Strong v. United States
Opinion of the Court
delivered the opinion of the Supreme-Court, February 11, 1878:
In this action upon a charter-party, executed March 15,1SG2. between Strong and the United States, for the use of his steamer Ocean Wave, he asks judgment for the amount he expended in repairing her after she had been discharged from the seivice of the Government, and also for per diem compensation, at the rate-fixed in the contract, for the time occupied in taking her from Port Royal, South Carolina, to New York, and in repairing her.
The Court of Claims Avas equally divided upon the question of his right to recover, and his petition was dismissed.
By the terms of the charter-party the G overnment avus entitled to the whole and exclusive use of the steamer during the term she was in its service. To the extent of her capacity, it was the duty of Strong to receive and transport all the “passengers”' and the “ stores, wares, and merchandise ” which the GoATernment might send to her. Her use was not limited to any particular waters, and as it was clearly within the contemplation of the contracting parties that she would be employed in aid of" the military forces then engaged in the war for the maintenance of the Union, sending her to the waters of North Carolina and' there employing her for the transportation of stores and men AAras clearly authorized by the charter-party. Munitions of war-AArere “stores” and soldiers “passengers,” Avithin the meaning of that instrument.
The only question which remains to be considered is that arising on the asserted liability of the Government for the per diem compensation for the time spent in taking the vessel from Port Royal and in repairing her in New York. The charter-party, it is true, expressly provided that she “was to be delivered to the owner in the port of New York, at the expiration of the charter, in as good condition” as she was at its date, “ordinary wear and tear, damage by the elements, bursting of boilers, breaking of machinery, excepted.” In view of this stipulation, was the Government, under the facts established, relieved from the duty of delivering her in New York % We think it was. By the terms of the charter-party-the owner was bound, at his own expense, to keep the vessel tight, stanch, strong, and sound, and her machinery, boilers, and everything pertaining to her in perfect working order, and to provide her with everything necessary for efficient séa-service. Any time which might be lost by reason of the machinery not being in order was to be deducted from the amount claimed to be due at the expiration of the charter. Now, it appears that on the 4th March, 1863, the vessel was out of order and condemned by the Government inspectors, and for those reasons was discharged at Port Royal from the service of the Government. It does not appear that this condemnation was improper or unjust. It is not pretended that she was at that time fit for efficient sea-service. The agreement of the Government to pay $200 per day for the use of the vessel was upon the condition — whether precedent or concurrent is immaterial — that the o wner would keep her in good order. His neglect of that duty, by reason of which she became unsafe and Avorthless for the purposes for which she had been hired, authorized the Government to abandon the contract and discharge her from its sendee. Its obligation to deliver her at
Judgment affirmed.