Ferson v. States
Opinion of the Court
delivered the opinion of the court:
The parties in this case contracted in writing for the purchase of certain quantities of oats and 451 tons of bran, to be delivered during the months of June and July, 1920, at
The contract (Article IX) contained the following provision :
“ Sec. 2. Termination in public interest: If in the opinion of the Quartermaster General the public interest shall so require, this contract may be terminated by the United States by fifteen days’ notice in writing from the contracting officer to the contractor, and such termination shall be deemed to be effective upon the expiration of fifteen days after the giving of such notice, and shall be without prejudice to any claims which the United States may have against the contractor under this contract. After the receipt of such notice the contractor shall not order any further materials, or facilities, or enter into any further subcontracts or make any further purchases in connection with the performance of this contract without written consent previously obtained from the contracting officer; but inspection of the completed article or work and acceptance thereof by the United States in accordance with the terms of this contract shall continue during such period of fifteen days as though such notice had not been given.”
The plaintiff had a contract for the delivery of 451 tons of bran. One hundred and twenty tons were to be delivered at the price of $2.72 per hundredweight, 120 tons at $2.77 per hundredweight, 120 tons at $2.88 per hundredweight, and 91 tons at $2.87 per hundredweight. One hundred and seventy-six (176) tons were delivered, for which plaintiff was paid, leaving undelivered 275 tons. The time of delivery under the contract was June and July, 1920, on receipt of shipping instructions from defendant. The postponement, by mutual agreement, of the time of delivery did not affect the contract. It remained as it was as far as the date for fixing the market value is concerned; that is to say, the date for this purpose remained the time of delivery fixed by the contract. The extension of it was unconditional and without reservation by the plaintiff. It is to be assumed that the plaintiff knew that in purchasing the quantities of bran needed to carry out the contract ic might be called upon to pay more or less in January than in July preceding. Plaintiff was a jobber, and while it had some bran on hand in January (how much does not appear) , it did not have a sufficient amount to complete delivery under the contract. But bran was plentiful and it could have procured it in the market. Had the price of bran gone up, it is fair to assume that plaintiff would not be here contending that January was the time for estimating the market value.
It must be held, therefore, that the measure of damages is the usual measure of damages in case of a breach such as we have here, viz, the difference between the contract price and the fair market price of the commodity at the time and place of delivery fixed by the contract. This has been found by the court to be $2,281.36. Aside from this, the extension of the time of delivery in accordance with the request of the supply officer at Camp Funston, who had no authority to alter the contract by granting or agreeing to the extension, would not change the time of delivery fixed in the contract.
Plaintiff should have judgment for the amount stated, and it is so ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.