Kentucky Metal Products Co. v. United States
Opinion of the Court
The amount of increased cost for material claimed in this suit is $1,286.84 for the ten subcontracts ; the claimed increased costs on the Billings, Mont., and Jonesboro, Ark., subcontracts are $12.46 and $2.87, respectively. No increased costs prior to August 10, 1933, are claimed.
On the evidence submitted plaintiff has not shown what amount of increased cost, if any, was incurred for material as a result of enactment of the National Industrial Kecovery Act.
On the two subcontracts and the eight sub-subcontracts mentioned in the findings plaintiff incurred increased labor costs of $1,106.04 subsequent to August 10,1933 as a result of the enactment of the National Industrial Kecovery Act, but plaintiff filed claims for increased costs under the act of June 16, 1934, only with respect to its two subcontracts in connection with the buildings at Billings and Jonesboro, and the increased labor costs incurred under these subcontracts amounted to $13.36 and $0.30, respectively. Plaintiff says, however, that as to eight of the buildings in respect of which it did not file claims it was a sub-subcontractor
Judgment will be entered in favor of plaintiff for $13.65. It is so ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.