Court of Claims, 1865

Clark v. United States

Clark v. United States
Court of Claims · Decided October 15, 1865 · Casey, Nott
1 Ct. Cl. 246

Counsel

Mr. McOalla for the claimant., Mr. KETCHAM.tho Solicitor, and Mr. Weed, the Assistant Solicitor, for the government.

Clark v. United States

Opinion of the Court

Nott, J.,

delivered the opinion of the Court.

This is an action brought to recover $13,000 damages for building an embankment in the Memphis navy yard. There are two causes of action alleged : 1st, that while the embankment built should have been measured monthly, and each portion built during the month should have been measured by itself, the officers of the government made all their measurements from a fixed base, thereby throwing the continued and increasing waste and shrinkage of the parts already built and measured upon the contractor; 2d, that the officers of the government hindered and obstructed the claimant in the performance of his work, and injured the work as he performed it, by compelling him to dump earth in running water during an overflow of the river, by ordering his carts to take circuitous routes, and by using the unfinished embankment as a roadway and for building sites.

On the first trial in the case Judge Hughes held “ that the work, in the progress of construction, was at the risk of the contractor, until from time to time inspected, approved, and received, and then it was at the risk of the United States;” and he concluded “that the United States were liable upon a quantum, meruit for all materials thrown directly into a current of water by order of the government agents ;” and upon these grounds he found for the claimant the sum of $10,684 21. Judge Scarburgh concurred in the opinion that the contract “is a severable and not an entire contract;” but held that the contractor “ could claim nothing for the material used, but only for embankment made and delivered;” and he found for the claimant in the sum of $4,094 90. Judge Loring held that by the leading provision of the contract the United States should “ pay for a specific thing, a specific price;” that the specific thing was “an embankment containing 221,000 cubic yards,” and the specific price was “ eighteen cents per cubic yard;” that “ the shrinking and waste during the execution of the contract were to be borne by the contractor,” and that he was entitled to recover nothing.

On the second trial Judge Hughes adhered “ to the conclusions expressed in his former opinion,” and again found for the claimant $10,684 21. Judge Loring also adhered to his opinion, which gave *248nothing to the claimant. Chief Justice Casey took a view of the question the exact opposite of that occupied by Judge Scarburgb, and held that the intermediate estimates were not to bo “ regarded as separate admeasurements of the work, but were estimates of its relative progress,” and that “ the final measurement of the work at the completion of the contract must determine the amount of embankment but that, for the yielding of the batture on which the embankment was built and for the material thrown in the water during the overflow, the claimant should recover; and he found for him in the sum of #3,480 66. Such is the troubled history of the case. The contract under which this work was done, and for a violation of which this action is brought, contains, among- others, the following provisions: That the said William Clark doth hereby contract and engage with the said Joseph S. Watkins as follows : that for the consideration hereinafter mentioned, the said William Clark will furnish all the material and make 221,060 cubic yards of embankment at the navy yard, Memphis, Tennessee, or so much as shall be required of hitn by the engineer or other duly authorized agent; the embankment to be made of clay, sand, gravel, or other good material, in such manner and places as shall be directed by the said engineer or other authorized agent. And the said William Clark doth further engage and contract to finish this embankment on or before the 15th day of July, 1847. * * * * That for the materials and embankment made, approved of, and received, and inspected as aforesaid, according to the terms and stipulations of this contract, there shall be paid to the said William Clark, or order, by the navy agent at Memphis, on account of all bills presented for the aforesaid materials and work delivered and executed, made out in approved form, authenticated by the certificate of the inspecting- officer or officers, and approved of by the commanding officer of said yard, the following price, viz : eighteen cents for every cubic yard. And it is hereby further stipulated by and between the parties hereto, that the department reserves to itself the right of diminishing or increasing the above-named quantity of embankment; and should the quantity be increased or diminished, the same price as is specified for the embankment shall be paid to the contractor, and no more. Mo other charge to be admitted nor allowance to be made by the United States for or on account of this contract, and ten per centum to be withheld from the amount of all payments on account thereof as collateral security, in addition to the bond given to secure its performance, and not in any event to be paid until it is in all respects complied with; and ninety per centum of the amount of all deliveries made will *249be paid by the said navy agent within thirty days after bills duly authenticated, as aforesaid, shall have been presented to him.

