Court of Claims, 1920

Cook v. United States

Cook v. United States
Court of Claims · Decided March 15, 1920 · Booth, Downev, Graham, Hat
55 Ct. Cl. 215; 1920 U.S. Ct. Cl. LEXIS 108; 1920 WL 619

Counsel

Mr. William R. Harr for the plaintiffs. Harr Ao Bates were on the briefs., Mr. Richard P. Whiteley% with whom was Mr. Assistant Attorney General Frank Davis, jr., for the defendants.

Cook v. United States

Dissenting Opinion

DowNev, Judge,

dissenting:

I dissent from so much of the conclusion of the court as includes in the judgment the item of $5,095.38 as architect’s commission on the sum of $101,901.66 paid to the building contractor under authority of the act of May 27,1908, quoted in Finding "VTI. I am of the opinion that the last-named amount is not properly to be included in the “ actual construction cost of the work * * * as shown upon the books of the Supervising Architect’s Office,” and the determination of the questions necessarily involves a construction of the contract in that regard.

The view of the court as to this item is evidently found in the statement that “the $101,907.66 upon which the plaintiffs claim that they are entitled to commission is a part of the construction cost of the work executed from the architect’s drawings and specifications, and the sum aforesaid was shown upon the books of the Supervising Architect’s Office.”

It is first provided in the contract that the architects shall be paid “ a fee computed at the rate of 5 per cent upon the actual cost of the work executed from the drawings and specifications and under their supervision, as shown upon the books of the Supervising Architect’s Office by the net amounts of contracts awrarded and proposals accepted for additions and deductions, but not including, etc.,” and after providing for partial payments on a stated basis it is finally provided that “upon completion of the building the entire fee shall be finally based upon and computed on the actual construction cost of the work * * * as shown upon the books of the Supervising Architect’s Office, exclusive, etc.”

In the first provision quoted are significant words with reference to the cost of the work as shown upon the Supervising Architect’s books and illuminating as a reason for the use of the books as a basis for determining the amount upon which the fee is to be computed. I refer to the words “additions or deductions” in the connection used.

*232If it could be known that the work could and would be completed at the contract price the amount of the fee could be accurately stated in the contract, but we know that in all building contracts there are provisions for additions and alterations. There were many of them in this case. Alterations sometimes involve additional compensation to the contractor and they sometimes involve deduction. Both are provided for in public building contracts. Hence the necessity for an account of “ additions or deductions.” The account first sets up, as shown by the findings in this case, the contract price. When the additions by reason of changes are added and the deductions subtracted the result is the net contract cost. The account also involves payments made, but that is a matter with which the building contractor is concerned and not the architects.

When the result stated is reached by a balancing of the books we have the “ actual cost of the work ” as it is stated in one place, or the “ actual construction cost of the work ” as stated in another place, under the contract, and in my judgment the language used in the architect’s contract with reference to actual cost must of necessity be construed to mean actual cost to the United States under the contract. I can not conceive of any other authorized construction. Cost to the contractor and cost to the United States under the contract were, of course, expected to be different. The difference expected in favor of the contractor represented his anticipated profits. If Congress had not seen fit to relieve this unfortunate building contractor no other construction of the architect’s contract than that stated would even have been suggested. It was made in contemplation of the erection of a building in the usual manner, taking into account the changes likely to be made during construction, and without anticipation of any special favors at the hands of Congress. The architects were, in fact, paid a percentage, as shown in the findings, on a sum considerably in excess of the amount shown to have accrued to Butler under his contract, but this was due to the fact that some lesser portions of the work were let to other contractors and the right of the architects to commission on the amount of such contracts was recognized.

*233It is to be inferred from what is said on the subject that this item would not have been included in the judgment authorized by the majority of the court had not the extra payment made to the contractor under the special act quoted been entered on the books of the Supervising Architect’s Office. But it appears that it was not entered as a contract item or as an addition or deduction. The account was closed in the usual way, the final footings showing the cost under the contract and the account of the authorization under the special act with the payments made thereunder followed. It was, of course, necessary and proper that there should be some record of the action taken for the relief of the contractor as directed by Congress. Even if this item had appeared in the regular account it could not, in my opinion, have entailed a liability against the United States unless within a proper construction of the contract, but in fact it did not so appear.

