Southern Pac. R. v. Smith
Opinion of the Court
The tracts of land in controversy in this suit having been patented to the defendant Smith under the pre-emption laws of the United States, and by him afterwards conveyed to the defendant Wolff, the complainant, claiming to be entitled to them by virtue of a congressional grant, brought this suit to obtain a decree that the title conveyed by the patent is held in trust for it, to compel the conveyance thereof to the complainant, and to enjoin the defendants from asserting any title to the lands. The grant under which the complainant claims is that of March 3,1871, entitled “An act to incorporate the Texas Pacific Railroad Company, and to aid in the construction of its road, and for other purposes” (16 Stat. p. 573), by which the complainant was authorized to construct a line of railroad from a point at or near Tehachipi Pass, by way of Los Angeles, to the Texas Pacific Railroad at or near the Colorado river, with the same rights, grants, and privileges, and subject to the same limitations, restrictions, and conditions, as were granted to the complainant by the preceding act of July 27, 1866, entitled “An act granting lands to aid in the construction of a railroad and telegraph line from the states of Missouri and Arkansas to the Pacific coast” (14 Stat. p. 292). The terms of the grant under which the complainant claims are, therefore, to be found in the act of July 27, 1866. So far as applicable to the present case, it was a grant of every alternate section of public land, not mineral, designated by odd numbers, to the amount of 10 alternate sections per mile on each side of the road thé complainant was authorized to build, to which the
The bill as amended, to which the defendants interposed a plea, which plea the complainant caused to be set down for argument, and which has been argued and submitted to the court for decision, alleges, among other things, that, on or before April 3, 1871, complainant fixed the general route of the entire line of railroad which it was authorized by the act of March 3,1871, to construct, and that, on April 3, 1871, the line of the road was designated on a plat thereof, filed on that day in the office of the commissioner of the general land office; that the said general route, plat, and designation of the line were duly approved and accepted by the; commissioner of the general land office and by the secretary of the interior, and, on April 21, 1871, the commissioner of the general land office, by direction of the secretary of the interior, dated April 19, 1871, withdrew the odd-numbered sections of land, within 30 miles of the railroad line shown upon the said plat, from sale or location, pre-emption, or homestead entry, which order of withdrawal has ever since continued in force and effect, except in so far as, if at all, the same may have been affected by an order of the secretary of the interior, dated August 15, 1887, directing the restoration of all land withdrawn and held for indemnity purposes under the grant to the complainant. The bill, as amended, further alleges that, on May 16,1871, complainant accepted the terms, conditions, and impositions of the act of March 3, 1871, and thereafter constructed and fully equipped the entire railroad provided for in the act in five several sections, along the route designated upon the plat filed April 3, 1871, and that, after the completion of the construction and equipment of the said sections, respectively, commissioners were duly appointed by the president to examine the same, who did so, and reported to the president the completion and equipment of the road in accordance with the requirements of the act, which report was accepted and approved by the secretary of the interior and by the president; that the section of the road opposite which the land in controversy is situated extends from Ban Fernando to Mojave, in respect to which section the report of the commissioners was made February 17, 1877, and was approved by the president March 2, 1877. The bill, as amended, further alleges that, on February 17, 1877, the complainant filed with the secretary of the interior a map of that portion of its road showing the definite location and construction thereof, which map was approved b,v the secretary of the interior March 6, 1877. The bill, as amended, also describes the
The plea denies that the map filed by the complainant in the department of the interior in the year 1871 was anything more than a map of the general route of the road it proposed to build under the authority of the act of March 3, 1871. It denies that the lands described in the bill as amended are situated within 30 miles of the line of the general route designated upon the map filed by the complainant in the department of the interior, and alleges that the said lands are situated more than 30 miles from that line. It alleges that on or about the-day of August, 1887, the secretary of the interior made and entered in his records an order revoking and annulling all orders previously made reserving lands within the indemnity limits of every grant made to the complainant railroad company, and restoring them to the public domain, except so far as they had theretofore been lawfully selected by complain
Prom the facts alleged, it appears that the lands in controversy are not within 30 miles of the general route of the road as located by the complainant, and as indicated on the map filed by it in the office of the commissioner of the general land office. They were not, therefore, withdrawn from pre-emption or sale, for the benefit of the complainant, either by the order of the secretary of the interior or by operation of the granting act itself. Nevertheless, the lands in controversy are within 30 miles of, but more than 20 miles from, the road as definitely located and constructed, and, if vacant and unappropriated, were subject to be taken as authorized by the law, to make good losses sustained by the complainant within the primary limits of its grant. Complainant attempted to select these lands, which are situated on the south side of its road, on October 3, 1887, in lieu of lands situated on the north side thereof within the primary limits of the grant, and which were lost to complainant, by including them in a list filed on that day in the proper local land office, in the form and accompanied by the certificates, affidavits, and fees required by law. This was prior to any attempt at settlement on, or entry of, the lands by the defendant Bmitli; his settlement, which was the basis of the patent subsequently issued to him, having been made December 7, 1887. Complainant commenced the present suit March 10, 1892, hut little more than four years after the inauguration of the adverse claim of the defendants.
The lands in controversy being within the indemnity limits of the complainant’s grant, and being, at the time of the complainant’s attempted selection of them, vacant and unappropriated, to which the United States had full title, and not falling within any of the exceptions to the grant, and the complainant having done all in its power to select them by filing in the proper office its claim to them in due form, accompanied by the affidavits and certificates re