In re Helicopter Crash Near Marsh Island, Louisiana, on December 8, 1977
Opinion of the Court
OPINION AND ORDER
This litigation consists of eleven actions pending in three districts: nine in the Western District of Louisiana and one each in the Eastern District of Louisiana and the Eastern District of Texas.
The actions arose from a helicopter crash on an oil production platform near Marsh Island, Louisiana, in the Gulf of Mexico on December 8, 1977. Seventeen persons were killed and two persons were injured in the accident. Petroleum Helicopters, Inc. (PHI), the owner of the helicopter that crashed, is named as a defendant in all eleven actions. Mission Viking, Inc. (Mission), the operator of the platform on which the crash occurred, is a defendant in all actions except the Texas action.
PHI moves the Panel, pursuant to 28 U.S.C. § 1407, to transfer the actions pending in districts other than the Western District of Louisiana to that district for coordinated or consolidated pretrial proceedings with the actions pending there.
We find that these actions involve common questions of fact and that their transfer to the Western District of Louisiana under Section 1407 will best serve the convenience of the parties and witnesses and promote the just and efficient conduct of the litigation.
No party denies the existence of common questions of fact among these actions concerning the cause or causes of the accident and the liability of the various defendants. Transfer is thus necessary in order to prevent duplicative discovery, eliminate the possibility of conflicting pretrial rulings, and conserve the time and efforts of the parties and the judiciary. See In re Helicopter Crash in Germany on September 26, 1975, 443 F.Supp. 447, 449 (Jud.Pan.Mult. Lit. 1978).
The Texas plaintiff argues that pretrial proceedings in the Texas action are sufficiently advanced to warrant exclusion of the action from transfer under Section 1407. During oral argument before the
We agree that the Western District of Louisiana is the appropriate transferee forum for this litigation. Many witnesses and relevant documents will be found in that district at the business offices of PHI in Lafayette, Louisiana, and also elsewhere in the district because of its proximity to the accident. Furthermore, the vast majority of the actions before us are already pending in that district. See In re Air Crash Disaster in the Ionian Sea on September 8, 1974, 407 F.Supp. 238, 240 (Jud. Pan.Mult.Lit. 1974).
IT IS THEREFORE ORDERED that, pursuant to 28 U.S.C. § 1407, the actions listed on the following Schedule A and pending in districts other than the Western District of Louisiana be, and the same hereby are, transferred to the Western District of Louisiana and, with the consent of that court, assigned to the Honorable W. Eugene Davis for coordinated or consolidated pretrial proceedings with the actions listed on Schedule A and pending there.
SCHEDULE A
Western District of Louisiana
Karen H. Huval, et al. v. Petroleum Helicopters, Inc., et al. 78-0519
Teresa H. Leathem, et al. v. Petroleum Helicopters, Inc. et al. 78-0603
Madeline R. Dohmann, et al. v. Petroleum Helicopters, Inc., et al. 78-0501
Teresa B. Smith, et al. v. Petroleum Helicopters, Inc., et al. 78-0537
Michael A. Peschier v. Petroleum Helicopters, Inc., et al. CI78-0699
Arthurine Witherwax v. Petroleum Helicopters, Inc., et al. CI78-0689
Hussey Huval, etc. v. Petroleum Helicopters, Inc., et al. CI78-0520
Bonnie Stebbins Thibodeaux, etc., et al. v. Petroleum Helicopters, Inc., et al. CI78-0635
Janelle O. Gonzales v. Petroleum Helicopters, Inc., et al. CI78-0786
Eastern District of Louisiana
Lillie J. Anderson, et al. v. Petroleum Helicopters, Inc., et al. 78-1413-H(G)
Eastern District of Texas
Wilma J. Anderson, et al. v. Petroleum Helicopters, Inc., et al. M-78-2CA
. In five of these actions, Mission is sued sub nom. Mission Drilling and Exploration Co.
. PHI moved on September 15, 1978 to include in those proceedings three additional actions pending in the Western District of Louisiana. This motion was filed too late for these three actions to be considered with the other actions in this litigation at the Panel hearing held on this matter on September 29, 1978, because the other parties did not have adequate time to respond. See Rule 7(b), R.P.J.P.M.L., 78 F.R.D. 561, 566 (1978). Accordingly, these three actions were treated as potential tag-along actions. See Rule 10(d), id. at 568. Because of the Panel’s disposition herein, these three actions are already pending before the transferee court, and thus no further action regarding these actions is necessary by the Panel. See Rule 10(a), id.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.