Gilbert v. United States
Opinion of the Court
delivered the opinion of the court.
The petitioners in this case are Gilbert & Secor, claiming in their own right, and Courbland Palmer, who claims as assignee and executor of Samuel Dakin, deceased, and as assignee and administrator of Rutherford Moody and Eunice Moody, admin-istratrix of said Rutherford Moody.
The petitioners claim compensation for their dispossession by the United States, on the 1st November, 1856, of a floating dry dock at Mare Island, in the State of California, leased to them by the United States on the 17th March, 1856, for the term of three years therefrom.
And the court find the facts to be that, in pursuance of the acts of Congress of September 28,1850, (9 Stat. L., 516,) and of March 3,1851, (9 Stat. L., 622,) the Hon. William A. Graham, Secretary of the Navy, on behalf of the United States, on the 19th day of May, 1851, contracted in writing with John T. Gilbert, S. D. Dakin, Rutherford Moody, and Zeno Secor, that they, in consideration of the covenants and agreements in said
And the contract provided, among other things, that the' contractors might construct the dock at such place on the coast of the Atlantic or Pacific Ocean as they might prefer, but that all the parts of the dock should be delivered to the United States put together complete, and in every respect ready for use in raising vessels at such point in the bay of San Francisco as the United States should designate before the dock was ready for use; and that the work should be forthwith commenced and progress in its several stages and periods of construction in proportion to the time stipulated for its completion, and should be completed in all respects within two years from and after the date of the contract; and that the contractors warranted the dock should be capable of successfully raising and sustaining for repairs a ship of the line of five thousand and three tons displacement, or a steamer of three hundred and fifty feet in length; and that the experiment for testing the power and capacity of the dock should be performed by and at the expense of the contractors, with a vessel to be furnished by the United States within three months after notice of the completion of the dock.
And, in the language of said contract, it was “further agreed that if the parties of the first part shall fail to comply in each and every particular with the specifications and provisions of this instrument, all the materials of every kind delivered and used upon the work shall be held and used by the United States as their property, as collateral security for advances made, or until a satisfactory adjustment of the case shall be concluded.”
And it was further agreed that all the materials and work of every description, shipped on the Atlantic coast for the said dock in California, should be fully insured and the policies of the insurance should be made payable in case of loss to the United States; and, in case ■ of loss, the insurance for loss or damage paid by or recovered from
The contractors having, according to the requirement of said contract, prepared the materials of the dock in the city of New York ready for shipment to California, on the 21st of November, 1851, notified the department of the fact, and asked that the place or site in the bay of San Francisco to which the materials should be sent might be designated 5 and, on the 22d November, 1S51, they were informed by the department that the materials might be shipped to San Francisco, and before their arrival there the site for the dock should be designated.
At this time the United States contemplated the construction of a basin or pier at the site of the dock, without which it could not be set up or worked. The vessels laden with the materials of the dock arrived at San Francisco, but the site of the
Tbe contractors then proposed to tbe Secretary of tbe Navy that they should select a site for tbe dock and construct a basin or piers for working it, in consideration that they should be allowed to use tbe dock in docking private vessels for tbeir own profit for three years from tbe completion of tbe dock. Tbe Secretary of tbe Navy submitted this proposition to Congress, and, by tbe act of July 21, 1862, (10 Stat. L., 16,) it was provided as follows: “And said dock may be used for tbe purpose of repairing merchant ships when not in use for the government, in such manner and for such compensation, and upon such terms and conditions, as shall be prescribed by tbe Secretary of tbe Navy.77
And, on tbe fourth day of August, 1852, another contract was made by tbe Hon. John P. Kennedy, Secretary of tbe Navy, on behalf of tbe United States, with S. D. Daken, Rutherford Moody, John T. Gibert, and Zeno Secor.