In the examination which I now make, the first question that presents itself is with respect to the admissibility and competency of evidence. We are all agreed that the mass of matter transmitted with the petition by Congress, and printed as a part of the record in the case, is not thereby made evidence. On the contrary, we think that only such documents should be printed in such cases as are made by proper references in the petition a part of the petition, or such documents as may be agreed upon by stipulation between the parties, or such as the claimant deems to be properly authenticated, and desires to put in evidence.

A claimant may manufacture any amount of irrelevant testimony and present it to Congress, and Congress may transmit it as a part of his case to this court, but Congress does not thereby make irrelevant matter relevant, or enact'that incompetent evidence is competent; and there is neither necessity nor propriety in this court including in the printed record of the case testimony which we must immediately reject as inadmissible.

There may be documents among such transmitted papers that would be admissible if properly authenticated ; and such there appear to be in thÍ3 case; but inasmuch as these have been referred to in the three trials of the action, and inasmuch as the Solicitor of the United States has raised no objection to them, and, on the contrary, has used some of them as evidence, we must conclude that he is satisfied of their authenticity, or that some stipulation has been entered into between the parties which docs not appear upon the printed record. In other words, we accept as admissible such of these documents as we find to be relevant and competent evidence.

Under this ruling, and under previous decisions of this court, I admit as evidence—

1. The notice to contractors of July 20, 1845; and the contract of the claimant.

2. So much of the letter of the claimant to the Secretary of the Navy as was read by the Solicitor as an admission of the claimant.

3. The account for the ten per cent.,” and the receipts annexed.

4. The deposition taken regularly in the case.

And I exclude as irrelevant or incompetent evidence for the claimant all other matter.

*250When this mass of irrelevant testimony is cleared away I have little difficulty in coming to the following conclusions :

1. The contract was for the building of an embankment, and not for the sale of loose earth.

2. There is nothing in the contract to warrant the assumption that the work was to be measured monthly. “ Payments on account” were to be made to the extent of ninety per centum “ within thirty days after bills duly authenticated” should be presented, but nothing is said as to the times when the measurements should be made.

3. In the silence of the contract, the law concludes that the embankment was to be of the ordinary kind, and the measurements to be made in the ordinary way. Although the claimants were eutitled to frequent measurements, it by no means follows that those measurements were to he made in an extraordinary manner. Measuring from a fixed base may be the ordinary and proper method of estimating embankments when the measurements are to be made at frequent periods. In this case the report of Engineer Warford shows affirmatively that it was the proper and ordinary method, and the claimant has neglected to show that it was not. In the absence of evidence to the contrary, we must conclude that it was.

' 4. The damages caused by the commandant interfering with the claimant’s carts, compelling him to dump earth in the water during an overflow, and using the embankment as a roadway, as shown by the witness Korex, were suffered after the 15th July, 1847, the day when the embankment was to have been completed, and consequently after the contractor was in default. The similar acts mentioned by the witness Hogan are not established with respect to time, and all are so loosely stated that it would be impossible to compute the amount of damages resulting therefrom, if the claimant were not in default.

5. If the claimant were entitled to recover for the amount lost by the natural sinking of the batture on which the embankment was built, there would be no evidence on which to found a judgment. The fact of its sinking rests on the opinion of witnesses; the extent to which it did sink is not shown by a particle of evidence. Ho computation of damages can be made from such a failure of proof.

It is, therefore, my opinion that, with regard to the contract, the claimant is mistaken in the construction he has placed upon it, and that with regard to the matters he has set up asa violation of the contract by the United States, there is a failure of proof.

Mr. McOalla for the claimant. Mr. KETCHAM.tho Solicitor, and Mr. Weed, the Assistant Solicitor, for the government.

