John V. Boland Construction Co.
Opinion of the Court
Contract; disputes; administrative remedies; failure to exhaust; limitation of actions. — Plaintiff filed its petition on
The case came before the court on defendant’s motion for summary judgment and plaintiff’s response thereto. Upon consideration thereof, together with oral argument of counsel, the court concluded that plaintiff had failed to exhaust its administrative remedy by failing to file a timely appeal from the Claims and Appeals Board and also that the claim was barred by the six-year statute of limitations (28 U.S.C. § 2501 (1958)) in that the petition was filed more than six years after the claim first accrued. On January 19,1962, the court ordered that the petition be dismissed. Plaintiff’s petition for writ of certiorari was denied by the Supreme Court, 370U.S.911.