Northern Pac. R. v. De Lacy
Opinion of the Court
The Northern Pacific Railroad Company brings ejectment to recover the possession of 160 acres of land in section 21, township 20 N., range 3 E. of the Willamette Meridian, in the state of Washington. The plaintiff claims title by virtue of the act of congress of July 2, 1864, incorporating the Northern Pacific Railroad Company, and authorizing it to construct and maintain a railroad from a point on Lake Superior westerly, on a line north of the forty-fifth degree of latitude, to some point on Puget Sound, with a branch, via the valley of the Columbia River, to a point at or near Portland, in the state of Oregon, leaving the main line at the most suitable place, not more than 300 miles from its western terminus; also, the joint resolution of May 31, 1870, authorizing the company to construct its main road to some point on Puget Sound, via the valley of the Columbia River, with the right to locate and construct its branch from some convenient point on its main trunk line, across the Cascade Mountains, to Puget Sound. The
The land in controversy lies within the primary limits of the land grant, both of the main line of the railroad, as definitely located between Portland and Puget Sound, and the line of the Cascade branch, as definitely located between the point where it leaves the main line, and crosses the Cascade Mountains to Puget Sound. It has been held that the grant of lands to aid the construction of that portion of the main line between Portland and Puget Sound dates from the joint resolution of May 31, 1870, and that prior to that time there was no land grant whatever in aid of the construction of that, portion of the road. U. S. v. Northern Pac. R. Co., 152 U. S. 284, 14 Sup. Ct. 598. And if the title in controversy in this suit were to be determined by the rights which the railroad company acquired under the joint resolution, only, the decision must be for the defendant; for it is clear that at and prior to the date of the joint resolution there was upon file in the local land office a valid and subsisting pre-emption entry upon the land in controversy, which entry, being unforfeited and uncanceled, operated to except the land from the grant. Railway Co. v. Dunmeyer, 113 U. S. 629, 5 Sup. Ct. 566; Bardon v. Railroad Co., 145 U. S. 535, 12 Sup. Ct. 856; Land Co. v. Griffey, 143 U. S. 32, 12 Sup. Ct. 362. But the land is, as already shown, also within the primary limits of the grant to aid the construction of the Cascade branch, and it remains to be considered how the rights of the respective parties are affected by that fact. The grant of July 2, 1864, gave land in aid of the construction of a railroad across the Cascade Mountains to Puget Sound. That grant was not intended to be abrogated by the joint resolution of May 31, 1870; and there is nothing in the opinion of the supreme court in U. S. v. Northern Pac. R. Co., supra, to the contrary. That decision goes no further than to hold that in the act of 1864 there was no land grant to aid the construction of a line between Portland and Puget Sound, and nothing to show that it was the intention of congress to connect those two points by a railroad. It must be held, there
It is contended that the Flett pre-emption entry in the land office constituted a pre-emption claim, which operated to bring the land within the exception contained in the grant, and that, therefore, the railroad company has no title upon which to recover. If there were no information before the court concerning the pre-emption claim, other than the entry in the land office, a different case would be presented ; but the defendant alleges in his answer an abandonment of this land by Flett in 1871, and a forfeiture of all his rights under the pre-emption entry. He produces before us also the record of a contest before the register and receiver of the local land office off the district in which this land is situated, which contest was carried by appeal to the secretary of the interior, and by him decided on the 28th day of November, 1891. From the record so offered, it appears that the plaintiff and defendant in this case, and John Flett, were parties, and appeared and presented the evidence of their respective rights. In that contest, as appears from the record, the evidence concerning Flett’s pre-emption settlement was fully submitted, and it was shown that in 1870 Flett had offered to prove up upon his claim before the officers of the local land office, and had been informed by them that the land was railroad land, and was not subject to his entry; that he made no appeal from that decision, and in consequence thereof abandoned his claim, and in 1874 made homestead entry on other lands. In consequence of the conclusion so reached by the secretary of the interior, a patent was issued from the government to the railroad company for the land on December 13, 1892. There are two periods to be regarded in determining whether the lands passed to the railroad company under its grant, — the date of the grant, and the date of the definite location of the road. If at either of these dates a claim attached, such as is mentioned in the exceptions to the granting act, the land which was subject to such claim was excluded; but if such a claim attached at a time between those dates, and was extinguished before the latter date, it would have no discernible effect upon the status of the title. Amacker v. Railroad Co., 7 C. C. A. 518, 58 Fed. 850. And this irrespective of whether or not
Case-law data current through December 31, 2025. Source: CourtListener bulk data.