Northern Pac. R. v. Sanders
Opinion of the Court
The complaint in this case sets forth a cause of action in the nature of ejectment to recover the possession of section 21, in
“There be and is hereby grantee! to the Northern Pacific Railroad Company, its successors and assigns, for the purpose of aiding in the construction of said railroad and telegraph lines to the Pacific coast, and to sécure the safe and speedy transportation of the mails, troops, munitions of war, and public stores over the route of said line of said railway, every alternate section of public land not mineral, designated by odd numbers, to the amount of twenty alternate sections per mile on each side of said railroad line as said company may adopt- through the territories of the United States, and ten alternate sections of land per mile on each side of said railroad whenever it passes through any state, and whenever on the line thereof the United States have full title, not reserved, sold, granted, or otherwise appropriated, and free from preemption or other claims or rights at the time the line of said road is definitely fixed and a plat thereof filed in the ofiico of the commissioner of the general land-office.” -1
It is urged by defendants that it sufficiently appears from their answer that at the time plaintiff’s road was definitely fixed a claim had attached to this land which excepted it from plaintiff’s grant. Plaintiff urges (1) that at the time of the location of this land as mining claims no claims conld attach to this land, because the same was at that time withdrawn from settlement or sale by virtue of section 6 of the act above referred to, as within 40 miles of the general route of its road as located in 1872; (2) that, considering there was this claim, it was not a valid claim, as it is.admitted it was for mineral purposes upon agricultural land. Several cases were cited by plaintiff in support of its first proposition, which I do not feel called upon to review, because I have found no railroad grants to other railroad companies which correspond in all particulars with that of plaintiff upon that point. The section of the act of congress in which is found plaintiff’s grant, which it is claimed withdraws this land entirely from market after the general route of plaintiff’s road was located, is as follows:
“The president of the United States shall cause the lands to be surveyed for forty miles in width on both sides of the entire line of said road after the*242 general route shall be fixed, and as fast as may be required by the construction of said railroad; and the odd sections of land hereby granted shall not be liable to sale or entry or pre-emption before or after they are surveyed, except by said company, as provided in this act.”
The provisions corresponding to this in the act granting to the Union Pacific Railroad Company their land is found in section 7 of that act, and is as follows:
“That within two years after the passage of this act said company shall designate the general route of said road as near as may be, and shall file a map of the same in the department of the interior, whereupon the secretary of the interior shall cause the land within fifteen miles of said designated route to be withdrawn from pre-emption, private entry, and sale; and when any portion of said route shall'be finally located the secretary of the interior shall cause the said lands hereinbefore granted to be surveyed, and set off as fast as may be necessary for the purposes herein named.” See 12 St. U. S. 493.
This act was so amended as to make “fifteen” in this section read “twenty.” 13 Id. 358. It will be seen by an examination of this section as amended that all lands, whether odd or even numbered sections, for 20 miles • on each side of the general route of said company’s road, are withdrawn from pre-emption, private entry, and sale at the time of the fixing of the general route of that company’s railroad, without any reference as to whether they are granted lands or not. The Central Pacific Railroad Company’s grant is the same as the Union Pacific Railroad Company’s, and subject to the same limitations. There is no doubt about the provisions of the Union Pacific Railroad and Central Pacific Railroad act requiring all lands, whether granted or not, to be withdrawn at the time the general route of the road is fixed within the limits of its grant. The act making the land grant to the Atlantic & Pacific Railroad Company, which is the same as the grant to the Southern Pacific Railroad Company, is also materially different from that of the act making plaintiff’s grant. The section in the act making the grant is the third, and is as follows:
“That there be and is hereby granted to the Atlantic & Pacific Railroad Company, its successors and assigns, for the purpose of aiding in the construction of said railroad and telegraph line to the Pacific coast, and to secure the safe and speedy transportation of the mails, troops, munitions of war, and public stores over the route of said line of railway and its branches, every alternate section of public land not mineral, designated by odd numbers,-to the amoutlt of twenty alternate sections per mile on each side of said railroad line as said company may adopt through the territories of the United States, And ten alternate sections of land per mile on each side of said railroad whenever it passes through any state, and whenever on the line thereof the United States have full title, not reserved, sold, granted, or otherwise appropriated, and free from pre-emption or other claims or rights, at the time the line of said road is designated by a plat thereof filed in t..e office of the commissioner of the general land-office.” 14 St. U. S. 294.
