mr. Chickey testified, that Mr. Chickey was considered an "expert[ ]." J.A. 3411. Because Meridian does not challenge that finding on appeal, we accept the Court of Federal Claims' determination and may rely on Mr. Chickey's testimony.
Even if we were to review the dewatering specification's classification, we would not find that the Court of Federal Claims erred. The dewatering specification unequivocally states that "[a]ll permanent construction shall be carried on in areas free from water." J.A. 1629. However, it leaves the means by which to accomplish this objective to the discretion of the contractor. See J.A. 1629 (ordering the contractor to submit a proposal "showing the method that he proposes to use to divert water" (emphasis added) ), 1629 (ordering contractor to, in its plans "describ[e] the proposed methods to protect each construction work area[ ] from storm runoff" (emphasis added) ), 1630 ("The Contractor shall submit the method of dewatering to [CO] for his approval. " (emphases added) ). Because the Specification does not "describe in precise detail the materials to be employed and the manner in which the work is to be performed," it is properly considered a performance specification. Blake Constr. , 987 F.2d at 745.
Meridian also contests the Court of Federal Claims' determination that Count V (Differing Site Conditions) of Meridian's Second Amended Complaint was barred by accord and satisfaction.
See
Appellant's Br. 54-57. Because we affirm the Court of Federal Claims' determinations that Count V fails on its merits,
see supra
Section III, we need not consider the Court of Federal Claims' alternative holdings with respect to the affirmative defense of accord and satisfaction for Count V,
see
Meridian I
,
The Court of Federal Claims further erred by not reviewing the other challenged element of the accord and satisfaction claim.
See
Holland
,
For the same reasoning, the Court of Federal Claims' citation to
M.C. & D. Capital Corp. v. United States
, which applies the provisions of FAR 52.232-5, would not apply here,
see
Meridian I
,
Meridian states in a conclusory manner that because "[i]t is now clear that the [Government] did, indeed, fail to pay Meridian even those sums that it agreed Meridian was owed," the Court of Federal Claims "erred in denying Meridian's good faith and fair dealing claim [ (Count XIV) ]." Appellant's Br. 62. "[M]ere statements of disagreement with the [trial] court as to the existence of factual disputes do not amount to a developed argument."
SmithKline Beecham
,
Reference
- Full Case Name
- MERIDIAN ENGINEERING COMPANY, Plaintiff-Appellant v. UNITED STATES, Defendant-Appellee
- Cited By
- 20 cases
- Status
- Published