The decision of the court is that the claimant should not recover, and judgment should he for the defendants.

The following is the opinion delivered by Judge Loring, on the first trial of the case, February 11, 1861:

I am obliged to dissent from the opinion given. I think the leading provision of the contract, and therefore its leading purpose, is, that the United States shall pay for a specific thing a specific price. The specific thing is an embankment containing 221,000 cubic yards, and the price is 18 cents per cubic yard; so that all the United States were to pay for the thing contracted for was 221,000 times 18 cents— $39,7S0. If this were not so, and they had to pay for the shrinking and waste during the execution of the contract, then, as these are indeterminate, they would have to pay some indeterminate amount beyond that stated, and the specifications of the quantity and price would be useless.

Therefore, I think that, on the construction of the contract, the shrinking and waste during the execution of the contract is to be borne by the contractor, and that the mode of admeasurement adopted by the United States was correct.

The contract contemplates that payments should bo made occasionally during the progress of the work; but this is usual in the contracts of the United States, and is for the convenience of contractors, and the provisions for it are to be construed in reference to that only. Then here those provisions expressly state that such payments are to be “ on accoimt” of the contract, and thus indicate that they are to be made subject to a final settlement, and not as payments, each, of so much work done. Then these payments are to be on the certificate of the inspecting officer and on his admeasurement; and, as no mode of admeasurement is prescribed by the contract, he was free, of the two modes of admeasurement, to take that which would fulfil the purpose of the contract, and give the United States 221,000 cubic 'yards of embankment for $39,780 when the work was done.

It is also observable that in the subsequent contract for the same work, put in evidence by the petitioner, similar provisions for occasional payments are made, with an express provision that the shrinkage and waste are to be borne by the contractor. The two things, there*252fore, are not incompatible, nor are they unnsal; for Mr. Warford, the engineer in charge of the work, in his report to the department, (put in evidence by the petitioner,) says: “ In the absence of anything in the contract to the contrary, the work done by Mr. Clark has been measured according to the common custom which prevailed on the various public works upon which the. undersigned has been engaged for a period of about a quarter of a century, and in accordance with the method known to have been practiced in some places where .he was not engaged. On all the public improvements of which the undersigned has any knowledge the amount paid for was what the contractors’ work measured at the time of the completion of the contract.” (P. 16.)

I am of opinion the petitioner is not legally entitled to the relief he claims.

Dissenting Opinion

Casey, C. J.,

dissenting.

I adhere to the opinion-and conclusion stated by me on a former trial of this case, and therefore dissent from the conclusion of the majority in the opinion just read.

The following is the opinion delivered by the chief justice on the second trial of the case, December 9, 1861:

The contract out of which this controversy arises between the government and the claimant, required the latter to furnish all the material and make 221,000 cubic yards of embankment at the navy yard, Memphis, Tennessee, or so much as shall be required of hirti by the engineer, or other duly authorized agent of the government. The embankment was to be made of clay, sand, or gravel, or other good materials, in such manner and places as should be directed by the engineer, or other authorized agent. “ That for the materials and embankment made, approved of, and received and inspected as aforesaid, according to the terms and stipulations of this contract, there shall be paid to the said William Clark, or order, by the navy agent at Memphis, on account of all bills presented for the aforesaid materials and work delivered and executed, made out in approved form, authenticated by the certificate of the inspecting officer or officers, and approved by the commanding officer of said yard, the following price, viz: eighteen cents for every cubic yard.”

