United States v. Joseph A. Holpuch Co.
United States v. Joseph A. Holpuch Co.
Opinion of the Court
delivered the opinion of the Court.
The narrow question here is whether a contractor’s failure to exhaust the administrative appeal provisions of a government construction contract bars him from bringing suit in the Court of Claims to recover damages.
Respondent, a building contractor, entered into two contracts
Article 15, which appeared in both contracts, provided: “All labor issues arising under this contract which cannot be satisfactorily adjusted by the contracting officer shall be submitted to the Board of Labor Review. Except as otherwise specifically provided in this contract, all other disputes concerning questions arising under this contract shall be decided by the contracting officer or his duly authorized representative, subject to written appeal by the contractor, within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto as to such questions. In the meantime the contractor shall diligently proceed with the work as directed.”
The dispute concerning the footing excavations arose out of an apparent inconsistency between certain figures used in the specifications and in the drawings. The specifications estimated that respondent was to excavate to a depth of 37% feet below the first-floor level of the buildings. The drawings, on the other hand, were found by the Court of Claims to call for excavations to the depth of 33 feet. Additional payments were to be made to respondent for excavations deeper than indicated “on the drawings,” while the Government was to receive a credit for excavations of a lesser depth. Respondent made vari
Article 2 of the contracts provided: “In case of difference between drawings and specifications, the specifications shall govern. In any case of discrepancy in the figures or drawings, the matter shall be immediately submitted to the contracting officer . . The specifications contained a similar provision and added that the constructing quartermaster was to be the interpreter of the “intent and meaning of the drawings and specifications.” The constructing quartermaster duly resolved the discrepancy in this instance by interpreting the specifications and drawings to mean that the footing excavations were to be paid for on the basis of the 37% feet estimated in the specifications. Respondent made no attempt to appeal from this decision to the contracting officer or to the departmental head in accordance with the terms of Article 15.
The other dispute concerned a required increase in wages for respondent’s bricklayers. The contracts established $1.00 per hour as the minimum wage rate for skilled labor unless, as of April 30, 1933, there should be a higher prevailing hourly rate prescribed by collective agreements between employers and employees. Article 18 (e) provided that this minimum wage rate “shall be subject to change by the Federal Emergency Administration of Public Works on recommendation of the Board of Labor Review,” in which case “the contract price shall be adjusted accordingly.” On March 3, 1934, the Board of Labor Review ruled that bricklayers on another Army construction project at San Antonio, Texas, with which respond
We cannot sanction respondent’s failure to abide by the appeal provisions of Article 15 of the contracts which it made with the United States. Both the dispute over the
But Article 15 is something more than a dead letter to be revived only at the convenience or discretion of the contractor. It is a clear, unambiguous provision applicable at all times and binding on all parties to the contract. No court is justified in disregarding its letter or spirit. Article 15 is controlling as to all disputes “concerning questions arising under this contract” unless otherwise specified in the contract. It creates a mechanism whereby adjustments may be made and errors corrected on an administrative level, thereby permitting the Government to mitigate or avoid large damage claims that might otherwise be created. United States v. Blair, 321 U. S. 730, 735. This mechanism, moreover, is exclusive in nature. Solely through its operation may claims be made and adjudicated
It follows that when a contractor chooses without due cause to ignore the provisions of Article 15 he destroys his right to sue for damages in the Court of Claims. That court is then obliged to outlaw his claims, whatever may be their equity. To do otherwise is to rewrite the contract.
In this instance no justifiable excuse is apparent for respondent’s failure to exhaust the appeal provisions of Article 15. Certainly the reasons relied upon by the Court of Claims are lacking in merit. The court felt that the dispute over the footing excavation figures involved only a matter of contract price computation and that the responsibility for such a computation rested solely with the Army Finance Officer at Fort Sam Houston, any decision by the contracting officer on the matter being no more than advisory. Since the contracts made no provision for an appeal of the Finance Officer’s computation, the Court of Claims held that there was no appealable decision confronting respondent and that respondent’s claim could be heard and determined by that court. Support for this novel interpretation was sought in the statement on the covers of the contracts that payment on the contracts was to be made “by the Finance Officer, U. S. Army, Fort Sam Houston, Texas.” The short answer is that this designation of a disbursing officer is not a part of the contracts and cannot be used in any way to alter or amend any actual provisions thereof. The designation only identifies the person whose duty it is to perform the ministerial
Respondent having failed to avail itself of the procedure created by Article 15 for the settlement of disputes arising under the contracts, it was precluded from bringing suit on such matters in the Court of Claims. And the Court of Claims erred in entertaining and deciding the claims involving those disputes.
Reversed.
The contracts here involved were both executed on U. S. Government Form No. P. W. A. 51.
The Court of Claims entered separate judgments and opinions in relation to each of the two contracts, although both of them were identical and involved the same issues. The only difference between the contracts concerned the particular buildings to be constructed.
