Peaslee-Gaulbert Co. v. United States
Opinion of the Court
delivered the opinion of the court:
The plaintiff is a Kentucky corporation engaged in manufacturing paints. In October, 1918, in response to an advertisement, it submitted a bid to manufacture 57,880 gallons of olive drab paint, the Navy Department, with which the contract was made, to furnish all the necessary ingredi
The plaintiff had another contract, dated October 18,1917, ■with' the War Department for the manufacture of paint. Deliveries under this contract were to be completed by December 31, 1917. They were not so completed until February 19,1918, being 50 days belated. On November 7, 1917, ■the plaintiff received notice to hold up the paint order that the defendant might change the style of package. All this paint was to go abroad, and the defendant contemplated •and finally did change completely the style of container for •packing the same. At least 10,000 gallons already packed' had to be repacked, a tedious and slow' process.' On November 20, 1917, the plaintiff received the official confirmation .and style of new container, and the repacking went forward thereafter, entailing an admitted delay of 23 days. Again, the defendant changed the formula of manufacture, and did not approve proceeding, after having stopped the work, -until the plaintiff had been delayed 17 days. The final result of these two interferences, which were authorized by the contract and provided for therein, threw the completion •of the contract into the strenuous commercial period when railroad embargoes, Fuel Administration orders, etc., made it impossible to effect immediate deliveries of freight. The plaintiff asserted under this contract a claim for a 50-day ■extension of time, and the contracting officer immediately .allowed it, and the Chief of the Bureau of Ordnance, as well as the Secretary of War, concurred in the allowance. Notwithstanding all this, liquidated damages to the extent of $485.61 were assessed against the plaintiff and withheld from its pay. Just why this was done, in the face of the provisions of article 4 of the contract, is difficult even to surmise. That it was unlawfully done and in direct violation of contractual, obligations to do directly the opposite thing needs no argument.
In view of the express terms of the contract and the action of the officers of the defendant thereon with respect to the performance-of the same we not only have no doubt of the plaintiff’s right to recover for this item of loss but are more
Judgment will be awarded plaintiff for $1,478.77. It is so ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.