It will be seen by a comparison of this grant with that of plaintiff’s that in the former the grant takes effect when the line of the road is designated by the filing of the plat thereof in the office named; in the lat
“That the president of the United States shall cause the lands to be surveyed for forty miles in width on both sides of the entire line of said road after the general route shall be fixed, and as fast as may be required by the construction of said railroad, and the odd sections of land hereby granted shall not be liable to sale or entry or pre-emption before or after they are surveyed, except by said company, as provided by this act.”
If I understand the case of Railway Co. v. Orton, 32 Fed. Rep. 458, the position is that the filing a plat designating even the general route of that company’s road fixed the grant, and the law withdrawing the lands granted took effect. The decisions upon the construction of that grant, then, upon this point, — and certainly those that pertain to the Union and Central Pacific Railroad Companies, — do not apply in this case. They are not even analogous upon this point. Plaintiff, however, calls the attention of the court with a considerable confidence to the cases of Buttz v. Railroad Co., 119 U. S. 55, 7 Sup. Ct. Rep. 100, and Denny v. Dodson, 13 Sawy. 68, 32 Fed. Rep. 899, upon this point. It cannot be denied that there is language in both cases which supports plaintiff’s view; but in the first case, at least, the language used was not necessary to the decision of the question at issue. In the first case it appears from the statement of facts that one Peronto, under whom, I suppose, plaintiff Buttz claimed, settled upon the land in dispute on the 5th day of October, 1871, while the land was situate in the Indian country. The United States statutes prohibits any settlement upon land in the Indian country. Peronto was, then, a trespasser there. On either June 19, 1873, or June 22, 1874, the Indian title was extinguished by treaty with the United States, and Peronto was found upon the land at that time. But on the 26th day of May, 1873, some 25 days before, in any event, the Indian title was extinguished, the Northern Pacific Railroad Company filed with the commissioner of the general land-office a plat of the route of their road as definitely fixed across the country upon such a line as would include the land Peronto had settled upon within its grant. The court held that, notwithstanding this Indian title of occupancy, the grant to plaintiff took effect upon the filing of this plat. As the said Peronto or Buttz had no settlement which could be at all recognized in law, up to this time the grant of the railroad company was prior to any rights that either could claim. There could be no doubt but when that grant gained precision by the definite fixing of the route of plaintiff’s road the land in controversy in that case was withdrawn from sale or homestead rights, or any other rights that could attach to the same subsequent to that definite fixing of the line of plaintiff’s road — First, because it had
"When the general route is thus fixed in good faith, and information thereof given to the land department by filing a map thereof with the secretary of the interior, the law withdraws from sale or pre-emption the odd sections to the extent of forty miles on each-side.”
It will be seen here that he makes the withdrawal of the land from sale, etc., to depend upon the filing of the map of the general route with the secretary of the interior. The law does not authorize the filing of any such map in plaintiff’s grant. It does not say the withdrawal shall take effect upon the filing of any such map. In the act making the grant to the Union and .Central Pacific Railway Companies there is a provision for filing such a map, and the withdrawal of all the land from market within the limits of the grant to .these companies. The general language of the opinion would also indicate that it was the opinion of the court that section 6 of plaintiff’s grant would withdraw all odd sections of land from the market, whether mineral or not, or whether homestead or pre-emption claims had attached to the same or not prior to the designating this general route. That certainly was not contemplated. It would appear that the eminent jurist in writing that opinion had in mind more the bearing of the provisions of the act making grants to the Union Pacific and Central Pacific Railway Companies, with which he was undoubtedly very familiar, than the act making plaintiff’s grant, for he makes no difference hardly in the provisions of these two acts, except as to the extent of the grant, while upon this point, as I have shown, they are very dissimilar. I think this is a proper case in which to apply the rule expressed by Chief Justice Marshall as to the authority of a decision in the case of Cohens v. Virginia, 6 Wheat. 399. In that case, speaking for the supreme court, he said:
“It is a maxim not to be disregarded that general expressions in every opinion are to be taken in connection with the case in which these opinions are used. If they go beyond the case they may be respected, but ought not to control the judgment in a subsequent suit when the very point is presented for discussion. ” 1
See, also, Barney v. Railroad Co., 117 U. S. 228—231, 6 Sup. Ct. Rep. 654. I do not believe there .was any demand for aconstruction of sec
*247 “All grants of this description are construed against the grantee. Koth-ing passes but what is conveyed in clear and explicit language; and, as the rights here claimed are derived entirely from the act of congress, the donation stands on the same footing asa grant by the public to a private company, the terms of which must be plainly expressed in the statute, and, if not thus expressed, they cannot be implied.”