It seems clear to me that the thing contracted for by the United States was embankment, and not so many cubic yards of loose detached clay, sand, or gravel. The object and purpose in letting the work *253was the making of a solid and firm foundation for the site of the navy yard, upon a low wet batture on the bank of the Mississippi river. To be suited to the purpose for which it was designed, it must be sufficiently compact and solid to support the buildings intended to be erected upon it, and prevent an overflow of the river upon the site in high stages of the water. A railroad company contracting for the delivery of materials and making an embankment to raise a depression in the line of their road-bed to. grade, would naturally expect to receive, and the contractor to make, such a permanent solid embankment as would support the superstructure of the road with the passage of the cars over it. If it were embankment for a canal, it would just as naturally imply that it should be of such closeness and texture as would confine the water within the limits of the improvement. In neither case would the contract be fulfilled by delivering so many cubic yards of sand or gravel as there should be of embankment when finished. It is not for the delivery of so many yards of material, but for the furnishing the material and the malting of so many yards of embankment.

But, as I read the contract, it appears to me that the construction is plain and manifest that it was embankment and not materials which the government contracted for. In the contract it is expressly provided that he is to “ furnish the material and make the embankment.” And he is to bo paid “for the aforesaid materials and work delivered and executed,” arid “ for the materials and embankment made.” Now, I cannot think that these engagements would have been met' by the delivery of the specified number of yards of material any more than an agreement to furnish the material and construct a hundred perch of stone wall would be fulfilled by delivering on the grounds of a hundred perch of stone. And in the one case, as well'as in the other, it was to be measured by the work that was done, and not by the materials supplied for its execution.

But it is contended, that if it was to be measured in the embankment, it was to be so measured at the end of each month, and that thenceforward the loss in the embankment from the settling of the materials, shrinkage, waste, &c., was to be borne by the government, and'not by the contractor; and this has given rise to the discussion whether it was an entire or severable contract. In other' words, whether it was one contract for two hundred and twenty-one cubic yards of embankment, or different and distinct engagements for the several parts or portions made in the respective months during the progress of the work. This question is only of any importance in the *254cause, as it may aid in determining upon whom the loss occurring from shrinkage of the embankment by the action of rain and the river should fall — whether upon the government or the contractor. In a careful examination of this contract, I have failed to discover any provision in it which bound the government to monthly or any other intermediate estimates and payments. That the engineer and commandant of the yarda portion of the time.adopted monthly periods to furnish the contractors with an estimate of the work performed, and authenticated bills for him, by which he was enabled to. receive pay as his work progressed, was to him a matter of favor and convenience, but, as I apprehend, not a right'uudcr the contract. In most of the agreements for the execution of public work it is-usual to insert a clause providing for monthly estimates, but it is entirely omitted in this agreement. The only part of the agreement upon which such a claim is based is that clause which provides that “ ten per centum be withheld from the amount of all payments on account thereof, as collateral security, in addition to the bond.given to secure its performance, and not in any event to be paid until it is in all respects complied with; and ninety per centum of the amount of all deliveries made will be paid by the said navy agent within thirty days after bills duly authenticated, as aforesaid, shall have been presented to him.” It will be seen that no time for taking estimates of the work is specified in the agreement, and the officers in charge of the work might as well have adopted any other period, say quarterly’or half-yearly periods, as monthly estimates. But, did the agreement even contain a clause requiring monthly estimates and payments, the conclusion sought to be drawn by the claimant would not follow. Where such a provision exists, the intermediate estimates are not regarded as separate admeasurements of the work, but mere estimates of its relative progress. They-are understood, both in England and in this country, to be mere approximations. And the stipulation itself is held to be only equivalent to a provision that the company or government shall, from time to time as the work progresses, advance .a stipulated proportion of the pay for the work which the engineer shall adjudge to be done. (Ranger vs. The Great Western Railway, 27 Eng. L. & Eq. Rep., 35; Redfield on Railw., p. 207, § 116.) Upon the same principle, in The People vs. Benton, 7 Barb,, 209, where an indifferent reference was provided for, in case either party should be dissatisfied with the measurement of the engineer, it was held, that this umpirage only extended to the final estimate.

If this be the true rule, the final measurement of the wovk at the *255completion, of the contract, or stoppage of the work, must determine the,amount of embankment “made and delivered,” and the amount of compensation the contractor was to receive at the rate fixed in the agreement. These views, as it appears to me, dispose of the question upon whom the diminution of the embankment from ordinary causes, as settling and shrinkage, must fall. The contractor can only recover for so much as the final measurement of the embankment shall show to have been “ made and delivered.”