The constructing quartermaster was in error in stating that respondent could have appealed the wage increase decision to the Board of Labor Review. Under Article 15, the Board is charged with handling appeals only on matters involving “labor issues.” This plainly means labor issues between' employers and employees. See Blair v. United, States, 99 Ct. Cls. 71, 149-150, reversed in other respects, 321 U. S. 730. Here, however, the only controversy lay between the respondent and the Government rather than between respondent and its bricklayers. Hence the ordinary review provisions of Article 15 were applicable, enabling respondent to appeal the contracting officer’s decision to the departmental head or his representative. The Court of Claims made a like error in this respect.
The Government points out that in 1933 and 1934 there were 18 Army Finance Officers located at various places in the United States and that all the notation on the cover could mean was that payment was to be made by the Finance Officer at Fort Sam Houston, Texas, and not by a Finance Officer located elsewhere.
Moreover, an affidavit by the Chief, Receipts and Disbursements Division, Office of the Fiscal Director, Army Service Forces, appearing as an appendix to the Government’s brief, states in regard to the notation: “This is merely an indication to the constructing quartermaster to which disbursing officer the constructing quartermaster should certify vouchers. The designation of the Finance Officer is not a term of the contract. It is part of an outline showing the parties, the amount, the site of the work, the services to be performed, and the authorized accounts to which payments will be charged. ... On a construction contract containing the above terms the disbursing officer would not in practice alter or modify and would not be authorized to alter or modify the decision of a certifying construction quartermaster as to the basis on which payments can be made under the contract when such basis, as here, is dependent upon an interpretation of the specifications or has been covered by a decision on a dispute by the contracting officer. . . . Another reason why the Finance Officer would not undertake to determine the question presented in this case is that finance officers as a rule have no experience with construction and would not be qualified to make such decisions.”
Such an assumption is faulty in that nearly every dispute between a contractor and the Government ultimately involves the amount of payment under the contract. Hence, under the view of the Court of Claims, all such disputes would be subject to the Finance Officer’s review, thereby nullifying Article 15 as well as other portions of the contract contemplating final decision by the contracting officer or the departmental head on these matters.
The Board of Labor Review, although a part of the Federal Emergency Administration of Public Works, is a distinct entity. And Article 18 (e) of the contracts made a clear functional distinction between the two in regard to wage rate increases. We are not free to disregard that distinction and rewrite the procedure established by Article 18 (e).
Dissenting Opinion
dissenting in part.
The Court requires this contractor to pay out of his own pocket the wage increase which he was directed to make. Whatever support that conclusion may have in a literal reading of the contract, it is so harsh and unfair as to be avoided if the contract does not compel the result. I do not think it does.
The contract set a minimum wage rate of $1 an hour for bricklayers. But it also provided that if the “prevailing” hourly rates under agreements between organized labor and employers on April 30, 1933, were above that minimum rate, the higher rate would become the minimum and be paid.
The Board of Labor Review, acting for the Federal Emergency Administration of Public Works,
So the respondent paid the extra wages under a ruling which, as I read the contract, was binding on him. It seems, therefore, manifestly unfair to hold that he must pay the wage increase out of his own pocket.
A contractor confronted with an order of the quartermaster to raise the wages of his employees is in an ex
There is justice in what the Court of Claims ruled and I would sustain it.
“In the event that the prevailing hourly rates prescribed under collective agreements or understandings between organized labor and employers on April 30, 1933, shall be above the minimum rates specified above, such agreed wage rates shall apply: Provided, That such agreed wage rates shall be effective for the period of this contract, but not to exceed 12 months from the date of the contract.”
“The minimum wage rates herein established shall be subject to change by the Federal Emergency Administration of Public Works on recommendation of the Board of Labor Review. In event that the Federal Emergency Administration of Public Works acting on such recommendation establishes different minimum wage rates, the contract price shall be adjusted accordingly on the basis of all actual labor costs on the project to the contractor, whether under this contract or any subcontract.”
The suggestion that the wage increase at San Antonio was not authorized by the Federal Emergency Administration of Public Works is not warranted by the record. The Board of Labor Review is a part of the Federal Emergency Administration of Public Works. It did not “recommend” an increase at San Antonio. It “formally ruled” that the bricklayers on that project “should be paid at the rate of $1.25 per hour.” The Court of Claims treated that as action by the Federal Emergency Administration of Public Works. That seems to me to be the fair construction; and it was so treated both by the quartermaster and the contractor.
The Government concedes that the quartermaster’s advice to respondent that he could file an appeal with the Board of Labor Review was erroneous. It points out that the Board of Labor Review was charged with the decision only of “labor issues,” which embrace controversies between employers and employees. The confusion existing in the mind of the Government’s own representative emphasizes the trap set for this contractor whether he followed the quartermaster’s suggestion or acquiesced in his ruling.