F. D. Rich Co. v. United States Ex Rel. Industrial Lumber Co.
F. D. Rich Co. v. United States Ex Rel. Industrial Lumber Co.
Opinion of the Court
delivered the opinion of the Court.
The Miller Act, 49 Stat. 793, as amended, 80 Stat. 1139, 40 U. S. C. § 270a et seq., requires a Government contractor
I
Between 1961 and 1968, petitioner F. D. Rich Co. was the prime contractor on numerous federal housing projects. During the years 1963-1966, much if not all of the plywood and millwork for these projects was supplied by Cerpac Co. The Cerpac organization was closely intertwined with Rich. The principals of Rich held a substantial voting interest in Cerpac stock, supplied a major share of its working capital, and were thoroughly familiar with its operations and financial condition.
On October 18, 1965, Rich contracted with the United States to build 337 family housing units at Beale Air
On February 22, 1966, Cerpac placed a single order with respondent Industrial Lumber Co. for all exterior plywood required under its plywood contract for the Beale project. Industrial is a broker, purchasing wood products and materials for resale. It acknowledged the complete Cerpac order, purchased the plywood from its own suppliers and arranged for deliveries at the Beale site to begin on March 10, 1966. Each shipment was receipted as it arrived on the site by a Rich representative.
Shortly after Industrial’s shipments began, Rich informed Cerpac that more plywood was needed for another Government project being constructed in Charleston, South Carolina, for which Cerpac had also contracted to supply Rich with all exterior plywood. Rich and Cer-pac decided to divert some of the Beale lumber to Charleston. Accordingly, Industrial was advised to supply, a shipment of the plywood called for under its Beale contract with Cerpac to the South Carolina site. Industrial arranged for the wood to be shipped by one of its suppliers to a railhead near Charleston. The shipment diverted to South Carolina was one of 22 called for by Industrial’s Beale Contract.
Both Rich and Industrial appealed. The Court of Appeals affirmed the judgment against Rich in large part.
II
Section 270a (a) (2) of the Miller Act establishes the general requirement of a payment bond to protect those who supply labor or materials to a contractor on a federal
The rights afforded by the Act are limited, however, by the proviso of § 270b (a). In MacEvoy Co. v. United States ex rel. Tomkins Co., supra, this Court construed § 270b (a) to limit the protection of a Miller Act bond to those who had a contractual agreement with the prime contractor or with a “subcontractor.” Those in more remote relationships, including persons supplying labor or material to a mere materialman, were found not to be protected. 322 U. S., at 109-111. Industrial was a supplier of materials to Cerpac. Thus, if Cerpac were a subcontractor for purposes of the Act, Industrial, having given the required statutory notice, could assert a Miller Act claim against Rich, the prime contractor. But, if Cerpac were merely a materialman, Industrial could not assert its Miller Act claim since it would be merely a supplier of materials to a materialman, a relationship found too remote in MacEvoy to enjoy the protections of the Act.
Petitioners assert that the courts below erred in finding Cerpac a subcontractor. Cerpac’s role under the plywood contract alone was that of a broker receiving standard lumber supplied by Industrial and, in turn, supplying it without modification to Rich. Petitioners argue that the court should not have looked beyond the plywood contract to determine Cerpac’s status under the Act.
“The relatively few subcontractors who perform part of the original contract represent in a sense the prime contractor and are well known to him. It is easy for the prime contractor to secure himself against loss by requiring the subcontractors to give security by bond, or otherwise, for the payment of those who contract directly with the subcontractors. . . . But this method of protection is generally inadequate to cope with remote and undeterminable liabilities incurred by an ordinary materialman, who may be a manufacturer, a wholesaler or-a retailer.” Id., at ,110. (Emphasis added.)
The Court of Appeals properly construed our holding in MacEvoy to establish as a test for whether one is a subcontractor, the substantiality and importance of his relationship with the prime contractor.
Measured against that test, Cerpac was clearly a subcontractor for the purposes of the Act. The Miller Act is “highly remedial [and] entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects.” MacEvoy, supra, at 107. It is consistent with that intent to look at the total relationship between Cerpac and Rich, not just the contract to supply exterior plywood, to determine whether Cerpac was a subcontractor.
Ill
We also agree with the courts below that venue under the Miller Act for suit on the shipment diverted to South Carolina properly lay in the Eastern District of California. The Act provides:
“Every suit instituted under this section shall be brought in . . . the United States District Court for*125 any district in which the contract was to be performed and executed and not elsewhere . . . .” 40 U.S.C. §270b (b).
