This is a suit to recover damages for an alleged breach of contract. The claimants, Normile, Fastabend & McGregor, copartners, entered into a written agreement to construct a lock and dam in the Yamhill River in the State of Oregon, a keeper’s dwelling house and necessary buildings appurtenant thereto, and do a certain amount of dredging in the channel of said river near the lock site. The contract was dated March 11, 1898, approved March 24, 1898, and called for the completion of the work by December 31, 1898.
The controversy is largely one of fact, the legal propositions involved being in a large measure elementary and established.
The first items for which claim is made grow out of the delay in procuring title to the sites for the lock, dam, and keeper’s dwelling house by the defendants. Finding II recites the undisputed history of this proceeding. Specification 41 expressly warned the contractors that operations under the contract must await the purchase of sites for the commencement of the work. While celerity of performance was an essential part of the agreement, as evidenced by the dates therein, still there is sufficient in this express condition to anticipate delay. The gravamen of claimants’ petition respecting this item is the unexplained delay between May 13,1898, and June 14, 1898, during which period the where
It is true that subsequent to the Spanish war prices of both labor and material used in this kind of construction began to advance, and have continued to advance. War was declared on April 25, 1898. There was no delay for which
Claimants were at work under the contract. The findings show that in addition to their inexperience in this particular class of work they were, in fact, assembling material in the orderly prosecution of the work. They were in no position to receive or care for large consignments of cement or other materials. The delay in the approval of the deed and the notification to proceed with the work was too remote to attribute these losses to that event.
The remaining items resting upon the alleged delay in procuring title to the site necessarily follow the disposition made of the one mentioned in Finding V, and will be dismissed.
The item claimed for under Finding VI is not recoverable under the facts. The work charged for was performed for the express benefit of claimants, and under a distinct understanding that the defendants had no funds available to pay for same. There was no contract, express or implied, for this particular portion of the work, and no proof as to the expense attendant thereon. The same was voluntary.
The claim under Finding YII has to do with the erection of a temporary cofferdam. It was indispensable to the successful completion of the work that a temporary structure of this sort be erected to enable the completion of the permanent wing dam, which extended from the lock wall to the opposite bank of the river. There were no plans or specifications concerning the character of cofferdam or going into detail of construction; in fact there was nothing said about it in the contract or specifications. It is conceded, however, that it was a necessary adjunct to the carrying on of the work. Without it the wing dam could not have been constructed. The enginer officer in charge of the work designated the location of said cofferdam. The claimants proceeded to erect the dam at said location, and were thrice unsuccessful in the attempt. It is manifest from the findings that said location was impossible. Subsequently said cofferdam was relocated and successfully built. The evidence
Under all the circumstances in this case it seems hardly possible that the claimants would have three times attempted the erection of a temporary cofferdam in one place unless obligated so to do. The engineer officer in charge was required to use ordinary care and skill in giving directions, and the defendants’ liability is limited to such acts as by the use of ordinary care and skill could have been foreseen and prevented. (See Moore case, supra, and authorities cited.)
The loss occasioned by the failure of the first cofferdam does not come within the rule. There is nothing in the record which would sustain a finding of want of ordinary care and diligence in making the location in the first instance.
The final claim for the retained percentages as shown in Finding VIII is devoid of merit. The contract work was not completed until 1900. The engineer officer was exceedingly liberal in granting extensions. The contractors neglected to employ a competent civil engineer, which, together with their lack of experience in work of this character, unduly retarded the completion of the same. There is nothing in the record which brings this item of the claim within specification 35 governing the subject of extension.
Judgment is awarded the claimants for $3,200. As to all other items the petition is dismissed.