McShain v. United States
Opinion of the Court
delivered the opinion of the court:
This suit arises out of a contract between the plaintiff and the defendant dated February 6, 1933, for the construction by the plaintiff for the defendant of a hospital in the Navy Yard at Philadelphia, Pa. On September 14, 1933, the defendant notified the plaintiff that the remainder of the contract work would be done in conformity with the requirements of the National Industrial Recovery Act, 48 Stat. 195; 15 U. S. C. A. Sec. 102, 712. On November 9, 1933, a supplemental agreement was executed whereby the plaintiff agreed that further performance of the original contract would be carried on conformably with the National Industrial Recovery Act. The plaintiff alleges compliance by
This action is based on the special jurisdictional act approved June 25,1938 (Public, No. 741, 75th Congress, chap. 699, 3d session, S. 3628), which confers jurisdiction upon this court to hear “and enter judgments against the United States upon the claims of contractors, including completing sureties and all subcontractors and materialmen performing work or furnishing material to the contractor or another subcontractor, whose contracts were entered into on or before August 10, 1933, for increased costs incurred as a result of the enactment of the National Industrial Eecovery Act: Provided, That (except as to claims for increased costs incurred between June 16, 1933, and August 10, 1933) tins section shall apply only to such contractors, including completing sureties and all subcontractors and materialmen, whose claims were presented within the limitation period defined in section 4 of the Act of June 16, 1934 (41 U. S. C., Secs. 28-33).”
The defendant has demurred to the complaint on the ground that the act does not permit the plaintiff to sue for claims which have not been paid by him or which he has not incurred himself.
The act above referred to is in the nature of an amendment to the act of June 16,1934,48 Stat. 974, and enlarges the classes of those who can maintain a right of action against the United States for losses sustained under the National Industrial Eecovery Act. The act of 1934, which this court had under consideration in the case of John B. Kelly, Inc., v.
The decision in the case of Leary Construction Company v. United States, 63 C. Cls. 206, 224, is to be distinguished. In the Leary case the contractor was suing in behalf of his subcontractors because the subcontractors had no privity interest in the contract. They could not maintain an action against the defendant under the prime contract. We held that the contractor was entitled to maintain an action for the amounts due and which were to be paid to his subcontractors. In the instant case the subcontractors had no privity to the contract to sue the defendant but Congress,
It is true that courts do not favor multiplicity of suits and endeavor to lay down rules of procedure to avoid unnecessary litigation. See Electric Boat Company v. United States, 81 C. Cls. 361. However, in the instant case, there is the right which continues to the subcontractors of the prime contractor which has been granted by Congress and, whether it incurs numerous suits or great expense, the courts must bow to the wisdom of Congress in enacting legislation. Under this statute, where a subcontractor has been paid by the prime contractor, the subcontractor has no claim remaining and cannot sue, but the prime contractor, who has made payment to the subcontractor, can sue for the amount so paid and recovery can be had in the amount established by competent evidence of the losses incurred by the subcontractor. The payment by the prime contractor to the subcontractor is not an assignment of the claim under the National Industrial Recovery Act, since it is the result of contractual relations entered into before the act of June 25, 1938, was approved, and, having paid the subcontractor, the prime contractor is the proper party plaintiff.
Who is the proper plaintiff depends upon what has been done between the prime contractor and the subcontractor by virtue of the contractual relations between them and does not depend upon what one or the other was or is obligated to do. This follows from the fact that Congress gives the subcontractor a right to sue as well as the prime contractor. It therefore follows that the prime contractor may sue for the recovery of National Industrial Recovery Act wages actually paid (1) directly by himself, or (2) indirectly by payments to subcontractors, and not otherwise; and that subcontractors may sue for and recover wages actually paid (1) directly by themselves, or (2) indirectly by payments to sub-subcontractors, and not otherwise. The final subcontractor may sue for and recover only those wages which he has paid and for which he has not been reimbursed by his principal.
The demurrer is overruled so far as the right of action of plaintiff to sue for himself and those to whom he has made payment, and is sustained for all those to whom plaintiff has not actually made payment. The case will be referred to a commissioner with instructions from the court to permit no evidence to be taken of any losses not actually incurred or claims of subcontractors not actually paid by plaintiff. It is so ordered.
(Note. — Plaintiffs motion to amend opinion announced November 14,1938, and for leave to file amended petition; and plaintiff’s motion for leave to file second amended petition — both overruled, January 9,. 1939.)
Case-law data current through December 31, 2025. Source: CourtListener bulk data.