Ravenna Arsenal, Inc.
Opinion of the Court
Contracts; changes; constructive change. — Plaintiff seeks Wunderlich Act review of a denial of its claim by the Armed Services Board of Contract Appeals (74-1 BCA pára.10375) for additional compensation for reworking of 130,000 155mm shells directed by defendant. Plaintiff claims that the specification was changed by the practice of the parties — or by acquiescence of defendant in the practice of plaintiff alone— of measuring cracks in the shells at their narrowest width; and also claims that defendant’s insistence upon or resurrection or reimposition of the contract standard was a constructive change. The Board held that both parties had used
Case-law data current through December 31, 2025. Source: CourtListener bulk data.