Alaska Pacific Navigation Co. v. United States
Opinion of the Court
delivered the opinion of the court:
On and prior to December 2, 1917, plaintiff was the owner of the motor ship Oregon. On that date, while the ship was at Seattle, Wash., the United States Shipping Board, under authority of the act of June 15, 1917, 40 Stat. 182, and Executive order of July 11, 1917, delegating to that board as the representative of the President of the United States the power to take over, operate, and manage such vessels, requisitioned the Oregon.
On December 3, 1917, plaintiff and the Shipping Board entered into a requisition charter in writing, time-form basis, by which their rights and duties with respect to the vessel were defined. The charter contained the following provisions:
“ First. * * * The vessel when placed at the disposal of the United States, as directed by it, shall be or shall forthwith be made by and at the expense of the owner tight, staunch, strong, well, and sufficiently tackled, appareled, furnished, outfitted, and equipped and in every respect seaworthy and in good running order and condition. * * * Any deficiency in these respects must be remedied forthwith by and at the expense of the owner; and any time lost in remedying such deficiency is not to be paid for by the United States.
“ Eighth. The United States shall pay for the use of the-steamship at the monthly rate which shall from time to-time be established by the United States Shipping Board for a vessel of her description * * *.”
“ Twelfth. The owner shall assume the marine risks * * * 5?
“ Twenty-second. In the event of loss of time from deficiency of men or stores, breakdown of machinery * * *- preventing the working of the vessel for more than twenty-four consecutive hours, the hire shall be reduced one-half until the vessel be again in an efficient state to resume her service.”
The motor ship was afterwards turned over to the Matson Navigation Company, an agency of the Shipping Board,, for operation. The ship started on a voyage from San Francisco to Honolulu in February, 1918, when her engines broke down and it became necessary to tow her into. Honolulu. Finding that she could not be repaired in that, locality, the Shipping Board was obliged to send out a. boat to bring her to San Francisco, where she arrived sometime during April, 1918. The plaintiff took charge of the.vessel there and arranged for the repairs, as the charter required. The repairs continued from May, 1918, until June, 1919, during which time the vessel was in plaintiff’s, hands and the repairs made on its account.
The Government refused to, and did not, pay hire after February, 1918. Serious questions had arisen during the-examinations and surveys for the repairs as to whether the-breakdown of the engines was not due to defects therein at. the time of requisition. There was a difference with respect to value and rates of hire between vessels under requisition, and those not under requisition, the value being higher in the latter case. Plaintiff having received no payment for hire after Febru'ary, 1918, its attorney came to Washington,. D. C., sometime prior to October 21 for the purpose of' endeavoring to secure the payment and a settlement. He-
No written or verbal protest was made by plaintiff’s representative at or after the time he received the settlement money, nor does it appear that any objection was made to the settlement by plaintiff until August 18, 1918, when by letter it called the Shipping Board’s attention to an error in the settlement which it claimed placed the dead-weight tonnage of the ship at too low a figure. As stated in plaintiff’s letter, it was “ a mutual mistake of the parties.” The error was corrected, the account adjusted, and a sum due plaintiff on account of this adjustment was paid to and accepted by it.
On November 26, 1918, plaintiff made formal application to the Shipping Board for the transfer of the Oregon to the Alabama Steamship Co., which transfer was authorized by resolution of the board on December 16. The ship was afterwards sold to that company.
The claim involved here was adjusted upon definite and well-understood terms. It is plain that the settlement was intended to be final, and was so regarded by both parties. The principles controlling the question of a final settlement and acquiescence where the amount claimed is “ confessedly
It must be held that the settlement in this case was final and binding upon both parties. This precludes the plaintiff from a recovery. The petition should be dismissed, and it is so ordered.