Burch v. Caden Stone Co.
Opinion of the Court
This action was begun in the state court, and was afterwards removed here by the defendants. The petition is in three paragraphs, though in the decision of the court upon the pending question the third paragraph need not be considered. The plaintiff, in substance, avers, in paragraph 1 of the petition, that he was, on the 22d of October, 189G, in the'employment of the Caden Stone Company, and was engaged in laboring for it; that while acting in the line of his duty as a servant of said company, and while acting under the orders of its agent and servant, Albert Caden, a derrick fell upon the plaintiff, and wounded and injured and caused him to sailer greatly, both mentally and physically, and impaired his ability to earn money, — all to his damage in the sum of $10,000. Further, ilia t said derrick fell and injured him, as a direct and natural result of the gross negligence of the servants of said company, who were running and operating its quarry, and who, with such gross negligence, had erected said derrick in such an unskillful and unworkmanlike manner as to greatly endanger the lives of all defendants’ employes near the same, and that, well knowing its dangerous condition, said company did erect and knowingly maintain the same, whereby plaintiff was injured as aforesaid. The second paragraph is in the following language:
“Plaintiff says, further, that said derrick was erected and maintained as set forth in the first paragraph of his petition, and at the time of his injury aforesaid, and prior thereto, Albert Caden was the agent and servant of said Caden Stone Company, and that he, with other agents and servants of said company, did assist in the erection and maintenance of said derrick, as set forth in the first paragraph of his petition, and that by his gross negligence, joined and concurring with the gross negligence of said company, all his injuries aforesaid were received, as the direct and natural consequence of said gross negligence. He sa.vs, further, that said Albert Caden was, at the time of his said injury, a stockholder, agent, and partner in the said Caden Stone Company. He says, further, that said Albert Caden is jointly and severally responsible to him for all his injuries aforesaid, and that by his gross negligence aforesaid this plaintiff has been damaged in the sum of $10,000.”
No suggestion has been made of a misjoinder, either of parties or of causes of action, but defendant Albert Caden has filed a general demurrer to the second paragraph of the petition, bringing up thereby the question of whether that paragraph states a cause of action against that defendant. Assuming its statements to be true (except that the word “partner” must be ignored), and giving to them
Case-law data current through December 31, 2025. Source: CourtListener bulk data.