Breyman v. Ann Arbor R.
Opinion of the Court
(after stating the facts). The motion in this case must he granted, to strike out so much of the plaintiffs’ petition as avers an overhaul beyond 600 feet of 55,066 cubic yards, and claiming compensation therefor at 1 cent per cubic yard for each and every 100 feet in excess of the 600 feet. This demand is made because of a printed clause of the specifications allowing such compensation to contractors, which was not stricken out, or otherwise canceled or modified, by the contract made between these parties, as were other parís of the printed form in use by the railroad company and its contractors. Outside of this disputed clause of the contract, 14 cents per cubic yard were to be paid, and the amount due under the allowance is $8,023.07, of which $5,292 have been paid, leaving a balance of $2,731.07, also sued for by this petition, to which, however, is added the claim for $18,274.65 for the overhaul beyond the 600 feet, making a total demand of $21,005.72 and interest as yet due.
The right to the $18,274.65 for the overhaul depends on a proper construction of the contract, and this motion is in the nature of a demurrer to the petition, which denies any such liability under (he contract that is pleaded. The printed form is that used by the railroad company on which to write its contracts with its contractors, and evidently intended to be adapted to each occasion on which it is used, according to its requirements. Possibly it is a fair inference, also, though it is not essential to determine this., that it is usually adapted to construction contracts that embrace longer distances than those involved in this contract to construct between the streets of a city or town, or within such a place, and its specifications would indicate
There can be no denial of the contention of the plaintiffs that the written clauses of this contract, specifying 14 cents per cubic yard as the price of this work, cannot override the printed clause of the specification allowing 1 cent per cubic yard for each 100 feet over the 600 specified as the ordinary working distance, unless there is an irreconcilable repugnance between them. This is' well settled by all the cases, and is a cardinal rule of construction of contracts, wills, and all other documents where repugnance is involved. It must be a fatal repugnance, in its irreconcilability, before any rule of construction is invoked, except the common one that all instruments must be construed according to their terms and tenor. Yet this quality of being reconciled does not depend wholly upon a mere harmony of phraseology, nor does the opposing quality of inconsistency or repugnancy depend on such mere verbal comparison or contrast when the two disputed terms are placed in juxtaposition or structural relation in the contract. If this were the rule, there is no repugnancy here, because there is nothing inconsistent between a stipulation to pay 14 cents generally, and one to pay that sum when the hauling is within 600 feet, and more when it is beyond that distance; and these two clauses, on their words, may stand.together, even when the hauling is within narrow limits, and the overhaul depends on an aggregation of minor distances actually traversed, as it may, within closely relate^ streets of a city. But all contracts are to be construed everywhere, not solely with reference to their words, but by the words as interpreted by the subject-matter and the object to be accomplished.
“It is understood that all material so handled in this district shall be put in place, as directed from time to time by the engineer in charge of the work, for and in consideration of fourteen cents per cubic yard.”
And, going hack to see what “so handled” may mean, we find that:
“They will take the material necessary for this work from any point which the engineer may designate, between Manhattan road and Lagrange street, on or adjacent to the line of railroad,” and “all borrow pits shall be left in such condition as to surface as the engineer in charge shall direct.”
It is this that is called “handling,” in contemplation of shorter distances than “hauling” would naturally imply.
Something is also claimed on ihe score of inconsistency because of a provision in the written part of the contract that the railroad company agrees to furnish free of charge to the contractors engines and supplies necessary, except help, to operate the locomotives for moving the' dump carts. Whether tills provision would indicate that the 14 cents was the full price for “hauling” beyond the 600 feet of .the printed clause is doubtful. It might he a part of the obligation of the railroad company at either or any price. Proof might make' it: plain that this was a special provision for the “hauling” or “overhauling,” hut it is not a necessary implication from the contract itself, and no importance is attached to it in this, judgment. But, taking the other consideration mentioned, and observing the form and appearance of the paper, partly written and partly printed, it seems a reasonable inference that the written parts embodied the agreement as to the price of the work, and the whole of it, and that the printed clause as to overhauls belongs ordinarily to a different class of work from this city work, like many of the other clauses of the specifications, and that in the process of striking out this clause was inadvertently, and not deliberately, left in the instrument. It is conceded by the court, however, that if this alleged repugnancy of the two clauses stood alone as the basis of this judgment, the rule of allowing written clauses to control printed clauses would he of doubtful application, at best. But, taking the fact that the narrow limitations of available territory, and the designation of the relatively close streets as the limits of the “haul,” is a specific designation of all the “haul” that can be, it is apparently a repugnancy to provide for' a generally indefinite distance that may or may not be more than 600 feet, and left intentionally open, as to that, to cover contingencies that may arise. It was certain here that the fillings had to he taken wiihin known and established distances, established by the contract, and named in it. Why, then, should there be any saving clause, which
There is,' however, another ground for this judgment, which, taken with that just considered, furnishes an altogether solid foundation for it. The case falls within Railroad Co. v. March, 114 U. S. 549, 5 Sup. Ct. 1035, and the large class of cases of which it is a type. • The language in that case, it is true, is stronger than in this, because there was a special provision that the estimate of the engineer should be ■final and conclusive, while in this contract there is no such provision that the court finds, and counsel do not point out any such clause. The twelfth clause provides that all differences or controversies which arise under or in reference to this agreement and specifications, or its performance and nonperformance, or the work to which they relate, or in any way whatever pertaining to or connected with said work, shall be referred to the general manager of the railroad company, and his decision shall be final and conclusive. Under this, this controversy might be finally determined by the general manager, but nothing appears to show that it has been, or that he has made any decision. There is no provision, as in the March Case, supra, that the estimates of the general manager shall be final and conclusive, but it amounts to the same thing; for, apart from all that, the absence of any such claim until now, and the fact that the “overhauls” have not been made in the monthly estimates that are provided for, is quite conclusive, as a practical construction of the parties to the contract, that the sole price was the 14 cents of the written contract, and aids the implication of repugnancy already made.
