R/W Contracting
Cases that cite this one
1 later published case cites this decision.
- Prevado Village Partnership v. United States (Court of Claims 1983)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
Contracts; changes; acceleration claim; oral modification; necessity for written approval; implied in fact contract.— Plaintiff was awarded a fixed-price contract to perform certain runway repairs at Blytheville Air Force Base, Blytheville, Arkansas, the work to be performed within 45 days. Prior to commencement of performance the contracting officer by letter presented an offer to plaintiff for acceleration of the work, subject to written approval of higher authority. However, the contractor at no time entered into any written acceleration agreement with the