Opinion of the Court
Contracts; delay; excusable delay; liquidated damages.— Plaintiff seeks review under Wunderlich Act standards, 41 U.S.C. §§321-22 (1976), of a decision of the Armed Services Board of Contract Appeals (the board) rejecting plaintiffs challenge to the imposition of liquidated damages for an unexcused delay of 286 calendar days in the contracted-for expansion of the electrical distribution system at the Naval Air Station, Cecil Field, Florida. On August 4, 1981 Trial Judge Roald A. Hogenson filed a recommended decision (reported in full at 29 CCF]j81,745) concluding that the board’s decision is entitled to finality, as supported by substantial evidence and not contrary to law. The trial judge found that the 286 calendar days of delay, unexcused by the contracting officer, were not beyond the control and without the fault of plaintiff and its subcontractors and suppliers. Rather, the delay resulted from plaintiffs poor management and inadequate material procurement methods. On February 23, 1982, the court, by order, adopted, as modified, the recommended decision of the trial judge as
Case-law data current through December 31, 2025. Source: CourtListener bulk data.