Massman Construction Co.
Opinion of the Court
"This contract case comes before the court on defendant’s motion for summary judgment. The petition alleges that defendant has breached its implied obligation to render a prompt decision on a claim for an equitable adjustment under a contract.
"But the Manpower decision teaches that, where suit is filed after there has been an initial administrative determination (as there was by the contracting officer here), claims under the contract may be treated as breaches only where the Government’s delay has caused the contractor to abandon the administrative process. Here, plaintiff cannot complain about the board’s failure to decide its claim, for board rules required that a complaint be filed, 33 C.F.R. § 210.4(c), (g), Rules 2, 6 (1976), a step which plaintiff took only in late November 1977. Thus, even if allegations concerning the regional counsel’s treatment of plaintiffs efforts to negotiate were true or false, plaintiff nonetheless could have instigated board proceedings at any time by the required complaint. Plaintiffs failure to do this cannot be blamed on the Government.
"Plaintiff thus cannot demonstrate injury caused by governmental breach of the implied covenant to resolve disputes in a reasonable time.
"it is therefore ordered, upon the written submissions of the parties, but without oral argument, that defendant’s motion for summary judgment is granted and plaintiffs petition is dismissed without prejudice.”
Case-law data current through December 31, 2025. Source: CourtListener bulk data.