Crescent Plumbing & Heating Co. v. United States
Opinion of the Court
delivered the opinion of the court:
This suit arises under a contract which required plaintiff to furnish all labor and materials and perform all the work required for the construction and completion of an underground steam and hot-water distribution system in consideration of the payment by the defendant of $77,000. The invitation for bids required the submission of unit prices for the various items of work, to be used as a basis for making deductions from or additions to, the contract price provided any deviation from the drawings and specifications decreased or increased the amount of the work indicated and required therein. Plaintiff, whose bid was accepted, submitted unit prices for the various items of material and labor and included among such items “ Excavation (rock) $10 per cubic yard ” and “ Excavation (gravel or clay) $1.25 per cubic yard.”
Paragraph H-31 of the specification relating to rock excavation is set forth in finding I.
When plaintiff began excavating for the trenches it encountered loose rocks which were removed by a gasoline-power shovel, used in excavating trenches, or by pick and shovel, and it also encountered ledge rock which required blasting for removal. During the progress of the work a controversy arose, as a result of plaintiff’s claim that it should be paid $10 a cubic yard for all rock removed, whether in solid formation or consisting of loose rocks. The constructing quartermaster decided that the unit price of $10 applied only to rock that was of solid formation and, upon appeal by plaintiff, the Quartermaster General approved that interpre
The Quartermaster General’s decision of November 23,1981, addressed to the constructing quartermaster, was as follows: “ Your interpretation of the specifications that the quotation of the Crescent Plumbing & Heating Company, Inc., contractors for the underground steam and hot-water distribution system at Carlisle Barracks, which quotes a unit price of $10.00 per cubic yard for rock, should apply only to rock in place, which requires blasting for its removal or to boulders of one-half cubic yard or more in volume, is approved by this oflice.”
Plaintiff further protested the classification made, which protest was transmitted to the Quartermaster General and was accepted and treated as an appeal by the contractor under the contract, but the previous decision was affirmed and no change was made therein. In accordance with this interpretation of the contract, plaintiff was paid $10,403.60 for the excavation of 1,040.36 cubic yards of rock, at $10 a cubic yard. The amount paid covered the total yardage of ledge rock removed with the exception of 2.7 cubic yards and boulders of one-half cubic yard or more in volume, but it did not include 520 cubic yards of loose rocks and 180.92 cubic yards of the softer strata of the upper portions of the ledge rock which were removed with a power shovel in the same manner in which clay and gravel were removed.
Plaintiff contends that under the specification for rock excavation and the unit price submitted by it the defendant should have paid $10 a cubic yard for all rock, whether ledge rock or loose rocks six inches square or over, and that it is entitled to recover the excess amounts for which payment was not made. At the outset it should be noted that plaintiff’s bid was for the construction of a complete underground steam and hot-water distribution system, and that it was to be paid $77,000 for furnishing the material and carrying out the work, plus $10 a cubic yard for additional rock excavation. The unit prices, with the exception of the unit price for rock excavation, were not material in determining the total amount
The second item of the claim is that plaintiff should be paid $765.15 for the cost of insulating certain expansion joints.
The specifications provided that “ all pipes, fittings, and appurtenances that carry live steam, hot water, and drips shall be covered ”; that is, that they should be insulated. During the progress of the work a change was made in the contract, at the suggestion of the plaintiff, substituting a different type of expansion joint for that originally specified, and plaintiff contends that the substituted joints were not required to be insulated since insulation was not recommended by the manufacturer and that it was not required by the terms of the contract and the specifications. The expansion joints carried steam and hot water and, in our opinion, came within the items mentioned in the specifications set out as items to be insulated. Inasmuch as the contract unmistakably provided for this, the opinion and recommendation of the manufacturer who supplied the material, with respect to the installation and insulation, cannot govern. In these circumstances, this item of the claim must also be denied.
The final item relates to liquidated damages assessed and collected by the defendant. The contract provided that the work should be completed March 31,1932, whereas it was not completed until April 13, 1932, and the defendant accordingly asserted liquidated damages of $130 at the rate of $10 a day. Plaintiff contends that $70 of this amount was improperly assessed and should be repaid. We do not find anything in the contract or in the acts of the parties in carrying it out which would justify a remission of the penalty collected or any part thereof. This item of the claim must be denied.
Plaintiff is entitled to recover $27, and judgment will be entered accordingly. It is so ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.