Independent Bridge Co. v. United States
Opinion of the Court
delivered the opinion of the court:
The plaintiff contracted to construct two lock gates at each of Dams Nos. 31 and 35. The work was to be complete within a definite period after September 1, 1917. The contract was made in January, 1917, and the parties entered into a supplemental contract in August, 1918, modifying the original contract in some of its features. The plaintiff also applied to the Secretary of War for relief under the provisions of section 8 of the act of July 18, 1918, 40 Stat. 912, with the result that a contract was made increasing its compensation. The work was completed in August, 1919, at one of the dams and in September, 1919, at the other dam. In making settlement for the amount or balance due the contracting officer deducted from the same the sum of $1,470.81 made up of the item of $1,234.01 for inspection and superintendence charges and $236.80 for watchman’s services. This deduction was objected to by the plaintiff and it received payment less the deduction under protest. Subsequently plaintiff made application to the contracting officer for the payment of the sum so deducted. That officer made
Article 5 of the contract for the construction of these gates provides for an extension of time within, which the work could be done in case of its noncompletion within the stipulated time and proceeds:
“ Should the time limit be thus waived all expenses for inspection and superintendence after the date fixed for completion, including all necessary traveling expenses connected therewith, and all other actual losses and damages to the United States due to the delay beyond the time originally set for completion, shall be determined by the contracting officer and deducted from any payments due or to become due the contractor: Provided, however, That no charge for inspection and superintendence shall be made for such period after the date fixed for completion of this contract, as in the judgment of the contracting officer, approved by the Chief of Engineers, shall equal the time which shall have been lost through any cause for which the United States is responsible, either in the beginning or prosecution of the work, or in the performance of extra work ordered by the contracting officer, or on account of unusual freshets, ice,*548 rainfall, or other abnormal force or violence of the elements, or by strikes, epidemics, local or State quarantine restrictions, or other unforeseeable cause of delay arising through no fault of the contractor, and which actually prevented such contractor from delivering the material or commencing or completing the work within the period required by the contract. The findings of the contracting officer, approved by the Chief of Engineers, shall be accepted by the parties hereto as final.”
There can be no question that under this contract the contracting officer, with the approval of the Chief of Engineers, was authorized to remit the charges in question. His findings, approved by the Chief of Engineers, are made conclusive upon the parties and the court should give effect to the contract provisions. The question has been frequently before this court and the Supreme Court of the United States. See Penn B'ridge Company case, 59 C. Cls. 892, 897, where the authorities are collated; National Contract Co., 59 C. Cls. 441; Moran Bros. Co., 61 C. Cls. 73, 99, 111. Nor is there any doubt under the facts that the contracting officer with the approval of the Chief of Engineers remitted the charges. After paying the plaintiff the balance due less the deduction the contracting officer, upon plaintiff’s application to him, considered the same and made a full report, which was considered first by the division engineer and then by the Chief of Engineers, who approved the contracting officer’s recommendation and authorized the payment to the plaintiff of the amount withheld. The only question suggested under these facts is whether the deduction made by the contracting officer was the exercise of his right to pass upon the matter, and he having made the deduction in the first instance whether his authority to act further was thereby destroyed. It was some time after the deduction in question that the contracting officer upon the insistence of the plaintiff made his report and recommendation, concurred in by the Chief of Engineers, which resulted in the payment to plaintiff of the amount of the deductions. This action was authorized by the contract. It was a part of the administrative duty of the contracting officer to determine in the first instance the expenses of inspection and
Case-law data current through December 31, 2025. Source: CourtListener bulk data.