John Rosenfeld's Sons v. United States
Opinion of the Court
delivered the opinion of the court:
Claimant is a commission merchant and entered into a contract with the defendant June 20, 1898, by which it sold and
In all essential features this case is like John J. Moore, trading as John J. Moore & Co., v. The United States, in which we have, in an opinion, given our reasons for the decision of the court, to which we refer without repetition here. The difference between the contracts in that case and this one is, that in the present case the coal was to be delivered from the vessel’s tackles. At the port of Honolulu it was not possible to deliver the cargo from the vessel’s tackles, or otherwise, without first arriving at the wharf. Claimant plainly undertook to deliver the cargo to the quartermaster’s department, United States Army, at Honolulu. This it could not do in the water, for the quartermaster’s department was on land, nor until arrival at the wharf, where the quartermaster was to receive it, and hence it was clearly its -obligation to deliver the coal upon the wharf, as it did. The petition will be dismissed.
Dissenting Opinion
dissenting:
It is a universal principle and practice in commerce that the consignee must be ready to receive the freight. All contracts of affreightment must be construed in the light of that general principle, and if the charterer wishes. to avoid it he must secure exemption by an express provision in his agreement.
In the preceding case of Moore & Co. the contract was specific to deliver at the wharf. It bound the shipper to
But in this case the contract was not to deliver at the wharf, but to deliver from the “vessel’s tackles.” The contract was broader than that in the other case. There the vessel was hound to deliver, and the consignees to receive, at one designated place — the wharf. Hero the vessel was bound to deliver from her tackles as the consignees might direct — on the wharf, on a ship of war, on an army transport, on a lighter. And reciprocally the consignees were bound to be read}'- to receive the cargo when the ship should arrive, except as otherwise provided in the contract. If the defendants intended that the coal should be delivered at the wharf, and nowhere else, they should have so provided in this contract as in the other. Thej' having an unrestricted right to have the coal delivered at the wharf, on another vessel, or in a lighter, laid upon them a reciprocal obligation to be ready to receive it in some of these ways; and the claimants, when they entered into the contract, had a right to expect that they would be ready. The defendants had no more right to keep the vessel waiting at her cost for a wharf than to have kept her waiting for a ship of war or an army transport on board of which they had intended to unload the coal. It is said that there were no public lighters in the port; but it was not the claimants on whom the obligation was to provide lighters. .It is said that the defendants had no lighters there of their own; but the claimants did not know that when they entered into the contract, and the defendants did. For the defendants to say that they had neglected to provide lighters is not equivalent to saying that they were prevented by the act of God. In the other suit the vessel was bound to get to the wharf;, in this, all that the vessel was bound to do was to be ready-to deliver from her tackles.
My conclusion is that the quartermaster’s compelling these vessels to wait for a wharf and neglecting to provide lighters or other vessels on which the coal could have been unloaded constituted demurrage, for which the defendants are liable.