Stanton v. Sturgis
Opinion of the Court
Upon the face of the complaint, the contract oh which this suit is brought was, in my opinion, void. The plaintiff, Stanton, entered into a contract with the Central Railway of West Virginia to construct its road, for which he was to be paid 15 per cent, upon the cost of construction.. On the same day he entered into another con
There is another ground upon which it seems to me that this complaint is demurrable. The contract between Stanton and the five directors, provided that:
“The contract entered Into this day between the Central Railway of West Virginia and said Stanton shall terminate and become null and void and óf no validity after July 1, 1900, unless substantial and satisfactory progress has been made in negotiating said bonds and stock and in putting the whole project in a reasonable state of certain success within that time, Unless the time be extended by mutual consent. It is understood between the parties hereto that the primary work of negotiating the sale of said bonds and stock shall devolve upon the party of the second part [Stanton, the plaintiff].”
The successful negotiation and sale of the bonds and stock provided for in the construction contract was the basis of the entire enterprise. If that did not take place, the road could not be built. By the above-quoted provisions Stanton had the primary work of negotiating such sale, and it was agreed that the construction contract should become null and void unless substantial progress had.been made in selling the securities before July 1, 1900. 'Stanton, being'charged by the contract with the primary work, knows whether such progress had been made. The complaint contains no allegation that it had been made. I think that, in order to recover in this action, such an allegation was necessary. In its absence the presumption is that the attempts to negotiate and sell the securities failed, and that therefore the construction contract became null and void as between the parties to this action.
My conclusion is that the demurrer should be sustained, with leave to the plaintiff to amend the complaint within 20 days upon payment of costs.