This second contract, after referring to the statutes above specified and to tbe previous contract, provided, among other things, that tbe United States, so soon as tbe said dock should be in all things completed and delivered according to tbe terms of tbe first contract, would, “ on tbe completion and'reception of said dock and appurtenances according to tbe contract and specifications thereof,77 surrender to the contractors tbe entire control of said dock and appurtenances, (unless it became necessary to deprive them of such control for docking vessels of tbe United States,) for them use and benefit for tbe term of three years from tbe date of tbe reception of said dock by tbe United States, and further, until notified by tbe Secretary of the Navy of bis intention to terminate tbe contract. And that tbe contractors should procure and provide at tbeir own cost and expense, and by tbeir own selection, at or near San Francisco, a safe and suitable site for tbe erection of said dock without cost to tbe United States of any sort, including demurrage and damage for detention of vessels and freight,* and to construct or procure safe and suitable piers and accommodations for tbe proper and safe working of said dock; and that they should keep tbe dock and appurtenances safely and in good and complete re
And that, with the exception of vessels of the Uniited States which are to be docked free of charge, the contractors should have the right on the entire and complete fulfillment of the conditions recited to establish a reasonable tariff of prices to be charged for the use of the dock, to accrue wholly to their use and benefit, which tariff shall be regulated and approved by the Secretary of the Navy ; and no greater amounts shall be charged for the docking of merchant vessels than shall be approved by him.
And that, by authority of a law oi Congress, this second contract- might be annulled at any time, and likewise might be annulled ami the control of the dock resumed by the Secretary of the Na. ry on the fa,ilure of the contractors to comply with any of the foregoing conditions; likewise by six months’ notice being given in writing to the contractors at any time before the expiration of the said term of three years; and that it might be so annulled by the Secretary of the Navy in writing at any time before the expiration of said t -rm of three years.
And that if, for any other cause than by default of the contractors to execute the covenants and agreements in this second contract by them to be performed, the Congress of the United States, by its act, shall, at any time before the expiration of the said term of three years, dispossess the contractors of the dock and its appurtenances, that then, if it shall be made to appear that the contractors have been at a greater outlay for the accommodations to work said dock .than the value and
And it was further agreed that the United States, the party of the second part, assume, after .its reception by them, the risk of said-dock against damage- or loss from lightning and fire only, and when proper care and watchfulness to guard the premises against accidents by those.elements shall have been duly exercised.
And it was further stipulated and agreed that if default should be made by the parties of the first part in any of the stipulations and conditions a-fore'said, that then, and in that case, the said parties will forfeit and pay to the United States the imnal sum of $610,000, the same being the contract price for the construction of said dock.
Under the contracts specified the contractors proceeded diligently in the execution of their contract, and, having selected a suitable site for the dock at Mare Island, they constructed and completed six sections of the dock, and thereafter continued to use the same for clocking and repairing vessels from November, 1853, until the completion of the dock in August, 1855, and in that time docked twenty-nine vessels of the United States free of charge, and also merchant vessels, and from the latter received a profit equal to $24,506 46 per annum.
Six sections of the dock admitted the docking of only one vessel at a time instead of two, and its use before its completion did not retard or interfere with its completion, .and was known and not objected to, but participated in by the government, and made under a- tariff fixed. by the contractors and approved by the Secretary of the Navy.
The ten sections of the dock were completed in August, 1855,
On or about March 17,1856, the dock was tested in the manner provided for by the contract, and thereupon accepted by the government, and the full contract price, including the ten per cent, reserve*! by the contract, was paid by the United States to the contractors 3 and then, to wit, on the 17th day of March, 1856, the dock, after its reception by the United States, was surrendered to the contractors, to be held and used by them for the term of three years from the date of the reception of said dock by the United States.
On the 20th of March, 1856, the Secretary of the Navy, the Hon. J. 0. Dobbin, by a written notice addressetl to Messrs. Dakin & Moody, Gilbert & .Secor, at New York, notified them that the exclusive possession of the floating dock at Mare Island, California, would be taken by the Secretary of the Navy on the 15th of November, 1856, and on that day the United States took possession of said dock and its appurtenances and dispossessed the contractors 3 and thereafter the contractors presented their claim for such dispossession to the Secretary of the Navy for his appraisal of the damages therefor, and he declined to determine the question whether the lease for three years provided for in the second contract commenced in November, 1853, when the use of six sections of the dock by the contractors began, or on 17th March, 1856., when the completed dock was accepted and received by the United States and then surrendered to the contractors. The contractors then presented their claim to the 37th Congress, and, on February 9, 1859, the Senate, by resolution, referred the matter to the Secretary of the Navy, who, on the 22d February, 1859, reported to Congress.
The claimants have since presented their claim to the Navy Department and its payment was refused.
Upon thé facts found by the court, a majority of the judges concur in the opinion (though for different reasons) that the claimants are entitled to judgment for the sum of $59,223 94. My reasons for my opinion are as follows:
It was contended on behalf of the United States that the lease of the dock for the term of three years commenced in November, 1853, when the claimants began to use six sections
Then the contract provided that the United States should assume, “ after its reception by them, the risk of said dock against damage or loss from lightning and ñre only.” And this shows that the United States were not to have the risks or rights of ownership in the dock till after its reception by them.”
