Manpower, Inc. of Tidewater
Opinion of the Court
Contracts; breach; erroneous estimate; implied contract to furnish adequate warehouse facility; delays in furnishing materials; damages; total cost theory. — Plaintiff contracted to furnish segregation,' identification, inventory, location and data processing services for materials contained in the supply allowance of the aircraft carrier U.S.S. Forrestal. Performance of the inventory contract, originally scheduled to take 39 days required 46 days, a delay plaintiff says was attributable to a series of contractual breaches by