This suit was not commenced until almost four years after the final settlement with these architects. In the meantime there had been continued and rather persistent efforts to get an allowance at the hands of Congress including all the items herein sued for. The Judicial Code, section 159, requires petitions in this court to fully set forth, as to all claims, “the action thereon in Congress * * * if such action has been had.” In Finding VIII the action had in Congress in this matter is fully set out. The effect to be given to such a situation has never, so far as I know, been the subject of accurate determination by the courts, and I am not inclined to contend that the facts shown in this case can be construed to work anything in the nature of an estoppel, but they are certainly significant and for consideration upon the merits of the case. It is safe to say from the facts found that in the beginning these plaintiffs did not conceive that they were entitled as a contract right to any compensation because of this extra payment made the building contractor, but were then in the attitude of seeking the bounty of Congress. They very significantly urged in their brief submitted to the committee having under consideration the bill introduced for their relief the “equity and justice ” of their claim and that “ inasmuch as Congress has *234relieved the said Thomas Butler for damages resulting from the same cause it can not with fairness reject their claim,” and while there was no final action by Congress with reference to their claim it is for consideration that the committee directed by Congress to investigate the matter and having before it all the facts set up not only in their brief but presented personally by one of the plaintiffs, and being fully advised also as to the relief granted the building contractor, reported favorably upon only one of the items claimed and that item is included in the judgment rendered in this case. It is safe to say under all the facts shown that for nearly four years there was no conception by anybody concerned with the matter that there was contractual liability to these plaintiffs on account of this item and that that asserted view of the matter is an afterthought. And in tihis connection it is not improper to observe also that when this action was commenced there was then pending a resolution to refer the last introduced bill to this court under the Tucker Act for findings and conclusions. The bill which it was then proposed to refer had been introduced in Congress more than three years after the final settlement made with these plaintiffs.

For the reasons stated I dissent from the inclusion in the judgment of the claimed percentage on the sum paid the building contractor under the special act quoted.

I am authorized to state that Chief Justice Campbell concurs in this dissent.

Opinion of the Court

Hat, Judge,

delivered the opinion of the court:

This is a suit brought by Isaac T. Cook, executor of the estate of William S. Eames, deceased, and Thomas' C. Young, the said Eames and Young having been partners, who, at the time of the making of the contract hereinafter mentioned, were partners, engaged in business as architects in the city of St. Louis in the State of Missouri. On July 9, 1903, the United States submitted to Eames & Young a a certain program for a competition for the selection of an architect for the erection of a customhouse building at San Francisco, Calif., and invited said firm to submit a design and estimates for the erection of said building, which were approved by the Treasury Department, and tire said firm was selected on December 19, 1903, as architects for said building. On February 6, 1904, the defendants entered into a contract with said firm. The plaintiffs performed extra work in eliminating from the original plans and specifications prepared by the plaintiffs and approved by the Treasury Department space for a subtreasury in said customhouse which was called for in the original program for competition by the Government and made part of the contract. For this extra work the defendants refused to pay. It was reasonably worth the sum- of $1,200.

*226The said firm prepared plans and specifications for the. installation of the power plant in the old appraiser’s stores building, which was work not included under the contract, .and the architects were not required to do it; it was work separately ordered by the department, and the reasonable value of the work so performed is the sum of $2,725. The third item of the claim is for the unpaid commission on the sum of $101,907.66, paid to Thomas Butler, the contractor for the construction of the building, due to the great earthquake and fire in San Francisco on April 18, 1906.

As to the first two items of this claim the defendants concede that they should be paid. The defendants resist the payment of the commission on the sum of $101,907.66, which was paid to Thomas Butler under the authority of a provision in the sundry civil appropriation act approved May 27, 1908, 35 Stat., 318. This provision is as follows:

“ The Secretary of the Treasury is authorized, upon completion of the customhouse of San Francisco, California, to pay to Thomas Butler, the contractor for the construction of said building, in addition to the contract price thereof, such sum as may be equitable and just to reimburse said contractor for any loss actually sustained in consequence of the earthquake and great fire of April, 1906, not exceeding the sum of $250,000. Providing that the amount allowed said Thomas Butler shall not be sufficient to enable him to make any profit out of the making and executing of said contract.”