Then it was claimed on behalf of the United States that the claimants had the benefit of the dock in the. profit derived from docking merchant vessels, from November, 1853, till March 17, 1856, and that a recoupment or allowance should be made for this. The use of the dock for the benefit of either party was not provided for by the contract, and is to be ruled by the equity between the. parties, and this depends on their respective legal rights.
By the provisions of the contract, the United States had a lien on the dock as security for their advances and the full performance of the contract, which required the possession of the dock to be by the claimants, and at their risk till its completion and acceptance. And tiis lien was the whole right of the United States, and they had no right whatever to the possession of the dock or to the benefit they derived from its use. The relation of the parties was that of mortgagee and mortgagor in possession, and in such case, by the rule in law and equity, the mortgagor, as general owner in possession, has a right to any use of the property not inconsistent with the lien and its security. And if the United States had a right to object to the use of the dock before its completion, they did not do so, but permitted it and participated in it by taking the benefit of having their own vessels docked and repaired free of charge to
Then it was claimed on behalf of the United States that the claimants, for the dispossession of the dock, are, by the express terms of the contract, “ entitled to receive from the United States such sum or sums as thp Secretary shall deem just and reasonable, provided Congress appropriate the money on Ms recommendation and that Congress not haying made the appropriation which would be their approval of the Secretary’s finding, that cannot be taken as the measure of compensation the contract provides. I think this is true, but immaterial, because it only remits the claimants to a quantum meruit on the evidence whether this action is or is not rested on the contract. And I think the claim here is not on the contract, but for a violation of it; and that the dispossession of the claimants was made by the government in November, 1856, not to determine the lease of three years during the term, but because they held that the term commencing with the use of six sections of the dock in November, 1853, expired in November, 1856.
It is observable that the notice of the Secretary to the claimants is dated March 20,1856, and states that possession will be taken on “ the first of November next,” and there is no perceptible reason for the specification of that date except the belief of the government that the three years would then have expired. And the notice is addressed to the claimants in New York, and would reach them there a day after it was mailed here. And I think the reason of the notice is this: by the terms of the contract the lease was to be “ for the term of three years from the date of the reception of said dock by the United States, and further until notified by the Secretary of the Navy, in ivriting, of Ms intention to determine the contract.” And thus the notice in writing was “to determine the contract” so as to prevent the lease from extending beyond what the department thought was the end of the three years, and the time the United States could take possession of the dock without incurring liability to the claimants for anything.
This testimony from the chief of the Bureau of Yards and Docks, to whose special jurisdiction the matter belonged, shows, I think, that the government acted on their belief that the lease of three years ended in November, 1856; and if so, then their notice of March 20 was not intended to determine the lease during the three- years, and was not the six months’ notice required for that purpose by the contract, and their dispossession of the claimants was not the execution of that purpose; but it was merely an unauthorized act induced by their misapprehension as to the commencement and expiration of the three years, and as such it was a wrongful dispossession of the claimants, from two years and five months of their term for three-years, and was thus a violation or breach of the contract for which the measure of damages is not to be fixed by the Secretary and Congress, nor under the contract, but by this court upon the evidence.
And the measure of damages is the profits the claimants would have made on their lease if they had continued in posses
In this case the petition contains a prayer for general relief, and therefore the claimants may recover on any cause of action shown by the evidence.
And we find as conclusions of law—
1. That by the contracts and facts above set forth, the Dnited States leased the dock abovementioned to said Samuel D. Dakin, Butherford Moody, John T Gilbert, and Zeno Secor, for the term of three years, from March 17,1856, and contracted with them that they should enjoy the same for said term, under and according to said contracts.
2. That by dispossessing said lessees on the 1st of November, 1856, the Dnited States became and are liable to pay to said lessees and their rejiresentatives, for their deprivation of the residue of said term, the net profits they would have received therefrom, which amount to said sum of $59,223 94.
Judgment is to be entered by the claimants for the sum of $59,223 94.
Concurring Opinion
concurring:
The only point upon which I differ with my brother Loring is with regard to the effect which he ascribes to the notice of re-entry given by the Secretary of the Navy to the claimants.
