Robert McMullan & Sons, Inc.
Opinion of the Court
Under Contract No. 62474-75-C-6398, dated March 26, 1976, plaintiff agreed to install, as part of the replacement of a steam heating system, six fuel oil tanks near six buildings at PSNS. The present controversy arose from the excavation for one such tank, adjacent to Building 502.
The excavation was required to be twelve feet deep, twelve feet wide, and twenty five feet long. The record noted that because Stirrett had not previously excavated to the depth required for the Building 502 tank, it subcontracted with Manning Construction (Manning) to excavate the 502 site. A pre-bid notice was issued to prospective bidders which warned them to take such steps as may be reasonably necessary to ascertain the general and local conditions which could affect the work and the cost thereof. Neither the bid specifications or drawings, nor the contract, included any data from boring samples or other soil investigations of the areas to be excavated. Significantly, neither plaintiff nor Stirrett nor Manning conducted any soil tests in the area or inquired of the Navy whether it had any soil profiles in the area of Building 502.
The excavation work adjacent to Building 502 was commenced on August 5, 1976. When the excavation reached the eight foot depth, a slight water seepage was encountered. By the next day, the water had risen to a level approximately five feet below the surface. Substantial
We conclude the Board’s decision must be affirmed. Our decision, of course, must comport with Wunderlich standards. Although the Board’s decision in this case entails to some extent an interpretation of the "Differing Site Conditions” provision of the contract, it is evident that the factual issues are more central to the decision and that the Wunderlich standard of review for factual determinations is required. See Charles T. Parker Constr. Co. v. United States, 193 Ct.Cl. 320, 333-34, 433 F.2d 771, 778 (1970). Here, plaintiff and its subcontractors conducted a cursory investigation of the site prior to plaintiffs submission of a
The Board found the testimony of the Government’s expert to be "most persuasive.” It was the opinion of the expert that none of the subsurface conditions at the 502 site were unusual, and that a contractor could anticipate subsurface drainage from the hills located on two sides of the site. "The Board of Appeals, as the original trier of fact, is in the best position to determine the credibility of the witnesses examined and the weight to be accorded to the testimony presented by the witnesses.” Wm. A. Smith Constr. Co. v. United States, 188 Ct.Cl. 1062, 1077, 412 F.2d 1325, 1333 (1969); See Arundel Corp. v. United States, 207 Ct.Cl. 84, 515 F.2d 1116 (1975).
Despite plaintiffs position, there is sufficient evidence in the Board’s findings of fact to constitute substantial evidence that the subsurface conditions actually encountered at the 502 site were not materially different from the usual conditions in the area, and that a "Category II” condition did not exist. Moreover, the Board’s decision is correct in its interpretation and as a matter of law.
All other arguments raised by the parties, though not directly addressed by this order, have been examined and found to be without merit.
Accordingly, it is therefore ordered, on consideration of the record and parties’ submissions, but without oral argument, that plaintiffs motion for summary judgment is denied, defendant’s cross-motion for summary judgment is granted, and the petition is dismissed.
To be granted relief under the Differing Site Conditions clause of the contract, the conditions encountered must fall within one of two distinct sets of circumstances, often referred to as "Category I” and "Category IT’changed conditions. "Category I” changed conditions occur where subsurface or latent physical conditions at the site differ materially from those indicated in the contract. "Category II”, which is applicable here, involved unknown physical conditions at the site of an unusual nature differing materially from those ordinarily encountered and generally recog-nised as inhering in work of the character provided for in the contract.