Lym-Horman Constraction Co. v. United States
Opinion of the Court
delivered the opinion of the Court.
The plaintiff, a partnership engaged in the general construction business, on August 3, 1948, made a contract with the Government, which acted through the Federal Public Housing Authority, to construct a large number of dwelling units at Hiawatha, Utah. The construction was a war housing project to house coal miners employed by the United States Fuel Company, a private corporation. The contract price, as modified by change orders, was $314,205.36, and the plaintiff was paid this amount. The work was to be completed within ninety days after the .receipt of notice to proceed, which notice was given on August 17,1943. In fact the work was not completed until many months later, but no liquidated damages for delayed completion were assessed against the plaintiff, as it was given extensions of time adequate to account for the delay.
It cost the plaintiff $408,593.55 to perform the contract, and it seeks to recover its loss, plus a reasonable profit, on the ground that its loss resulted from breaches of contract by the Government. Most of its unanticipated costs, and therefore its losses, probably resulted from the fact that it did not get as far along with its work as it had expected to before the onset of winter weather which, in particulars recited in our findings, made construction difficult and expensive.
The land on which the houses were to be built belonged to the United States Fuel Company. It had, in former years, had one or more coal loading tipples on the land, and a great
The plaintiff having agreed with the Fuel Company on August 6 to remove the coal, the Government is, of course, in no way responsible for any harm which its late removal may have caused the plaintiff. If the plaintiff did not, as it says, have sufficient equipment to both remove the coal and get its grading done in time to avoid winter construction, it should not have undertaken to do both. Having so undertaken, it had no one to blame but itself for any harmful delay which may have resulted from its late removal.
The contract drawings, which the plaintiff had in its possession when it made its bid, showed the three-inch line mentioned above, and noted that it had a pressure of 180 pounds. The plaintiff visited the site and talked with the United States Fuel Company’s Mining Superintendent. It learned that the water line and the water supply belonged to that company, and was told that it might use water for construction purposes without charge.
The contract required that earth in fills be compacted by rolling in layers not exceeding six inches, each layer to be sprinkled before rolling. On a project of this size, a considerable amount of water was needed, for this compacting of fills and for mixing cement and mortar. There was a shortage of water in the reservoir, in September and early October, so that water had to be used sparingly. On one occasion the Mining Superintendent found that a hose was left running open uselessly and he shut off the water supply for twenty-four hours. For about a week, water was shut off for parts of days. For a time, a valve was clogged in the line which prevented the water from coming down. When the trouble was discovered, it was fixed. From September 15 to October 15 there was only enough water to supply a %-inch hose.
The plaintiff asserts that the Government misrepresented, probably innocently, to it that there was sufficient water avail
The plaintiff asserts that, whether.or not the Government misrepresented the facts as to a supply of water, the inadequacy of the supply, which we have found, was an unforeseen condition which brought into play Article 4 of the contract, quoted in finding 3, and entitled the plaintiff to a compensating increase in the contract price. There might be merit in this contention, if we. could ascertain whether, and if so, to what extent, the shortage of water increased the plaintiff’s costs. The plaintiff began its work late in August. That left it a relatively short time to work before cold weather. The diversion of its machines to the removal of coal, rather than to grading the site, may have delayed it. It says it did delay it. It had shortages of labor, materials and equipment, and was delayed by these. Its working time before cold weather was so short that almost any delay at all might have been crucial. We do not find that the water problem was, to any ascertainable extent, the cause of the plaintiff’s delay and damage.
The plaintiff’s petition will be dismissed. It is.so ordered.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.