It is said in argument that this does not appear; but the absence of all averments in the petition .upon the subject is, as against the pleader, an implication that he has had no such estimates in his favor, and, in the view of the provision for a decision of all controversies by the general manager, that there was never any controversy until this suit was brought to be “referred” to him, whatever that may mean. This is a very strong1 evidence in the pleading itself that this overhaul claim is an afterthought, — that is, set up after the regular monthly estimates, in which the overhauling would from time to time occur, — and the magnitude of this claim of over $18,000 for overhauls would seem to preclude the idea of any overlooking or postponement of the demand, if it was understood by the parties to be part of the contract, until the final estimate of the engineers provided for by yet another clause of the contract. The plaintiff had a right to collect all but 10 per cent, as the work progressed, and of this $18,000, for overhauls done from day to day and month to month, over $16,000 could have been collected, from month to month, as accrued, if the parties had understood the contract to be as now set up; and, if it had been claimed from month to month, the claim would either have, been paid or provoked a controversy that the general manager would, have had jurisdiction to settle, or, at least, presumably, would have claimed to settle it, under this contract. All this is fair inference — •
Moreover, the rule of the March Case, supra, does not wholly depend upon the provision, found in that particular contract, that the estimate shall be final and conclusive. Not at all. It is just as final and conclusive if the contract only designates some person who is to certify the fact to be determined, unless the petition or pleading sets up fraud, some kind of bad faith, gross negligence, or mistake as an avoidance of the stipulation. In the two cases cited by Mr. Justice Harlan in the March Oase, there was no such provision as that the estimates should be final and conclusive, but only a designation of a person to make them, and a provision that payment should be made and title pass when the certificate is made, and the estimate or decision as to amount is fixed. Kihlberg v. U. S., 97 U. S. 398; Sweeney v. U. S., 109 U. S. 618, 3 Sup. Ct. 344. Here the stipulation is that the railroad company agrees to pay the contractor for “all work done, up to and including the last day of the preceding month, certified to by the party of the first part’s general manager to be in accordance with this contract.” This is quite as imperative and conclusive as the stipulation found in the other cases. Ten per cent, is to be retained until the final completion and acceptance of the work, and then “the percentage so retained, together with the balance due on the final estimate, shall be paid upon the certificate of the party of the first part’s general manager that the whole work provided for in this contract is completed and acceptably finished within the time specified.”
There is another provision, for the sole benefit, seemingly, of the railroad company, that the engineer, “in computing the final estimate, and giving his final certificate, need not be bound by the preceding estimates and certificates, but such preceding estimates and certificates shall be held to be only approximative to the final estimate, and the said monthly estimates and certificates on unfinished work shall in no case be taken as an acceptance of the work, or a release of the contractor from responsibility therefrom, until the final estimate is made, and the work in its entirety is accepted as complete under this contract.” Whatever benefit, if any, may inure to the contractor, under such a stipulation as this, for a revision of the estimates in his favor, and the correction of mistakes, surely he cannot claim that it keeps open a large and substantial part of the work, and, as appears by the figures here, an enormous relative proportion of the compensation for the whole, — $18,274.65 for “overhaul,” as compared with §8,023.07 for the other parts of the work actually done under the estimates, — until this final estimate, or that the contractor can withhold any demand by the month, and await the final estimate to set,up the claim for “overhaul.” He does not allege that he demánded an estimate from month to month of these overhauls, and that it was refused
Motion granted.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.