To the same effect are the cases of Rice v. Railroad Co., 1 Black, 360; Railroad Co. v. U. S., 92 U. S. 733. The reason of this rule is thus expressed in Gildart v. Gladstone, 11 East, 675:
“The reason of this rule is obvious. Parties seeking grants for private purposes usually draw the bills making them. If they do not make the language explicit and clear to pass everything that is intended to be passed, it is their own fault; while, on the other hand, such a construction has a tendency to prevent parties from inserting ambiguous language for the purpose of taking by ingenious interpretation and insinuation that which cannot be obtained by plain and express terms. ”
This language was quoted and approved by the supreme court in the case of Railroad Co. v. Litchfield, supra. If it is said this is a law, and we must be governed by the intention of the law-making power, the answer is that in construing such a law the intention should be formed from the terms used and the subject-matter under consideration, and it should be recognized that it makes a grant of land. In the case of Railroad Co. v. U. S., supra, the supreme court, in speaking of a land grant made in 1863 (the year before the plaintiff's grant) to the state of Kansas, said:
“Formerly lands which would probably be affected by a grant were, as soon as it was made, if not in advance of it, withdrawn from market. But experience proved that this practice retarded settlement of the country, and at the date of this act the rule was not to withdraw them until the road should be actually located. In this way the ordinary working of the land system was not disturbed. Private entries, pre-emption, and homestead settlements, and reservations for special uses, continued within the supposed limits of the grant the same as if it had not been made: but they ceased when the routes of the roads were definitely fixed.”
We learn from this the state of mind congress was in upon this subject. The great body of the country on the proposed route of plaintiff’s road at the time of the grant was Indian country, to which the Indian title of occupancy was not extinguished. But very few of the lands along this route had been surveyed. Yet most of the country was accessible. It could hardly have been contemplated that it would be 18 years after the grant was made before the fixed route of that road would be established in Montana. It was very uncertain from the nature of the bountry what would be the fixed route of that road. The determination of this fixed route would give precision to the grant made plaintiff, and furnish a data for determining what lands had been granted. Can it be supposed that congress intended, 10 years before the fixed route of plaintiff’s road was established, to withdraw the lands granted to plaintiff from market, and leave it to subsequent explorations and surveys to determine what would be the lands granted? Upon such lands, during the time of these explorations and surveys, homes might be established
“The land granted by congress was from its very character and surroundings uncertain in many respects until the thing was done which should remove that uncertainty and give precision to the grant. Wherever the road might go the grant was limited originally to five sections, and by the amendment of 1864 to ten sections, on each side of it within the limits of twenty miles. These were to be odd-numbered sections, so that the even-numbered did not pass by the grant; and these odd-numbered were to be those not sold, reserved, disposed of by the United States, and to which a pre-emption or homestead right had not attached at the time the line of said road is definitely fixed. When the line was fixed, — which we have already said was by the act of filing this map of definite location in the general land-office, — then the criterion was established by which the lands to which the road had a right were to be determined. Topographically this determined which were the ten odd sections on each side of that line where the surveys had been made. This filing the map of definite location furnished also the means of determining what lands had previously to that moment been sold, reserved, or otherwise disposed of by the United States, and to which a pre-emption or homestead claim had attached, for by examining the plat of this land in the office of the register and receiver or in the general land-office it could readily have been seen if any of the odd sections within ten miles of the line had been sold or disposed of or reserved or a homestead or pre-emption claim had attached to any of them. In regard to all such sections they were not granted. The express and unequivocal language of the statute is that the odd sections not in this condition are granted. The grant is limited by its clear meaning to the other odd sections, and not these.”