By whom such loss and destruction as occurs from inevitable accident, as by inundation, during the progress of the work, is to be borne, is a question of greater difficulty, and one upon which neither the elementary writers nor the adjudicated cases entirely agree. In the civil law, the owner of the property is liable to the workman for the labor and materials in case of destruction by fire, inundation, or earthquake. (1 Domat., Civ. L., p. ISO.) In the common law, in the ease of personal property the law appears to be settled, that if the employer furnishes the material and the workman is to manufacture an article, as a carriage, or a ship, for a certain price, and the thing perishes before completion and delivery, the owner loses the materials, and whether the workman loses or is to be paid for his labor depends somewhat on the contract, or usage, or on the nature and character of tlie employment. If the workman is to furnish the materials and the work the loss is to be borne by him, for there was no ownership in the employer until completion and delivery; and resperit domino. (Story on Bail, § 427 a.)

Mr. Bell, in his commentaries, deduces the following rules: “ 1st. If the work is independent of any material or property of the employer, the manufacturer has the risk, and the unfinished work perishes to him. 2d. If he is employed in working up the materials, or adding his labor to the property of the employer, the risk is on the owner of the thing with which the labor is incorporated.” 1 Bell’s Com., p. 456, 5th ed.) The principles, as stated above, are much discussed and recognized in the cases of Menetone vs. Athawes, 3 Burr. Rep., 2592; Gillet vs. Mawmen, 1 Taunt. Rep., 137; Gregory vs. Stryker, 1 Denio, 628; Hurd vs. West, 7 Cow. 752; Smith vs. Clark, 21 Wend., 83; Pierce vs. Schenck, 3 Hill, 28; Baker vs. Woodruff, 2 Barb., 520; S. C. 2 Comst., 153; Mallory vs. Willis, 4 id., 76.

