Lasker-Goldman Corp. v. United States
Opinion of the Court
OPINION
This case is before the court after argument on defendant’s motion to dismiss the complaint or, in the alternative, for summary judgment and plaintiff’s opposition thereto. Plaintiff’s cross-motion for partial
FACTS
Plaintiff is a sub-subcontractor of Associated Universities, Inc. (“AUI”), under a contract between the latter and the United States Department of Energy (the “DOE”) to operate the Brookhaven National Laboratory (“Brookhaven”). AUI subcontracted with Ammann & Whitney, Inc., and Safeguard Construction Management Corp., both Delaware corporations (the “Joint Venture”), for construction of an “intersecting storage accelerator” at Brookhaven. On October 27, 1980, the Joint Venture subcontracted with plaintiff to furnish materials, plant equipment, and all labor and services necessary for construction of the accelerator. A revised version of the contract between the Joint Venture and plaintiff was signed on January 31, 1981. Both contracts were subject to DOE’s approval. The new contract incorporated, inter alia, a revised Disputes clause to eliminate appeal to the DOE.
In its motion defendant revealed that on April 27,1983, plaintiff sued the Joint Venture and AUI in New York State Supreme Court claiming damages for expenses incurred by plaintiff in complying with changes to the contract work required by the defendants to that suit. Lasker-Goldman Corp. v. Ammann & Whitney, Inc., et al., No. 17768/83 (N.Y.Sup.Ct.). On June 15, 1983, plaintiff filed suit in this court against the Government based on identical claims. Defendant also produced at oral argument a copy of an order entered on August 8,1983, in the state court litigation dismissing the amended complaint as to AUI based on lack of privity.
DISCUSSION
Defendant has moved to dismiss the complaint on the ground that no privity of contract exists between plaintiff and the United States. According to defendant, plaintiff could only show privity by demonstrating that the Joint Venture acted as an agent of the United States in contracting with plaintiff. In that case the pendency of plaintiff’s suit against the Joint Venture and AUI would deprive this court of jurisdiction. 28 U.S.C. § 1500 (1976). The dismissal of the state court litigation as to AUI avoids this argument. Plaintiff admits that the Joint Venture was not acting under the authority of the United States, arguing instead that the Joint Venture and defendant were independent parties to the same contract and that plaintiff has the right to sue each party where it can find jurisdiction.
The Federal Circuit has spoken on the issue of whether a subcontractor may sue the Government directly under the Contracts Dispute Act of 1978, 41 U.S.C. §§ 601-613 (Supp. V 1981) (the “CDA”), when the Government did not execute the subcontract, when the subcontract was subject to prior government approval, and when the Government disclaimed a contractual relationship between itself and the subcontractor. United States v. Johnson Controls, Inc., 713 F.2d 1541 (Fed.Cir. 1983). Lack of privity bars such a suit.
Plaintiff puts forward three arguments to support its contention that the Government is a party to plaintiff’s contract with the Joint Venture. First, plaintiff reproduces the signature block of the contracts, which contains the signature of Vern F. Witherill for DOE. Plaintiff’s reproduction, however, omits article 5 of the contracts, which appears directly above the signature block in each contract and states:
This Contract is subject to the written approval of AUI and DOE and shall not be binding unless so approved. Such approval shall be effective as of the effective date of this Contract. This Contract does not bind nor purport to bind the Government.
Johnson Controls points to such a disclaimer as manifesting the lack of intention to bind the Government. Johnson Controls, 713 F.2d at 1553.
Finally, plaintiff adduces as evidence of the existence of a contract between itself and the Government the fact that it was required to furnish Miller Act performance and payment bonds, although the Joint Venture was not.
CONCLUSION
Defendant’s motion to dismiss the complaint is granted, and the Clerk of the Court will dismiss the complaint for lack of jurisdiction of the subject matter.
IT IS SO ORDERED.
. A similar limitation in the prime contract between the Joint Venture and AUI is vitiated,
. Although the terms of the performance bonds imply that there is some doubt as to whether they are Miller Act bonds (“[i]f the said contract is subject to the Miller Act .... ”), instruction 1. on the payment bonds states that “[T]his form ... shall be used whenever a payment bond is required under ... [the Miller Act].”
. At argument plaintiffs counsel advised that settlement would be accomplished within several weeks. The court allowed the parties approximately five weeks within which to file a stipulation of dismissal to obviate the need to rule on defendant’s motion. Plaintiff has now moved to defer the ruling further because settlement has all but been concluded and payment will likely be received in order to allow filing a stipulation of dismissal by January 10, 1984, or even within one week from this date. Defendant took the position that the settlement was without regard to the disposition of this case. In these circumstances further deferral of the ruling on defendant’s motion is not warranted, especially given the conclusion that jurisdiction is lacking.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.