American Can Co. v. United States
Opinion of the Court
delivered the opinion of the court:
Following certain negotiations between plaintiff company and representatives of the Government, a contract was entered into on December 31, 1917, by and between plaintiff and the Government, under the terms of which plaintiff agreed to manufacture and deliver to defendant 4,000,000 complete rounds of 75 m/m high-explosive shells, on the basis of cost, plus a variable profit, dependent upon the actual cost of the work. Plaintiff was to deliver 100,000 shells in February, 1918, and thereafter in certain specified increasing quantities each month until the month of August, 1918, when the contract was to be completed and the final deliveries made. The defendant was to furnish all the raw material and pay the entire cost of manufacture estimated at $8.18 per shell as profit. It was provided that if the actual cost exceeded $8.18 a reduction would be made in the amount allowed as profit, but the profit should never be less than 50 cents per shell. If the actual cost should be less than the estimate the profit was to be increased, but should never exceed $1.50 per shell.
On August 31, 1918, when the entire contract should have been completed under the terms of the contract, plaintiff had manufactured only 30,000 complete rounds of shells.
As the result of numerous conferences between plaintiff and representatives of the Ordnance Department, and at the suggestion of plaintiff, a supplemental contract was entered into on November 1, 1918, whereby the original contract was converted into a fixed-price contract, under the terms of
The signing of the armistice rendered unnecessary the manufacture of the remaining shells covered by this contract, and the Government desired to terminate the contract. After certain negotiations plaintiff submitted a proposal that it be permitted to complete 2,500,000 rounds, to be delivered to the United States by February 1, 1919, to be paid for at the rate of $8.50 per round, the United States to be permitted to furnish plaintiff certain component parts for which plaintiff was to pay a stipulated price, same to be deducted from the unit price of $8.50 per round. This proposal was accepted and the second supplemental contract was executed, bearing date of February 1, 1919.
Under the terms of this contract the United States paid plaintiff $8.50 each for 2,500,000 complete rounds of shells, less deductions for material delivered by the United States and less 60 cents pér shell for shells accepted which were not loaded. The Government also paid plaintiff for all materials and components which plaintiff had on hand.
On June 30,1919, plaintiff presented a claim to the proper ordnance claims board alleging its right to additional compensation growing out of extra costs on account of changes in the sum of approximately $2,500,000, which was disallowed in its entirety by the Secretary of War on March 22, 1921. No further steps were taken by plaintiff in the prosecution of its claim for more than four years. The subsequent history of the transactions between plaintiff and the Government is interesting, and we believe sufficiently important to justify a brief recital thereof. In this connection it should be stated that prior to the actual execution of the original contract, to wit, on December 19, 1917, the Government loaned to plaintiff the sum of $4,908,000 to be repaid
[In January, 1925, the Department of Justice again requested the plaintiff to permit a further examination of the books relative to the war-time transactions with the plain
It is therefore manifest that until the discovery Government of the unpaid balance on the note there had been no such frank disclosure by plaintiff of the existence-of such balance as would be inferred from the requested findings of fact hereinabove set forth, although plaintiff was in possession of exact information on the subject certainly as early as December, 1921. In fact, it is inconceivable, we think, that plaintiff did not know at all times that the note transaction was being carried on its books as an open account, showing an unsatisfied balance. It should be-remembered that the discovery of said balance could not be obtained from an examination of plaintiff’s general ledger.
In its petition plaintiff asks for a recovery of $2,638,258.20 for extra costs due to changes in the contract, less the sum of $766,291.94, the unpaid balance of the loan, the net amount being $1,871,966.26. . In its brief, however, its claim is set forth as follows:
(1) Excessive wastage of forgings due to inferior steel— $112,224. 03
(2) Excessive labor costs of making shell bodies- 203,240. 72'
(3) Extra costs of routing and handling- 483, 848.43-
(4) Extra costs of code marking- 76,063.50-
(5) Cost of lacquering, etc_ 23,872.26-
Total extra costs due to such changes- 989,248. 94
Deducting the amount admittedly due on the loan,. $766,291.94, from the above total, leaves the sum of $222,957.00 now claimed by plaintiff for extra costs due to changes, as against $1,871,966.26 claimed in its petition, and!
The first supplemental contract of November, 1918, changed the contract from a cost-plus to a fixed-price contract, the fixed price being $8.50 per shell. Plaintiff contends that a proper construction of the contract, as amended, would require the payment of the $8.50 per shell, plus or minus the increased or decreased cost occasioned by the changes. Defendant contends that the contract as supplemented by the agreements of November 1, 1918, and February 1, 1919, definitely fixed the price to be paid at $8.50 per shell. The changes upon which this suit is based were made prior to the date of the fixed-price contract, and the second supplemental contract of February 1, 1919, and it is defendant’s further contention that the matters involved in this controversy were intended to be, and were, settled under the terms of the fixed-price contract and the subsequent supplemental contract of February 1, 1919. Special attention should here be directed to article 1 of the latter contract which provides as follows:
“Artigle 1. The contractor shall deliver and the United States shall accept the following specified quantities of the articles contracted for at the prices provided in the original contract as amended, payment of which prices shall be accepted by the said contractor in full satisfaction of any and all claims arising out of the said omginal contract as hereby amended.” (Our italics.)
It will be remembered that the Government at this time desired to terminate the contract on account of the cessation of hostilities, and plaintiff, having expended considerable sums for material then on hand and in certain operations on shells then in process of manufacture, desired to continue with the contract, and made a proposal to the Government that it be permitted to complete the manufacture of at least 2,500,000 of the 4,000,000 shells under contract. The Government acceded to this proposal, and the contract was entered into by the plain terms of which plaintiff was to make 2,500,000, at $8.50 per shell. The language used in the provision above quoted is plain and unequivocal, and appears
For the reasons hereinabove set forth the court is of the opinion that plaintiff is not entitled to recover herein, and the petition will, therefore, be dismissed.
Defendant is entitled to recover on its counterclaim the sum of $766,291.94, with interest from September 22, 1919, and it is so adjudged and ordered.
Matter in brackets substituted as of May 6, 1929, by order of court June 2, 1930.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.