With regard to personal property the law appears now to be pretty well settled, but where thfe subject-matter' of the contract relates to the erection of buildings or other structures upon real estate, there appears to be more doubt and difficulty. There, the materials and *256labor having been affixed or added to the real estate of the employer, it would appear inconsistent with the nature and character pf that species of property that any ownership should reside in the builder or contractor. He has a bare right or license to enter for the purpose of his employment, the legal possession and seizin, in the meantime, remaining in the owner. It is clear, therefore, that the question, whether it is a sale or bailment, cannot arise. The authorities I have ' cited above, and the cases of Woods vs. Russell, 5 B. & A., 942, and Clark vs. Spence, 4 A. & E., 448, discussed on the argument, have no direct or authoritative bearing on the question involved. It must, therefore, be determined on other principles. And, in this aspect of the case, it appears to me that the question whether the contract was entire or severable becomes important. I have already stated, in regard to the measurement, that I hold this to be a contract for 221,000 cubic yards of embankment, and not so many distinct and different engagements as there were months employed in its execution. A contract embracing several particulars, though made at the same time, and contained in the same instrument, may yet have the nature and operation of several different contracts. (2 Smith Lead. C., p. 45.) As where it embraces a number of distinct subjects which admit of being separately executed and closed. (Perkins vs. Hart, 11 Wheat., 237; 6 Curtis, 578.) “ Even if the work was to be paid for as it progressed, it would not show that the contract was distinct and severable. As the sale of 100 bags of hops, at 56 shillings per hundred pounds ; or to serve for 10 months and spin yarn at three cents per run ; or to serve for 12 months at ten dollars per month. (McMillan vs. Vanderlip, 12 John. Rep., 65; Davis vs. Maxwell, 12 Metc., 286; Clark vs. Baker, 5 id., 452.) In a contract to build and complete a house, the employer to pay certain sums respectively when the walls should be raised, the roof put on, and when ready for painting, and the residue when finished ; or a contract to build a bridge at a stipulated price per lineal foot; the erection of a wall at so much per perch ; or the excavation of a section of canal; or the making of an embankment by the cubic yard, and to be paid a stipulated proportion while the work is in progress. In all these cases the contractor, though to be paid by instalments, and by estimates as the work advances, has engaged to finish an entire thing. (Cunningham vs. Morrell, 10 John. Rep. 303; Tompkins vs. Elliot, 5 Wend, 496; Bean vs. Atwater, 4 Cow., 4; McLano vs. Rush, 9 Dana, 64; Redfield on Railw.; McKnight vs. Dunlop, 4 Barb. S. Ct., 36.) And where he is to furnish the materials as well as perform the work, and the work perishes by *257inevitable accident, without any default on the part of the employer, it appears to me the loss will fall upon the contractor. If the house before being finished should be sonsumed by fire, the bridge prostrated by a storm, or the embankment be swept away by an inundation, although paid a rateable proportion of the work, before he could recover for the entire thing he would have to replace the structures. Two cases contained in our books are almost, if not altogether, in direct opposition to each other. In Wilson vs. Knott, (3 Humph. Rep., 473) Knott was to build a house for Wilson at so much per square foot, to be measured when finished, Wilson to furnish the materials. When nearly completed the house was consumed by fire. The supreme court of Tennessee held that Knott was entitled to be paid for his labor. It is admitted by the judge who delivered the opinion in that case that if the materials had belonged to the workman the law would have been held differently. On almost .the identical state of facts in Brumly vs. Smith, (3 Ala. Rep. N. S., 123,) it was held that the workman was not entitled to be paid for his labor; that the materials perished to the owner, and the work to the builder. As Clark was not only employed to perform the labor, but to furnish the materials and construct and complete an embankment, to consist of one entire thing, containing 221,000 cubic yards, or so much of it as should be necessary, that contract was not performed until he presented such an entire thing, or was relieved or excused from its fulfilment. It was, therefore, necessarily at his risk, and what was lost by the overflow of the river, without any fault of the government or its agents, must be borne by him, and he was only entitled to be paid for so many cubic yards as his embankment measured when he was permitted to suspend the prosecution of the work, with the additions hereafter stated. For this he has been paid in full, and, if there were nothing else in the cause, it would determine that nothing is due to the claimant.

But there are two facts in proof in the case which satisfy my mind that the measurements made do not give the claimant the full measure of justice to which he is entitled. The first is, that a large portion of the embankment was constructed upon a low,-wet batture on the bank of the Mississippi river, and which yielded very considerably to the pressure of the superincumbent embankment. To whatever, extent it so .yielded, measurements made from bench marks on the bluffs before the work was commenced would not ascertain the true amount of embankment made.

*258Secondly. The evidence shows, that the claimant was required by the officers in the yard to deposit a portion of the material in the water during the high stages of the river, a large portion of which material was of course lost. Under the contract the officers in charge had a right to direct where the material should be placed, but it was a right to he exercised in a just and reasonable manner, and with a due regard to the interests of the contractor. I cannot regard it as either right or reasonable to compel the contractor, during a temporary overflow of the river, to deposit the material in water of from four to eight feet deep, and where necessarily a large portion of it would be wasted and carried away by the current, and for wbat loss he suffered in this way I am clearly of opinion he should be paid. The difficulty is .in the want of reliable and definite proof upon which to found a calculation. In the absence of proof by the claimant I adopt Mr. Warford’s estimate of the diminution of the embankment previously made by the government, and on which he allowed fifteen per centum for shrinkage and waste.

The amount of embankment as measured by the engineer was 12S,913jS(fo- cubic yards, to which I add the fifteen per centum for the depression of the batture and the loss by depositing in the water, making 19,337 cubic yards, and amounting to three thousand four hundred and eighty dollars and sixty-six cents, ($3,480 66,)'to which extent I am of opinion he is entitled to relief, and that a bill for that amount should be reported in his favor.

Case-law data current through December 31, 2025. Source: CourtListener bulk data.