Fidelity & Deposit Co. v. United States
Opinion of the Court
delivered the opinion of the court:
The Yang Construction Company, herein referred to as the contractor, entered into a unit-price contract with defendant dated November 9, 1932, for the construction of a lock and dam across the Allegheny River about five miles from Pittsburgh, Pennsylvania. Eight items involving a powerhouse, lock machinery, and other machinery and equipment were lump-sum items. All others were unit-price items. The estimated contract price based on these lump-sum items and other estimated quantities for the unit-price items was $1,190,251.48. The contractor’s bid, which was accepted, was submitted October 14, and prior to October 24, 1932, it was advised by defendant that the contract had been awarded to it. The contractor, with the consent of defendant, began construction operations under the specifications and drawings October 24,1932, and, subsequent to November 9, signed the formal contract and furnished a performance bond on which plaintiff was surety. The contract was signed and the bond approved by defendant December 6, and the contractor received formal notice to proceed on the following day, December 7, 1932. This fixed the completion date, for a period of 450 days, as March 1st, 1934.
While the contractor was continuing with the work a receivership proceeding was filed against it July 11,1934, and, on the same date, the U. S. District Court for the Western District of Pennsylvania appointed receivers for the contractor. Under authority given by this decree the receivers on July 13 elected to disaffirm the contract between The Vang Construction Company and the defendant and notified the contracting officer of their refusal to accept the contract and proceed with its completion. Thereupon, and on the same day, the plaintiff, as surety on the contractor’s performance bond, entered into a supplemental contract with the Govern
In completing the contract work plaintiff used substantially the contractor’s organization, including its employees and laborers, and expended $138,301.38 for such completion. In addition plaintiff paid $156,145.56 for material and labor claims against the contractor which had accrued at the time of appointment of the receivers. These two amounts total $294,446.94.
During and upon completion plaintiff received from the Government progress payments for contract work performed by it in amounts totaling $78,270.96. This amount included $15,114.72 allowed but not paid to the contractor on progress estimate no. 23. On the final payment voucher plaintiff also received $88,671.80 representing the total of the retained percentages due after deduction by defendant of $16,042.92 for liquidated damages for 53.5 days’ delay. The total of the amount so paid to plaintiff by defendant was $166,942.67. The sum of $50,000 of the retained percentage of $88,671.80 above-mentioned represents amounts withheld by defendant from prior progress payments earned by and paid to the contractor. In addition to the amount of $166,942.67 received from the Government upon completion of work, plaintiff also received from the contractor $98,216. The total of the amounts which plaintiff received from the Government and the contractor was $265,068.76, and inasmuch as plaintiff had paid out for completion of the contract work and on material and labor claims against the contractor a total of $294,446.94, its loss was $29,378.18. The total paid plaintiff
The first item of the claim is $8,143.88 for alleged excess cost of reconstructing the first of two concrete caissons which the contractor, with the consent of defendant, elected to use as the foundation for the abutment of the dam. The reconstruction cost was $6,013.34 (finding 19). The proof does not show that rebuilding of this caisson delayed the final completion of the contract work.
The specifications and original plans required the contractor to build a cofferdam around the area of the foundation for the abutment and, after pumping the area dry, to construct the concrete foundation. However the contractor proposed the caisson method and asked permission to use it. This permission was granted by change order no. 1 which authorized the contractor at its own expense and risk (finding 8) to use two caissons, each 75 feet long, 28 feet wide, and 30 feet high, with walls and three partitions 8 feet thick above the working chamber. The change order specifically provided that the contractor would be responsible for the construction and the sinking of the caissons and that “any
It is now claimed on behalf of the contractor that the breaking of the caisson was caused by the unauthorized and arbitrary action of defendant’s inspector in requiring the contractor to use unworkable concrete that was too dry to permit it to bond properly with reinforcing rods in the cutting edge and walls of the caisson, but this claim is not sustained by the evidence. The inspector’s actions and instructions were taken and given in an honest effort to exact
If it be assumed, however, that the inspector in his instructions exceeded his authority under the specification provisions relating to concrete and that plaintiff is not barred by its failure to protest to the contracting officer, the contractor still cannot recover on this claim for the reason that the far greater weight of evidence shows that the break in the caisson was due not to the weakness of the concrete but to the manner
The second item of the claim is $26,146.32 for alleged loss of profit and excess cost of constructing the third section of the cofferdam for the final section of the dam across the river where it joined the navigation lock. The contract required the concrete navigation lock and all of its machinery and equipment to be completed and opened for the flow of water and for navigation purposes before the cofferdam for the final section of the dam was constructed. The claim is based on alleged excess cost of the third section of the cofferdam over the cost of the adjoining second section previously constructed. The proof does not show that such excess cost was more than $12,255.36 (finding 36).
The basis of this claim is that defendant by misrepresentations in the specifications and drawings as to subsurface conditions at the lock site delayed the contractor in completion of the lock, thereby throwing the work of constructing the third cofferdam section into winter weather and a period of high water which rendered such construction more difficult and expensive than the contractor had anticipated, or was required to expect.
The proof conclusively shows that defendant made no such misrepresentation as to subsurface conditions at the lock site as would render it liable for damages as for a breach of contract for any additional time required on account of the subsurface conditions actually encountered. This was a unit-price contract as to all excavation and concrete work that might be necessary or required. The contractor was given extensions of time for all extra work due to changes, unforeseen conditions, and various other causes, and was paid the contract unit prices for all work performed. Eock was encountered by the contractor above the rock elevation indi
The contracting officer gave the contractor an extension of time of 30.4 days in accordance with change order no. 5 (finding 24) for all work connected with or incidental to additional rock excavation, including such excavation and other work as made necessary by reason of the extension of foundations, all of which work was included in the terms of the change order and the formula set forth therein for determining additional time to be allowed. The proof does not show that this extension of time was inadequate to cover the time needed and used for the additional work covered thereby. Moreover, when the contractor protested June 18, 1933 that change order no. 5 of January 24 did not include such time as might be necessary in connection with concreting operations for the extended foundation and the contracting officer held that the formula set forth in the change order did include such work, the contractor did not appeal to the head of the department until six months after the contracting officer first denied its claim for additional time.
For the reasons stated we hold that defendant did not breach its contract in relation to the navigation lock structure by preventing the contractor from completing the same by October 25,1933, as it claims. It follows, therefore, that defendant is not liable for any excess costs that may have been sustained by the contractor or plaintiff in construction of the third and final section of the cofferdam for the river dam.
The last item of the claim is for $16,042.92, liquidated damages charged and deducted by defendant for 53.5 days’ delay. The proof does not establish that defendant was responsible for this delay in completion of the entire work by the contractor and plaintiff. No protest or appeal .was taken, as required.
Plaintiff is not entitled to recover and its petition is dismissed. It is so ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.