Brixey v. City of New York
Opinion of the Court
The verdict must be set aside and a new trial granted because of prejudicial error in the charge. The action was for damages sustained by the plaintiff by reason of the explosion ■of a large quantity of dynamite in one of the public streets of the city, of New York, which was kept there opposite the Murray Hill Hotel for use in the excavation of the subway. The plaintiff was a guest in that hotel, and was sitting in his room when the explosion occurred. There is no question that he was seriously and to some extent permanently injured. Under the act authorizing the construction of this public work, the contractor and subcontractor' prosecuting the work were authorized and had the right to do all things reasonably necessary to accomplish the purpose. In so doing they had the right to use certain designated portions of the public streets in all necessary ways. Things necessary to be done in these designated places, ordinarily nuisances, were not such under the circumstances and necessities of the case because of the legislative grant of authority. But these designated places in the public streets did not cease to be parts of "the streets, and they were so far under the control of the city authorities that it was their duty to look out for and abate obviously dangerous nuisances existing there if they had express or implied notice. The keeping and preparing for use of dynamite in the place in question in necessary quantities was not a nuisance if properly done, and its presence there was reasonably necessary for the proper prosecution of the work. But if its, presence there was not reasonably necessary, it became and was a nuisance, and it was the duty of the city to abate it if it had notice of its existence. A permit was granted for taking to and having at the 'place in question a specified amount of dynamite, but a much larger quantity was for a long time, and down to the happening of this event,
“Yes, that is true; but I also charge you that it was not a mine, and that it would not have been a violation of the labor law to have put this dynamite down there [meaning in the excavation].”
Defendant’s counsel excepted. The court immediately added:
“But I do charge that if this city, or its officials having charge of the matter, believed that the storing of dynamite down there [in the subway excavation] was a violation of the labor law, that then you may drop that question as to whether or not it was a nuisance to keep it above ground at all.”
The plaintiff’s counsel excepted. Clearly this was prejudicial error. There was no evidence whatever that the officials of the city believed any such thing, or acted on any such assumption or theory. Again, the belief of the city officials charged with the duty of abating nuisances had nothing to do with the questions at issue. Again, the statement was dangerously near an instruction that if the city officials held and acted on that belief, then the keeping and storing and handling of the dynamite in the street for a long time in an obviously dangerous manner did not constitute a nuisance for which the city would be liable in case of injury therefrom. This statement obscured the whole issue, and put the case on a false basis, and probably misled the jury.
The motion for a new trial must be granted.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.