Johnston v. United States
Opinion of the Court
delivered the opinion of the court:
The contract involved in this suit called for and required the construction of a levee and the excavation of a drainage canal of about five miles in length on the Mississippi Eiver near New Madrid, Missouri. The pertinent portions of the contract and specifications are set forth in the findings. The contract provided that the material for the levee should be, and it was, procured from excavation of the drainage canal which was dug landward of the levee and parallel thereto. The construction of the levee necessitated excavation for the drainage canal inasmuch as existing drainage ditches
Plaintiffs insist that they were not paid for 69,569 cubic yards of material required to be excavated in constructing the levee, and that no payment was made for 2,451 cubic yards of material excavated and placed in road crossings at certain points in the levee; that the defendant erroneously and illegally failed to pay plaintiffs with respect to 5,537 cubic yards at 25 cents a cubic yard for material which had been excavated by another government contractor and placed at the site of the levee constructed by plaintiffs, and that the defendant illegally, and in violation of the contract, deducted and withheld $770 as liquidated damages for 77 days’ delay in completing the contract.
We are of the opinion that under the provisions of the contract and upon the facts disclosed and established by the record that plaintiffs are entitled to recover only on the third item of their claim.
It is unnecessary to discuss the facts in detail other than to state that as to the first item they show clearly that measurements for payment were made in accordance with the contract and specifications and that plaintiffs have received payment of the entire amount to which they were entitled under the contract. The contract and specifications are clear that plaintiffs were only entitled to be paid on the basis of the dimensions of the net levee section or the cubical content of the corresponding required canal section, whichever was greater. The record establishes that payment was made on this basis. Plaintiffs contend that they were required to excavate yardage from certain sections of the canal in excess of the dimensions of the required drainage canal section for which they claim payment. But this contention is not supported by the evidence. Plaintiffs are, therefore, not entitled to recover on the first item of the claim.
With reference to the second item of the claim for $612.75 for 2,451 cubic yards of material placed in constructing road crossings on the levee at certain stations where canal yard-, age was paid for,- plaintiffs contend that because such yardage was procured beyond the drainage canal limits and
The facts' with reference to the third item of the claim for $1,384.25 are set forth in finding 9. They show that this material iof 5,537 cubic yards was placed in the levee by Clarke Brothers Construction Company, which company, under contract with the defendant, was engaged in the excavation of two drainage ditches along the northern part of the site of the levee called for by plaintiffs’ contract. In measuring for payment to plaintiffs at this section, the defendant excluded this yardage from the dimensions of the net levee in that section and made payment to plaintiffs accordingly. We are of opinion that the defendant was without authority under-the contract with plaintiffs to make this deduction. While the plaintiffs did not excavate "and
The last item of the claim relates to liquidated damages of $710 deducted by the defendant for 77 days’ delay in completing the contract on time at the rate of $10 a day. The facts with reference to this delay are set forth in finding 11. They show that plaintiffs are not entitled to recover. It is clearly established that the delay of plaintiffs in properly prosecuting the work caused the work to extend
Moreover, the plaintiffs did not comply with the provisions of Art. 9 which provide that the contractor should within ten days from the beginning of any delay notify the contracting officer in writing of the causes thereof and that the contracting officer should ascertain the facts and extent of the delay and that his findings of fact should be final and conclusive, subject only to appeal within thirty days to the head of the department whose decision on such appeal as to the facts and the delay should be final and conclusive. The contracting officer found as a. fact that the delay in completing the contract on time was the fault of plaintiffs.
Judgment will be entered in favor of plaintiffs in the amount of $1,884.25. It is so ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.