Gelco Builders & Burjay Construction Corp.
Opinion of the Court
Plaintiff on behalf of itself and its subcontractors seeks an equitable adjustment under the Changes provision of its contract with the Government Services Administration for the installation within a specified period of a central air conditioning system in the main Post Office in New York City and the Morgan Annex. Before issuance of the invitation for bids, the Government had entered into five other contracts with different contractors to perform in essentially the same work areas where plaintiff was to perform. Plaintiff’s work and that of its subcontractors was interrupted and delayed by GSA and the Post Office Department, particularly because of the priority given to the contractor engaged in the erection of the mail flow conveyor system in the same area as plaintiff. Trial Commissioner William E. Day issued a report on March 4, 1971 concluding that the repeated rescheduling of plaintiff’s work and that of its subcontractors made necessary by defendant’s unreasonable deference to the other contractors constituted a change in the contract work compensable by an equitable adjustment in the contract price; and that effective control over the work of plaintiff and its subcontractors was exercised not by the contracting agency
Case-law data current through December 31, 2025. Source: CourtListener bulk data.