The report of the committee appointed by the Secretary of the Treasury to adjust the claim of the contractor under the provisions of the statute above quoted shows that the contractor was entitled to receive the sum of $101,907.66, and that this additional payment covered only the actual increased cost to the contractor of constructing said building due to the earthquake and fire of 1906, exclusive of any profits to the contractor.

The contract of the defendants with the architects provided :

“And the party of the first part covenants and agrees to pay, or cause to be paid, unto the party of the second part, or to the heirs, executors, or administrators of the party of the second part, a fee computed at the rate of five per centum *227upon the actual cost of the work executed from the drawings and specifications and under their supervision, as shown upon the books of the Supervising Architect’s Office, by the net amounts of contracts awarded and proposals accepted for additions and deductions, but not including the cost of the site, or furniture, electric plant, gas or electric fixtures, mural paintings, architects’ fee, or the contingent expenses incident to the construction of said building set apart by the party of the first part.
“And the party of the first part covenants and agrees that payments will be made in the following manner, viz: One-fifth of the fee when the preliminary drawings are completed and approved in the manner provided in said regulations; three-tenths of the fee when the general working drawings and specifications are completed and copies thereof delivered to the Supervising Architect; and the balance of the fee monthly upon the basis of payments for work performed and in place as of record upon the books of the Supervising Architect’s Office, or as ascertained to be due to the several contractors who execute such work: Provided, That until the actual cost of the work executed from the architect’s drawings and specifications and under their supervision can be determined, the monthly payments on account of the fee shall be computed upon the proposed cost of said building as estimated by the party of the second part, viz, one million two hundred seventy-seven thousand six hundred ($1,277,600) dollars, or as may be readjusted from time to time; and upon the completion of the building the entire fee shall be finally based upon and computed on the actual construction cost of the work executed from the architect’s drawings and specifications and under their supervision, as shown upon the books of the Supervising Architect’s Office, exclusive of the cost of the items herein-before excepted.”

It will be observed that this contract provides “ upon the completion of the building the entire fee shall be finally based upon and computed on the actual construction cost of the work executed from the architect’s drawings and specifications and under their supervision, as shown upon the books of the Supervising Architect’s Office, exclusive of the cost of the items hereinbefore excepted.” The $101,907.66 upon which the plaintiffs claim that they are entitled to commission is a part of the construction cost of the work executed' from the architect’s drawings and specifications, and the sum aforesaid was shown upon the books of the *228Supervising Architect’s Office. Under the contract they are entitled to be paid their commission on this sum.

Judgment will be entered for the plaintiffs in the sum of $9,020.38, as shown by Findings V, VI, and VII.

Graham, Judge, concurs.

Concurring Opinion

Booth, Judge,

concurring:

