Newcomb v. United States
Opinion of the Court
delivered the opinion of the court:
This case grows out of an informal contract for the repairing of a derrick belonging to the defendant and for strengthening two other derricks. The derricks had been originally constructed by the McMyler Interstate Company, the original plaintiff. Since the commencement of this suit A. G. Newcomb and P. A. Connolly, .receivers, have been substituted as plaintiffs by order of the court. The contract originated in a request that the plaintiff’s company make the repairs necessary. There was no liability on the company under the original contract to make these repairs. The only question is, to what amount of remuneration are the plaintiffs entitled growing out of the making of the requested repairs.
The company did the work and the work was accepted, and it also did work amounting to $170.05 on two other derricks that needed strengthening at the request of the representatives of defendants. The conditions of pajunent were embodied in a communication from the company to the defendant, and the latter is liable for the services rendered under that proposal.
The plaintiffs’ company presented a bill which afterwards was reduced to $4,045.16, the amount sought to be recovered in this action. There was covered in this bill $134.35 for other expenses of the superintendent in arranging for the commencement of this work and also an item of $95.19 for
The plaintiffs are entitled to recover the amount claimed, less the two items of $134.36 and $95.19 just mentioned, and it is so ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.