Smith v. United States
Opinion of the Court
delivered the opinion of the court:
The plaintiff sues for a balance which, he asserts, has not been paid him for the rental of his power shovel for use on a Civil Works Administration project at Beltsville, Maryland. The project consisted of road building and other activities on a Department of Agriculture Experiment Station. It was a relief project, designed to give employment to persons on relief rolls. Because of the greater accomplishment which could be produced by combining a certain amount of mechanical equipment with the hand labor, machines such as the plaintiff’s shovel were hired. In order, apparently, to give the impression that practically all of the civil works money was being paid for personal labor, which was the primary object of the Civil Works Administration, rather than for material and the use of equipment, a pay roll called the Team, Truck, and Equipment pay roll was used in addition to the regular labor pay roll.
The operator of a rented machine was placed on this pay roll, and he was paid the entire amount of the agreed rent for the machine which he operated, whether he owned it or
The petition will be dismissed. It is so ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.