We have here a clear assertion that what lands are granted are only determined when the line of the road is definitely fixed. In quite a number of decisions by the supreme court it is said of such grants as the one under consideration they are in the nature of floats. When the route of the road is fixed which the law defines shall fix the grant then it takes precision, and attaches to certain specific lands. Schulenberg v. Harriman, 21 Wall. 60; Railroad Co. v. U. S., 92 U. S. 741; Railroad Co. v. Price Co., 133 U. S. 509, 10 Sup. Ct. Rep. 341. Can it be that congress intended to say in the act granting lands to plaintiff that, although it will not be known until plaintiff designates a fixed line for its road and files its map thereof in the office of the commissioner of the general land-office, what specific lands are granted to it, yet these lands
But let it be admitted that the land granted was withdrawn from market at the time of the filing of the plat of the general route of plaintiff’s road. Then the question arises what are the lands granted? The act does not say “every odd section within forty miles of such general route,” but “public lands not sold, reserved, or otherwise appropriated, and free from pre-emption or other claims or rights, at the time the route is definitely fixed, and a plat thereof filed in the office of the commissioner of the general land-office.” This brings us back to the same point as the construction contended for. The land granted must at this time be free from a claim, or it is not land granted. Hence I hold that the premises in dispute were subject to be entered upon and a claim inaugurated at any time before the definite line of plaintiff’s road was fixed and the plat thereof filed in the proper office.
The next question is as to whether the claim made upon these lands would avail if not a Viilid claim. The premises being agricultural, no valid claim of them for mining purposes could be made. The language for consideration here in the act making the grant to plaintiff is: “Shall be free from pre-emption or other claims or rights.” What, in effect, the court is asked to do in construing this clause is to insert before “claims” the word “valid,” so the clause would read “free from preemption or other valid claims or rights.” Can the court do this? In the case of Newhall v. Sanger, 92 U. S. 761, the supreme court was called upon to construe a statute of the United States in which the words “ lands claimed under any foreign grant or title” occurred. The position taken in that case was that the word “lawfully” should be placed before “claimed.” But the court said there is no authority to import a word into a statute in order to change its meaning. In the ease of Railroad Co. v. U. S., supra, the supreme court quoted with approval this language of Patterson, J., in Rex v. Burrell, 12 Adol. & E. 465:
“1 see the necessity of not importing into statutes words which are not found there. Such a mode of interpretation only gives occasion to endless difficulty. ”
And then said:
“ Courts have always treated the subject in the same way when asked to supply words in order to give a statute a particular meaning which it would not bear without them.”
“It is not conceivable that congress intended to place these parties as contestants for the land, with the right in each to require proof from the other of complete performance of its obligation. Least of all is it to be supposed1 that it was intended to raise up in antagonism to all actual settlers on the soil when it had invited to its occupation this great corporation with an intent to defeat their claims, and to come between them and the government as to the performance of their obligations. ”
I do not see why this language is not as applicable to" a party asserting a right to a mining claim as to one asserting a right to a homestead claim; and, if so, I might say it is inconceivable that congress intended to give to plaintiff the right to test the validity of every mining claim which existed within 40 miles of the line of its road at the time the same was definitely fixed. Under such circumstances, public policy would dictate that the terms of limitation in plaintiff’s grant should not be so modified as to permit such a condition of affairs. I think the facts presented show that the assertion of title by the parties' who located the ground in dispute as mineral land should be dignified with the appellation of a “claim.” I would not say that every assertion of title to land would be entitled to the term “claim.” Perhaps acts sufficient should accompany the assertion of title to entitle the claimant to a stand
Case-law data current through December 31, 2025. Source: CourtListener bulk data.