North Platte Canal & Colonization Co. v. United States
Opinion of the Court
delivered the opinion of the court:
The matter to be considered arises out of a demurrer to the petition.
It is alleged that a contract between plaintiff and the State of Wyoming was entered into for the construction of the principal canal described in the pleadings (and the lateral ditches thereto), which contract was subsequently changed on the application of the United States to the plaintiff whereby the General Government should have the right to enlarge and extend the canal and to occupy and use the
The second principal count in the petition contains an allegation that plaintiff had sold for cash to the Rawhide Ranch Company paid-up perpetual water rights for water to be delivered from the canal for beneficial use and irrigation upon lands situate and lying under and in the vicinity of the main canal and subject to irrigation by the waters therefrom under the permit. The charge is that the ranch company, relying upon the conditions set forth in the plaintiff’s contract with the United States that water would be delivered to the ranch from the canal for beneficial use during the irrigation season of 1906, planted and cultivated a large body of land, but by reason of the failure of the Government to keep its promises there was a loss to the ranch company of several thousand dollars, which disabled it from paying to the plaintiff the sums agreed to be paid to the corporation for the use of the water, either by the corporation itself or by those with whom plaintiff dealt.
The amount demanded on this count aggregates $13,745.04 as losses sustained by the ranch company which plaintiff had to pay.
The claim was presented to the Secretary of the Interior, who in writing rejected the same upon the ground that the allegations of fact upon which the claims were based were not admitted by the officers of the Reclamation Service.
The demurrer sets forth generally that the petition does not allege facts sufficient to constitute a cause of action, but that the damages, if any, as claimed by plaintiff are consequestial and sound in tort. In further demurring to the specific items, the grounds stated by the defendants are that the items are respectively for anticipated profits, speculative in their nature and contingent and too remote from the contract to be recovered in this action for breach of the agreement.
Defendants failed to deliver the water to which plaintiff was entitled during the irrigation season of 1906 and did not complete the canal sufficiently for the delivery of the water for beneficial use upon all of said land during any sufficient portion of the irrigation season of 1907.
But water rights were sold to persons living upon the land to be irrigated by plaintiff in 1905, from which it would have derived the consideration in the way of profits contemplated by the contract if defendants had fulfilled their obligations. The demurrer admits all of the facts well pleaded.
The failure on the part of the defendants to supply the water during the' time stipulated made plaintiff responsible to those to whom it had sold water rights, resulting in the water-right purchaser sustaining injury to the growing crop. Such injury arose out of the failure of the defendants to keep their contract. The authorities amply sustain the proposition that damages for injuries to growing crops directly due to breach of contract to deliver water for irrigation may be recovered. These authorities are collated in Smith v. Hicks, 19 L. R. A., 938, and from an examination of them we find that the rule followed in irrigation communities is the difference between the amount realized from the crops and the amount that would have been realized had water been furnished, less cost of raising, harvesting, and marketing. There is necessarily more or less uncertainty as to the measure of damages in all such cases, and on the merits this phase of the matter must be considered. Certainly actual damages properly proven are recoverable.
It is argued by defendants that the entire petition sets forth an action sounding in tort and that there is want of jurisdiction. This defense will now be considered.
The rule that the duty to pay damages for a tort does not imply a promise to pay them upon which assumpsit may be maintained has been recognized by the Supreme Court upon the authority of Goober v. Cooper, 147 Mass., 373. That a party may in some eases waive a tort by forbearing to sue for the tortious act and yet sue in contract has also
We make out of a confused and very inartificially drawn petition a third count. Plaintiffs describe certain land as being subject to irrigation from the canal under the provisions of its permit, which land they allege was damaged by, through, and because of the washing, cutting, and wasting of said land by a large volume of water flowing over and upon the land from the canal which is alleged to have been caused by the willful and negligent acts of the officers and agents of the United States. Though it is alleged that the immediate and direct effect of the acts of these officers was that a considerable portion of said land was ruined and rendered valueless, there is no allegation that the ruined land was “ taken ” for public use, nor that the defendants derived any benefit from the tortious acts of their officers. On these allegations the court can not imply a contract especially where the defendants received no benefit. If this be so the court does not see its way clear now to hold that the plaintiff may recover damages for breach of contract in not supplying water as they, the defendants, had agreed to do when it appears that the loss was caused by a purchaser not wanting the water because his land had been ruined by the tortious acts of third persons, for whose tortious acts the Government is not liable.
The express contract was not for the sale and delivery of water but merely to enlarge an existing canal and in order that both parties should in future have a joint interest therein and be the several owners of the water. The con
There is much to say on this branch of the case, but for the present we will be content to add that where a plaintiff sues on an express contract he must stand upon it.
Without further comment, leave is given to the plaintiff to amend its petition in this behalf within 60 days.
As to the first and second principal counts the demurrer of defendants is overruled, with leave to answer the entire petition within 90 days.