Chapman Decorative Co. v. Security Mut. Life Ins.
Opinion of the Court
This is a suit on a building contract. It was tried in this court, and a verdict rendered April 16, 1906, in favor of the plaintiff for the sum of $18,495.06. A motion and reasons for a new trial were filed in due time by the plaintiff, which raised, as tersely stated by the plaintiff’s counsel, three main grounds or reasons why a new trial should be granted, viz.:
“(1) That at the outside the $50 a day clause should only have been enforceable until the date of substantial completion, and not until the date when the work was accepted by the defendant.”
The court was'requested by the plaintiff, in its first point submitted, to instruct the jury that in no event could liquidated damages of $50 a day be allowed to the defendant beyond the date when the work under the contract was substantially completed by the plaintiff. The court added “and accepted by defendant,” and in this shape affirmed the proposition, so that the jury were instructed that it was not only necessary to substantially complete the work, but that it was necessary that it should be accepted as substantially completed by the defendant. If we were to assume that the court was wrong in instructing the jury that it was necessary that the building should be accepted by the defendant after it had been substantially completed, the plaintiff was not injured by this instruction, for the reason that the plaintiff made no claim that the building was completed before the 23d day of August, the date upon which the plaintiff claims the defendant accepted the building, and this was the date fixed by the plaintiff’s secretary, Mr. Biddle; and considerable evidence, both direct and substantial, was offered to establish the fact that upon this date the acceptance occurred, and Mr. Biddle also testified, and was corroborated by other witnesses, that the building was completed on that date. At the argument, however, counsel for the plaintiff claimed that it was substantially completed on July 8th. There is no evidence in this case sufficient to support such a finding.
“(2) That the clause in article 11 constituted a penalty, and not liquidated damages.”
The clause is as follows:
“It is mutually agreed and understood that in the event of said interior finish herein contracted for not being entirely finished on or before the loth day of March, 3905, that the actual damages sustained by the owner will be difficult of computation; therefore it has been agreed, and hereby is agreed, by and between the parties hereto that in the event of the failure of said contractor to have all of said interior finish of main entrance and eighth floor completed on or before the 15th day of March, 1905, there shall be due and payable, and said contractor shall pay, to the said owner the just and full sum of $50 per day for each and every day after March 15, 1905, that the same or any part thereof remains unfinished and incomplete, and that said sum is hereby agreed upon as liquidated damages.”
This building of the defendant company was a large office building, and was being erected for its own use and for that purpose. At that time there was a large building, of the same kind and for similar purposes, being erected in this town by another company. The defendant had made contracts of rental with tenants, who were permitted to occupy the building without rent until it was finished. How many more prospective tenants deferred moving in because of the unfinished condition of the building and the number the defendant company lost by reason of the delay cannot be calculated; in other words, there was such a condition of affairs that it would “be difficult of computing” the damages, and the provision of this clause expressly stipulated that the sum of $50 should be liquidated damages. The jury were so instructed, and found that the delay was 161 days, for which they allowed a set-off at the rate of $50 per day against plaintiff’s claim. In this the court is convinced the instructions were proper, and the verdict of the jury right.
“(3) That, even if it is properly interpretable as liquidated damages, nevertheless, under the evidence, the delay was due, in part, at least, to the act of the defendant, and that therefore the clause falls, and the jury should only have been permitted to deduct such actual damages, if any, as the defendant could prove.”
New trial refused.