In the first place I do not think that the reports of officers in. the Navy Department are admissible in evidence to explain or show the theory upon which the Secretary of the Navy acted. The notice must be construed like any other instrument, and the only facts admissible to explain its terms, if they need explanation, are the legally established facts of the case upon which the parties acted or should have acted.
Tiiis involves, I may add, a different effect to be given to the award of the Secretary of the Navy. In this view of the case, it is the precise estimate of damages contemplated by the contract, and upon which the action necessarily rests, and by which both parties agreed to be bound.
In regard to the recoupment of damages upon which the court is divided, I think it proper to add that I have not considered it, for the reason that I do not think it my duty to consider a possible defence in the nature of a cross-action when it has been neither pleaded nor proved on the part of the defendants, and when the cross-demand has never been made by the defendants in or out of court, and is not even suggested in any of their briefs, but on the contrary is first taken by the oral argument of their counsel on the fourth hearing of the case.
Dissenting Opinion
dissenting:
The damages claimed and recovered in this case arise upon two contracts for building a floating dry dock in the harbor of San Francisco, California. The first is dated the 19th May, 1851, for the completion of a dock of ten sections, in two years from its date, at the sum of six hundred and ten thousand dollars, payable in instalments as the work progressed. Ten per cent, was reserved until the completion of the work. The claimants were to furnish all the materials and labor, and the government was to designate the site. The materials and dock were required to be insured in the name of the United States, and as a further security to the United States it was stipulated that “ the said materials are to be held and used as the property of the United States.”
The second contract was dated the 4th of August, 1852. The time for the performance of the work was not changed, but the claimants agreed to procure a suitable site for the dock, and at their own exx>ense, and construct a suitable pier to work such dock. They were to keep it safely and in good repair, and at all times give preference to vessels of the United States free of charge. On the completion of the dock and its acceptance by the United States, it was to be surrendered to, and used by, the claimants, for the period of three years, they, in
The claimants allege that by the terms of the second contract they were entitled to have the use of the dock for three years from and after its completion and acceptance by the United States; and that as they only had it for about seven and one-half months after that date, they are entitled to recover in damages-a sum equivalent to the net earnings of the dock for the residue of the three years. These damages, they claim, were by the terms of the contract to have been assessed or appraised by the Secretary of the Navy, and that he has, in his report to Congress of February 22, 1859, assessed them at $59,223 94, and for this sum as liquidated damages they claim judgment.
To this claim, or the greater part of it, there are three several matters of defence.
I. There was nothing in the contract that authorized the claimants to use the dock in its unfinished state; nor was there anything in the contract which prevented the parties from agreeing that the use might commence before its comx>letion. The fact is clear, from the acts and conduct of the parties, that they did come to such an understanding, for the.claimants made
Now this dock, in my opinion, contrary to the position of the claimants, during all this time was the property of the United States. It was so expressly stipulated in the contract that from time of payment of the first instalments the materials and dock were to become the property of the United States. ■ There was, therefore, no room for any implication of law as to whether it was vested in the claimants or the United States; for by the express, undoubted law. of the contract, it was vested inthe United States; and the claimants having used it for their own advantage and benefit, are presumed to have occupied it lawfully and rightfully under their contract, and not as intruders or trespassers.
II., But if I am in error on that point it does not follow that the plaintiffs are entitled to the damages claimed. Admitting that the agreements only provide for an occupancy under the lease from and after the completion and acceptance of the dock, what follows ? Simply this: that the claimants, with the permission and assent of the United States, have had the occupancy and use of this property, which the United States had paid for, and which, by the express terms of the contract, was vested in them. They are bound to pay for such occupancy and use, and if the contract is silent as to the amount, then it is to be a reasonable amount, to be judged of by all the circumstances. And this amount so ascertained, is to be set off against the damages claimed. Now in this case all these amounts are ascertained with great precision by the reports of the Secretary of the Navy. The value of the remaining time of the lease, as alleged by the claimants, is $59,223 94. The amount received after deducting all charges, expenses, breakages, repairs, &c., as stated by themselves, was $53,519 37, leav
III. But there is still another objection to the claimants’ recovery, which is, in my opinion, equally fatal to their case.
This action under the contract did not accrue until the Secretary of the Navy had made his report of the damages in the case. That report was made on the 22d February, 1859 $ this suit was not brought until the 2d of March, 1866; the six years expired on the 22d February, 1865, more than a year before the filing of the original petition in this case. It is, therefore, barred by the limitation of the tenth section of the act of March 3d, 1863. And I am in favor of dismissing the petition.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.