Petitioners argue that this provision bars a district court in California
IV
We turn now to the question of whether attorneys’ fees were properly awarded respondent as a successful Miller Act plaintiff. The so-called “American Rule” governing the award of attorneys’ fees in litigation in the federal courts is that attorneys’ fees “are not ordinarily recoverable in the absence of a statute or enforceable contract providing therefor.” Fleischmann Distilling Corp. v. Maier Brewing Co., 386 U. S. 714, 717 (1967). There was no contractual provision concerning attorneys’ fees in this case. Nor does the Miller Act explicitly provide for an award of attorneys’ fees to a successful plaintiff. But the Court of Appeals construed the Act to require an award of attorneys’ fees where the “public policy” of the State in which suit was brought allows for the award of fees in similar contexts. The court reasoned that the Act provides remedies “ ‘in lieu of the lien upon land and buildings customary where property is owned by private persons’ .... The federal remedy was intended to substitute for the unavailable state remedy of the lien. Therefore, if state [law] allows a supplier on private projects to recover such fees, there is no reason for a different rule to apply to federal projects . . . .”
We think the Court of Appeals erred in its construction of the statute. The Miller Act provides a federal cause of action, and the scope of the remedy as well as the substance of the rights created thereby is a matter of federal not state law. Neither respondent nor the court below offers any evidence of congressional intent to incorporate state law to govern such an important element of Miller Act litigation as liability for attorneys’ fees. Many federal contracts involve construction in more than one State, and often, as here, the parties to Miller Act litigation have little or no contact, other than the contract itself, with the State in which the federal project is located. The reasonable expectations of such potential litigants are better served by a rule of uniform national application.
A uniform rule also avoids many of the pitfalls which have already manifested themselves in using state law referents. For example, California law does not provide for awards of attorneys’ fees in suits arising from private construction projects. And, a California court had held that the state statute providing for awards of attorneys’ fees in suits on the bonds of state and municipal.public works contractors is inapplicable to construction projects of the United States.
Finally, the Court of Appeals intimates that in providing that Miller Act claimants should recover the “sums justly due,” 40 TJ. S. C. § 270b (a), Congress must have intended to provide for the award of attorneys’ fees because without such fee shifting, Miller Act claimants would not be fully compensated — the claimant’s recovery would always be diminished by the cost of his legal representation. This argument merely restates one of the oft-repeated criticisms of the American Rule.
The American Rule has not served, however, as an absolute bar to the shifting of attorneys’ fees even in the absence of statute or contract. The federal judiciary has recognized several exceptions to the general principle that each party should bear the costs of its own legal representation. We have long recognized that attorneys’ fees may be awarded to a successful party when his opponent has acted in bad faith, vexatiously, wantonly, or for oppressive reasons,
Miller Act suits are plain and simple commercial litigation. In effect then, we are being asked to go the last mile in this case, to judicially obviate the American Rule in the context of everyday commercial litigation, where
The judgment of the Court of Appeals is affirmed insofar as it holds that Cerpac is a subcontractor for Miller Act purposes and that there was proper venue for suit on the shipment diverted to South Carolina, but reversed insofar as it holds that an award of attorneys’ fees to respondent Industrial is required by the Act.
It is so ordered.
Government contracts of less than $2,000 in value are excepted from the statute’s coverage.
Shipments under the contract were invoiced by the truckload. The South Carolina shipment involved two such truckloads, while the other 21 shipments were each of only one truckload of lumber.
When Cerpac fell behind in its payments, Industrial indicated it would not deliver the final two truckloads of wood to the Beale project until it received satisfactory assurances of payment. Rich agreed to pay Industrial directly for the last two shipments, with Cerpac to receive its customary profit as a commission from Industrial. The last two shipments were made on May 18 and June 23, 1966, invoices being payable in full 30 days thereafter. The shipments were invoiced directly to Rich with copies to Cerpac, the invoices showing the shipments as being under the original “Beale 647” contract between Industrial and Cerpac. Rich nonetheless refused to pay the full invoice price of the two final shipments. Rich has since conceded its obligation to pay Industrial’s claim for these two shipments, so there is no longer any controversy in regard to the amounts due on those invoices.
Cerpac subsequently filed for discharge in bankruptcy and is no longer a party.
All invoices under the Beale contract between Industrial and Cerpac were payable within 30 days with interest at an annual rate of eight percent after the due date. The District Court awarded Industrial seven percent interest on all “unliquidated claims.” The Court of Appeals, however, ruled that the amounts due under the terms of the contract were liquidated damages and should bear an interest rate of eight percent.