The terms of the contract wherein provisions are made for the architects’ fees clearly indicate an intent to meet the circumstances of the architects’ employment and their relation to the contract work. It is first provided that the architects’ fees shall be five per cent, to be ascertained from the net amount of contracts awarded. This is followed directly by a provision for a preliminary payment of one-half of this fee upon the completion of the drawings and. specifications. There was a manifest purpose for making it so, for if the building was never completed the architects nevertheless were to be paid this preliminary sum. One-fifth of the fees was to be paid when the preliminary drawings were completed. At this time no contract for the building had been let. It could not be let until the preliminary plans and specifications had been first provided by the architects. Therefore, as a basis for determining how much the two and one-half per centum would amount to in gross, reference was provided for to the contracts for the building of the structure. If the building had never thereafter been built, this two and one-half per centum would have been paid. This was one contingency which had to be met, and was so met by these preliminary provisions in the contract. Again, the contract provides for another contingency — i. e., for monthly payments of the remaining two and one-half per centum upon the basis of the limit of cost, viz, $1,277,600, not the contract cost, and this shall continue to be the basis of monthly payments to be made to the architects “ until the actual cost of the work executed from the architects’ drawings can be determined.” Up to this point the contract is dealing with known and existent conditions, contingent because of the very nature of the services to be rendered by the plaintiffs and which must be provided for in justice to *229the architects. There comes a time, however, when all com tingencies and conditions respecting the payment for the services of the architects are merged into an absolute certainty, and that time is when the work is completed and the actual cost of the building capable of definite ascertainment. So it was provided in the contract that upon the completion of the building the entire fee should finally rest upon the actual construction cost of the building. No mention is made in the final paragraph of contract cost, and inasmuch as the terms of the contract expressly cover every stage of construction progress, it seems to be a contract to pay the architects in the end five per centum of the actual cost of the building as shown on the books of the Supervising Architect’s Office. This is the usual and customary fee paid to architects, and the provisions of the contract 'respecting the same accord with the general and long-continued practices respecting contracts for the payment of the same. Supposing that in this case the officers of the Government had concluded to do a vast amount of work by day labor, which might have been done if a sufficient margin obtained between the limit of cost and contract price. Would it then be said that the cost of such work was not to be included in the computation of actual cost of the building, so as to form a basis for the allowance of plaintiffs’ fees? No written contract would have existed, but surely the item would be actual cost. The sum allowed by act of Congress to Butler, the contractor, was not a gratuity; quite the contrary — it was based on precise estimates made after personal inspection and certified to as items of actual construction work. It was in legal effect an increase in the limit of cost, and in the end made the building actually cost $1,382,004.14, whereas originally it was designed to limit the cost to $1,211,600. Certainly the mere fact that Butler might not have recovered this amount in court does not convert the sum allowed as actual cost into a gratuity. Congress every session sends many controversies to this court by special jurisdictional acts where the claimants are barred from judicial proceedings otherwise. In this instance, instead of waiving legal defenses in a court of justice, Congress referred the matter to the proper department of the Government to *230investigate and determine the sum to be paid not in excess of the amount expressly limited in the bill. It did not give Butler any fixed sum.

Section 159 of the Judicial Code, providing for a statement in the petition of claimant “ of the action thereon in Congress,” is the continuation of an ancient provision appearing in the act of February 24, 1855, establishing this court. It was at the time an indispensable prerequisite, for the jurisdiction of the court embraced all claims “which may be referred to said court by either House of Congress.” We were at the time a commission, possessing no general jurisdiction. It was manifestly carried into the Judicial Code because of our jurisdiction under the Bowman and Tucker Acts, wherein congressional and departmental action upon the claim preferred is a vital and necessary prerequisite. It can have no possible relation to general jurisdictional cases, and can not be held to be even a necessary allegation in a petition filed under our general jurisdictional laws and should not be in the findings. It was never required in other cases. The right of petition to Congress for relief is constitutional, and the fact that Congress acted adversely upon a petition so made can not affect the rights of the plaintiffs in a subsequent legal proceeding to recover under the law what Congress in its legislative judgment saw fit to deny them. The plaintiffs’ case is not to be prejudiced because they in the first instance availed themselves of a constitutional right instead of resorting to the courts. Whatever argument they advanced, either in person or by attorney, in an effort to obtain congressional relief can not militate against them in the present suit, properly brought under an act giving this court jurisdiction of the subject matter. Previous statements as to matters of fact, of course, are available to impeach contrary ones on the cross-examination of witnesses, but whatever may have been the arguments advanced to persuade Congress to pass the bill and grant the relief requested have no place in this record, for this is not a congressional case. The plaintiffs may have been mistaken as to their legal rights or wrongly advised with respect thereto; they may have changed their minds, and whatever may have been the previous attitude in their *231course before Congress, save as to material statements of actual facts going to the truth or falsity of the actual situation as it existed, they are not to be prejudiced thereby.

I therefore concur in the opinion of the court.

Case-law data current through December 31, 2025. Source: CourtListener bulk data.