Pittsburgh Plate Glass Co. v. United States
Opinion of the Court
Plaintiff, the Pittsburgh Plate Glass Company, sues to recover increased labor costs pursuant to the Act of Congress approved June 25, 1938 (52 Stat. 1197), entitled βAn Act to confer jurisdiction on the Court of Claims to hear, determine, and enter judgment upon the
It appearing that plaintiff qualifies under the Act of June 25, 1938, and it further appearing that there has been compliance with the memorandum and order as to procedure in submitting proof of increased costs issued February 1, 1939, by the court, and the court having found that plaintiff in the performance of the contracts incurred increased labor costs in the amount of $1,892.05 as a result of enactment of the National Industrial Becovery Act, it follows that plaintiff is entitled to recover that amount. It is so ordered.