The District Court had also given judgment against Transamerica on its bond for the shipment which was sent to the South Carolina site. The Court of Appeals held that judgment should not have been rendered against Transamerica for material not delivered to the project for which it served as surety.
Petitioners also raise issues in their brief concerning the timeliness of the Miller Act notice and the amount of prejudgment interest awarded respondent. Those issues were not raised in the petition for certiorari, hence are not properly before the Court. See, e. g., Namet v. United States, 373 U. S. 179, 190 (1963); Rule 23.1 (c) of the Rules of this Court.
See, e. g., Aetna Casualty & Surety Co. v. United States ex rel. Gibson Steel Co., 382 F. 2d 615, 617 (CA5 1967); Basich Bros. Construction Co. v. United States ex rel. Turner, 159 F. 2d 182 (CA9 1946); cf. United States ex rel. Bryant v. Lembke Construction Co., 370 F. 2d 293 (CA10 1966).
Travelers Indemnity Co. v. United States ex rel. Western Steel Co., 362 F. 2d 896, 898 (CA9 1966); United States ex rel. Wellman Engineering Co. v. MSI Corp., 350 F. 2d 285, 286 (CA2 1965).
Beale Air Force Base is located in the jurisdiction of the Federal District Court for the Eastern District of California, hence respondent brought suit on the Beale contract in that court.
United States ex rel. Capolino Sons, Inc. v. Electronic & Missile Facilities, Inc., 364 F. 2d 705 (CA2 1966); see cases collected, id., at 707.
The Court of Appeals reversed the judgment against Trans-america, on its bond, as to the shipment of wood diverted to South Carolina, because a Miller Act surety is liable only for material supplied for use on the bonded project. But, a decision on the ultimate question of the surety’s liability involves different considerations from the questions of whether venue for suit on the bond is proper. Petitioner Rich’s liability for the amount due on the South Carolina shipment was based on a pendent claim, the substance of which was not challenged in this Court or in the Court of Appeals.
473 F. 2d 720, 727 (1973). The same analysis has been accepted in several other cases; see Transamerica Insurance Co. v. Red Top Metal, Inc., 384 F. 2d 752 (CA5 1967); United States ex rel. White Masonry, Inc. v. F. D. Rich Co., 434 F. 2d 855, 859 (CA9 1970); Arnold v. United States ex rel. Bowman Mechanical Contractors, Inc., 470 F. 2d 243, 245 (CA10 1972).
After the decision in the District Court, but prior to the Court of Appeals’ opinion, Cal. Govt. Code §4207 (1966) was replaced, and the effective provisions transferred to Cal. Civ. Code § 3250 (Supp. 1974), by an act of the California Legislature, dated August 31, 1969, that took effect on January 1, 1971. Given our reasoning, however, the revision in language of the applicable California law is of no relevance to the result reached herein.
B. C. Richter Contracting Co. v. Continental Casualty Co., 230 Cal. App. 2d 491, 41 Cal. Rptr. 98 (1964) (construing the former law, see n. 13, supra).
The American Rule has come under repeated criticism over the years. See generally Ehrenzweig, Reimbursement of Counsel Fees and the Great Society, 54 Calif. L. Rev. 792 (1966); Kuenzel, The Attorney’s Fee: Why Not a Cost of Litigation?, 49 Iowa L. Rev. 75 (1963); McLaughlin, The Recovery of Attorney’s Fees: A New Method of Financing Legal Services, 40 Ford. L. Rev. 761 (1972) ; McCormick, Counsel Fees and Other Expenses of Litigation as an Element of Damages, 15 Minn. L. Rev. 619 (1931); Stoebuek, Counsel Fees Included in Costs: A Logical Development, 38 U. Colo. L. Rev. 202 (1966); Note, Attorney’s Fees: Where Shall the Ultimate Burden Lie?, 20 Vand. L. Rev. 1216 (1967).
Judicial Council of Massachusetts, First Report, 11 Mass. L. Q. 1, 64 (1925).
See, e. g., Vaughan v. Atkinson, 369 U. S. 527 (1962); McEnteggart v. Cataldo, 451 F. 2d 1109 (CA1 1971); Bell v. School Bd. of Powhatan County, 321 F. 2d 494 (CA4 1963); Rolax v. Atlantic Coast Line R. Co., 186 F. 2d 473 (CA4 1951); 6 J. Moore, Federal Practice ¶ 54.77 [2], p. 1709 (2d ed. 1974).
