Bryne & Forward v. United States
Opinion of the Court
delivered the opinion of the court:
Pursuant to an advertisement made and specifications issued by the defendant, the plaintiff made a bid for removing a wreck of a floating dry-dock from St. Thomas Harbor, Virgin Islands. The plaintiff’s bid was accepted, the work was completed one hundred seventy-six days after the contract expiration date, and the plaintiff was paid the contract price less liquidated damages at the rate of $25 a day as provided in the contract for the period of the delay. After-wards upon review, $925 was paid to the plaintiff because the Chief of Engineers recommended that plaintiff be allowed thirty-seven days additional time for completion of the work and that $925 of the liquidated damages be remitted.
The items of plaintiff’s claim are as follows:
Liquidated damages for 139 days-$3,475.00
Cost of removing ballast tanks and bottom frames_ 4, 987. 56
Expenses incurred while barge was transporting dredging material for defendant under defendant’s prior contract- 738.72
Contributory items of expense caused by plaintiffs work being thrown into the molasses season_ 8, 609.36
Total_17, 810.64
It will be observed the plaintiff is claiming that all of the deduction on account of liquidated damages for delay in the performance of the contract should be remitted and that it should be paid the full contract price. This claim is closely connected with the second item which is based on the cost of removing the ballast tanks and bottom frames. It is contended by plaintiff that the specifications did not make sufficiently clear the number of ballast tanks or the structure of the bottom frames of the dry-dock. Conceding for the purpose of the argument that the plans and specifications were not clear in this respect, this would furnish no basis
As a further warning it was stated:
Bidders are expected to visit the wreck and ascertain for themselves its exact location and condition and make their bids accordingly, as the accuracy of the-above description is not guaranteed.
Plaintiff was notified that there were ballast tanks but-for some reason, as stated in a letter from plaintiff to the-contracting officer, expected to find only four although there were in fact ten of the tanks. The map of the wreck which went with the specifications showed in a general way the-location of the ballast tanks and the structure of the frame. Whether the number of the tanks was made plain we need not determine as under the contract this was for the plaintiff to find out for itself or take the risk. There was no-misrepresentation of conditions or any statement that would tend to mislead the plaintiff. The member of plaintiff’s firm who was a diver made a perfunctory examination of' the wreck. That it did not disclose the number of ballast tanks was the fault of plaintiff and not of defendant.
The contracting officer, however, took a lenient view of plaintiff’s contract and when plaintiff asked for a supplemental agreement allowing thirty more working days for the completion of the work the contracting officer requested authority to make a change order involving an increase of thirty-seven calendar days in plaintiff’s completion time and this order was subsequently authorized. December 15, 1931, the contracting officer advised the plaintiff that he had concluded to accept its offer but by that time the plain
The findings show that plaintiff agreed to complete the job in one hundred days, the completion date being November 19,1931, but did not actually finish it until one hundred seventy-six days thereafter. In other words, plaintiff exceeded by more than five months the time for completing a work estimated to require only a little over three. Plaintiff
Plaintiff’s petition must be dismissed and it is so ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.