Shippey v. United States
Opinion of the Court
delivered the opinion of the court:
This cause was referred to the court under section 1063, Comp. Stat., 1901, p. 738, 22 Stat., 485, and under the act of March 3, 1887, 24 Stat., 505, by the Acting Secretary of War. The first reference under the same sections by the
Plaintiffs entered into a contract in writing with the United States for certain excavation work to be done by them on the Colbert & Bee Tree Shoals Canal near Riverton, Ala., on the Tennessee River. Three different classes of material were to be excavated; for earth excavation, 0.1749 cent per cubic yard; for hardpan, 50 cents per cubic yard; and for rock excavation, $1 per cubic yard. Considerable controversy arose during the progress of the excavation work as to what constituted hardpan as contradistinguished from mere earth excavation, and the present action is to recover for the work alleged to have been done under the original and a supplemental contract. The details of the work covering the different stations need not be stated as the two agreements are the same as to terms, conditions, and specifications.
Before the contract was awarded test holes had been made by driving down steel rods at the different stations on the axis of the canal and usuahy also at points about 50 feet to the right and left of each station. The results were recorded subject to inspection by bidders. The Government did not guarantee the character of the material, and bidders were expected to assume responsibility. Bowlders of more than 9 feet in volume were classified as rock excavation. Material other than rock that could only be loosened by a six-horse plow, or removed by a steam shovel without blasting, was classified as hardpan. All other materials were classified as earth excavation. All excavation was to be measured in place and paid for on monthly estimates of yardage covering work done in a manner satisfactory to the Government engineer. The engineer was authorized to withhold any estimate in case satisfactory progress was not made, and in case of any doubt or disagreement arising under the specifications the decision of the engineer was to be final.
Under the administration of the first engineer officer in charge in the beginning of the supervision of the work, the classification of the material to be excavated as to quality and quantity was made by an assistant engineer. This assistant was the designated agent provided for by the con
Turrell also refused, for some reason not explained, to follow the directions given to him by the principal engineer officer after making the allowance of the 14,000 cubic yards which the principal engineer officer had directed. On the contrary, Turrell did not classify according to the construction given to the contract by his principal, nor did he observe or undertake to classify any more material according to the method pointed out by the inspector assigned to the work for the purpose of making a thorough investigation, except as hereinafter stated.
The principal engineer officer first in charge of the work does not appear to have had knowledge of the failure of his subordinate to obey the instructions, inasmuch as this principal was relieved from duty soon after the allowance of the 14,000 cubic yards. Complaints, were made again in regard to the classification to an officer who was placed in temporary charge.
This officer was succeeded by Maj. Harts, to whom the contractors again complained of the classification, protesting orally and in writing to the last engineer-officer of the way they were being treated. Plaintiffs submitted a formal claim in writing to the last officer in charge for 97,000 cubic yards of additional hardpan, amounting to $31,534.70.
The matter.being referred again to Turrell, the work was reexamined by him, and he made a confidential report for an allowance for hardpan of 56,170 cubic yards, amounting to $18,260.86. This recommendation was approved by Turrell’s superior officer on duty as the assistant engineer in local charge of the work.
From all the testimony and circumstances in evidence the court is satisfied that the subsequent failure of the subordinate officer who refused to observe the directions of the chief supervising engineer (after the allowance set forth in the first paragraph of Finding V) resulted in an erroneous classification. There is no explanation as to why this subordinate did not continue to classify according to his superior’s construction of the contract as to that material excavated for
It is, however, reasonably doubtful that plaintiffs are entitled to the enormous amount claimed after the final decision in the War Office looking to a settlement of the dispute in the courts. The increase in plaintiffs’ estimate of hardpan excavation as made in the complaint before us is so far in excess of the formal claim made in the early part of the year 1908 that the court is impressed with the idea that the ad damnum is greatly exaggerated. Finding VI in its third paragraph discloses that in the early part of that year plaintiffs claimed for only 97,000 cubic yards as additional hardpan, which under the contract would have entitled them to $31,534.70. Their subsequent claim, which was later embodied in the petition and has been considered, is for enough additional hardpan to swell the claim to $122,072.12.
We come now to another and final question: Do the findings, taken all together, support the judgment under that line of decisions which make final the judgment of engineer officers
Paragraph 29 of the specifications provided that the decision of the engineer officer in charge as to quality and quantity should be final. That paragraph came under what the specifications termed general conditions.