See, e. g., Hall v. Cole, 412 U. S. 1 (1973); Mills v. Electric Auto-Lite Co., 396 U. S. 375 (1970); Natural Resources Defense Council v. EPA, 484 F. 2d 1331 (CA1 1973); Callahan v. Wallace, 466 F. 2d 59 (CA5 1972); Bright v. Philadelphia-Baltimore-Washington Stock Exchange, 327 F. Supp. 495, 506 (ED Pa. 1971); cf. Nussbaum, Attorney’s Fees in Public Interest Litigation, 48 N. Y. U. L. Rev. 301 (1973); Comment, The Allocation of Attorney’s Fees After Mills v. Electric Auto-Lite Co., 38 U. Chi. L. Rev. 316 (1971).
See, e. g., Cooper v. Allen, 467 F. 2d 836 (CA5 1972); Knight v. Auciello, 453 F. 2d 852 (CA1 1972); Lee v. Southern Home Sites Corp., 444 F. 2d 143 (CA5 1971); La Raza Unida v. Volpe, 57 F. R. D. 94 (ND Cal. 1972); Ross v. Goshi, 351 F. Supp. 949 (Haw. 1972); Sims v. Amos, 340 F. Supp. 691 (MD Ala. 1972); cf. Bradley v. School Bd. of the City of Richmond, 416 U. S. 696 (1974); Northcross v. Memphis Bd. of Education, 412 U. S. 427 (1973); Newman v. Piggie Park Enterprises, Inc., 390 U. S. 400 (1968); Nussbaum, n. 18, supra; Note, Awarding Attorneys’ Fees to the “Private Attorney General”: Judicial Green Light to Private Litigation in the Public Interest, 24 Hastings L. J. 733 (1973).
A congressional committee charged with making a broad-based inquiry about legal services is currently studying, inter alia, the general issue of attorneys’ fees. Hearings on Legal Fees before the Subcommittee on Representation of Citizen Interests of the Senate Committee on the Judiciary, 93d Cong., 1st Sess. (1973); cf. S. Rep. No. 93-146 (1973), accompanying S. Res. 101.
Dissenting Opinion
dissenting in part.
The Court, dealing with the Miller Act’s predecessor, held in Illinois Surety Co. v. John Davis Co., 244 U. S. 376, 380, that the Heard Act “must be construed liberally.” That same principle applies to the Miller Act. Fleisher Co. v. United States ex rel. Hallenbeck, 311 U. S. 15, 17-18. The Act is silent as to attorneys’ fees, saying only that the payment bond shall allow the supplier “to prosecute said action to final execution and judgment for the sum or sums justly due him.” 40 U. S. C. § 270b (a).
The Court says that dependence on state law is inappropriate, for we deal with a federal standard that should be uniform. That takes great liberties with the Miller Act. Here the contract and law were made in California and were to be performed there. In Illinois Surety Co. v. John Davis Co., supra, the contract and law were made in Illinois and were to be performed there. “Questions of liability for interest must therefore be determined by the law of that State,” said Mr. Justice Brandéis speaking for the Court, 244 U. S., at 381. If state law would give the claimant interest, it should give him attorneys’ fees based on the purpose of the Miller Act. Judge Carter writing for the Court of Appeals pointed out that the Miller Act is the federal equivalent of state lien laws. See 473 F. 2d 720, 727. The remedy in a federal suit is therefore properly composed of the same elements as would be available to lien claimants in a state court collecting for labor and materials furnished on nonfederal projects. One of the elements of recovery permitted in a California court is attorneys' fees. The “sum or sums justly due” should as a matter of federal law be construed to be the same as that -due a claimant whose remedy is based on a state statute, when the federal remedy was intended to be the equivalent of the state remedy.
The Court of Appeals for the Fifth Circuit awarded attorneys’ fees under a Florida statute where suit was brought under the Miller Act, United States ex rel. Weyerhaeuser Co. v. Bucon Construction Co., 430 F. 2d 420, 425. And see United States ex rel. White Masonry, Inc. v. F. D. Rich Co., 434 F. 2d 855, 859, where the Court of Appeals for the Ninth Circuit followed Alaska law.
Reference
- Full Case Name
- F. D. RICH CO., INC., Et Al. v. UNITED STATES for the Use of INDUSTRIAL LUMBER CO., INC.
- Cited By
- 1053 cases
- Status
- Published