Sweeney v. United States
Opinion of the Court
delivered the opinion of the court:
The plaintiff in this case responded to a proposal issued by the United States Veterans’ Bureau, District No. 8, Chicago, Ill. The situation was this: The bureau wras occupying under a lease the seventh, eighth, and tenth floors of the Leiter Building, No. 14 East Congress Street, Chicago. A new location for the bureau had been acquired in the Butler Bros.’ Building, 301 Canal Street, Chicago, eleventh and twelfth floors. The bureau was under the imperative necessity of vacating the Leiter Building by July 1, 1922, and the proposal issued solicited bids for removing the bureau from the Leiter to the Butler Building. Plaintiff offered to perform the service for $3,100 and his bid was accepted. No formal contract, except as evidenced by the proposal, plaintiff’s bid and acceptance thereof, was executed by the parties. A purchase order was duly issued to the plaintiff on June 9, 1922. On June 14, 1922, the plaintiff, with all the necessary equipment and force of employees, appeared to commence the work, and, to their utter astonishment, were denied and refused the use of the freight elevators by the representative of the Leiter Building to transport the office furniture and supplies of the bureau from its quarters to the ground floor. It was and is an established custom in this and other large office buildings in the city of Chicago to make available to incoming and outgoing tenants the free use of the freight elevators. Whether in this instance the facility was denied the plaintiff solely because of the bureau’s departure from the building does not appear; at any rate, no reason was assigned for such conduct, and the exercise of the arbitrary conduct not only seriously discommoded the plaintiff, but put upon him an extra expense of such proportions that compliance with his agreement upon the accepted consideration would entail financial loss.
The defendant opposes a judgment, basing its contention upon an assertion that the extra expense incurred by the plaintiff was in legal effect a bonus; that having contracted to perform the service for the stipulated sum of $3,100 the plaintiff could only be relieved from his contract through the intervention of acts of God or the other inevitable events which excuse performance of a contract. We believe the contention untenable. Plaintiff is not claiming a bonus; he seeks not something for nothing. It is conceded that the officers of the bureau possessed authority to make a contract for the removal of the bureau’s effects from one place to another; and if such authority obtained in the first instance, how may it be denied that it did not continue to modify the agreement when mutually' unforeseen and unanticipated events occurred which rendered the performance of the original agreement an unconscionable bargain and hardship? Both parties to the agreement entered into it with an understanding that the usual and customary facilities for its performance were available, and when they subsequently discovered that an entirely different situation prevailed there was nothing in the way of meeting the changed conditions. What the officers of the bureau did was not to increase the
The contract in suit was made in view of an established usage and custom, one long prevalent; both parties to the agreement recognized its existence, and both were equally disconcerted by its refusal. The plaintiff could not go on with the performance of his contract when he faced an additional expense of more than 50 per cent of the price he had originally agreed to charge, an expense which others similarly-situated would not have had, and had no reasonable grounds to anticipate. The bureau realized that it had no right to> insist upon performance under the changed conditions, and expressly promised that if the plaintiff would proceed the bureau would see that he received reimbursement for the extra cost. The plaintiff did proceed under these conditions and under them only. It is not unusual to increase the consideration for a contractual obligation when in the course of performance unforeseen events radically change the relationship of the contracting parties, and by so doing controversy over the terms and conditions of the original contract, is obviated and set at rest. Cook v. Murphy, 70 Ill. 96; Hostetter v. Park, 181 U. S. 30, 40. By so doing, the increased consideration is not a bonus. The cases in this court cited in defendant’s brief are inapposite. Manifestly if the plaintiff was to be paid additional compensation by way of savings he w-as under contract to save in any event, the pay
Judgment for the plaintiff for $1,671.52. It is so ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.