Paragraph 54 provided that in case of any doubt or disagreement arising under the specifications the decision of the engineer should be final. By paragraph 55 the word “engineer” was understood to mean the United States Engineer officer in charge of the work or his designated agent. These two last paragraphs came under what the specifications termed special conditions.
The court has felt safe in adopting the decision of the engineer’s subordinate for the double reason that the word ' “engineer” was construed by the special conditions set forth in the specifications to mean the designated agent of the chief engineer and because this designated agent’s estimate conformed to the first engineer officer’s interpretation of the contract. No doubts have been suggested as to the correctness of the construction given to the contract by Maj. Newcomer, supported, as his construction was, by the examination of an experienced classifier of the material, and likewise supported, as the estimates finally were, by other officers whose integrity dues not seem to be involved.
The Chief of Engineers of the Army, at the seat of government, did not decide adversely to the contractors as to their right to bring suit for as much as the contractors thought they were entitled to receive. On the contrary, this high official declared that if Maj. Harts was satisfied that a mis
In refusing to make any modification of the estimates submitted to him this court must regard the decision of this officer as made without proper information and involving such doubt in his mind as to make the decision he did render a formal and perfunctory matter, to the end that the contractors might prove their right to another classification in this court, which alone possesses jurisdiction.
It is not doubted at this late day that where a contract provides that in case a disagreement arises under specifications the decision of the engineer is final unless there be fraud or such gross mistake on his part as to imply bad faith. In the case under consideration the contract went a little further in the use of those words which provide that in case of “doubt” the decision of the engineer should be final. ■But here the chief engineer’s doubt grew out of the fact that he did not see the excavated material and did not have opportunity to see or make any kind of an inspection of the material taken out. There was disagreement growing out of the doubt, and the doubt resulting in disagreement the two words must be taken to mean substantially the same thing. The rule mentioned applies to both doubt and disagreement.
The word “ engineer” was declared by the contract to mean the engineer officer in charge of the work or his designated agent. This designated agent made a decision, which was
The rule mentioned required not only a decision but a decision involving the exercise of honest judgment. But here there was a failure to exercise anything more in the nature of a judgment beyond the expression of a doubt, which meant, if it meant anything, that the parties should have an opportunity to present proof to the tribunal having jurisdiction. If the chief engineer did not go to the work in time to form a judgment of his own it was his duty to take information, to the end that he might make a more certain decision. The refusal to modify the estimates arising out of the chief engineer's doubt being predicated confessedly upon the want of information, the court is of opinoin that there was a failure to exercise that kind of judgment that plaintiffs were entitled to receive. Under these circumstances it seems proper to say that there was a failure to exercise judgment for want of information when we consider that the doubt expressed was to give the contractors opportunity to make proof of their claim to a court which the chief engineer was unwilling to receive as a disbursing officer. The Government should have no more advantage in the failure of the engineer officer to better inform himself, if possible, and act more advisedly than in those cases where there was a failure on the part of the officer to exercise an honest judgment.
It seems to be a violation of the spirit and intent of the contract to bind the contractors in the decision of the chief engineer when it was a decision rendered without adequate information.
The paragraph in the specifications can not be said to have been met when the agent’s judgment, being required, was followed by his refusal to act, the chief engineer believing at the same time that, in justice to the contractors, they should have the opportunity to present their case on more proof elsewhere.
The court is of opinion that the action of the chief engineer in charge of the works was tantamount to a refusal to render any decision at all. It was error on his part not to examine the sides or banks of the canals and to make such tests in connection with the accessible testimony as would enable him to render a decision approving the claim or disallowing the same. Inasmuch as this engineer officer took the view that he was a disbursing officer and that he could not decide the matter, we must regard his action as perfunctory and not a sufficient compliance with the specifications which required him to make a final decision on the merits of the claim.
In United States v. Adams, 9 Wall., 661, it was said that where proper findings are not made by this court on specific matters sufficient to enable the appellate court to properly review the judgment, additional findings should be made on a remand of the cause. This proposition was acted upon in Ripley v. United States, 220 U. S., 492. It may be our duty to be more explicit in the findings, but as the case presents enough, in our opinion, to enable the appellate court to review our action and proceed to final judgment on what we have found, we conclude to render judgment on the present findings. Injustice may result, if we do not, to the contractors.
The view of the court is that plaintiffs are entitled to judgment in the sum of $18,260.86, which is now directed to be entered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.